Entry  Wednesday, June 19, 2019, 17:25, Fernando Maldonado, , , , , , , Done, Thermocouple connection 
Wednesday, June 19, 2019, 17:13  Ferran and Fernando tested the 9-pin connector to have a reading on a thermocouple following the connections used
by Aurelia (see elog 721).
Wednesday, June 19, 2019, 17:24: Test succesful!
Entry  Monday, June 24, 2019, 15:41, Fernando Maldonado, , , , , , , Problems/Solutions, TMS:Q3 polarity 
Monday, June 24, 2019, 15:25: Current quadrupole polarities:

    
        
             

           Top/Bottom
            North/South
        
    
    
Entry  Tuesday, June 25, 2019, 17:19, Fernando Maldonado, , , , , , , Problems/Solutions, Burnt cables on top of the test stand 20190625_154015.jpg20190625_153834.jpg20190625_165001.jpg
Tuesday, June 25, 2019, 16:15: While inspecting the 9-pin connection with Ferran, it was noticed how two braided cables were burnt out pretty bad to
the point they were separated in half (see attached pictures).  Additionally the plastic insulator for the anode wire was melted.
Tuesday, June 25, 2019, 16:30: Braided cables need to be changed and anode wire redone. 
Entry  Thursday, June 27, 2019, 09:51, Fernando Maldonado, , , , , , , Problems/Solutions, Melted cables changed 
See elog 737 

    
        
            Fernando
Entry  Tuesday, July 02, 2019, 18:25, Fernando Maldonado, , , , , , , Done, Blank on FEBIAD gas line installed 20190702_182254.jpg
 Tuesday, July 02, 2019, 18:24: A blind is installed  on the FEBIAD gas line (see attached picture)  to rule out the possibility
of  gases entering the TIS.
Entry  Thursday, July 04, 2019, 15:16, Aaron Schmidt, , , , , , , Problems/Solutions, TBHT insulator changed 
Thursday, July 04, 2019, 15:00: TBHT insulator was swapped out on the source tray side.  
The old one is very chipped.
Entry  Friday, July 19, 2019, 13:48, Fernando Maldonado, , , , , , , Problems/Solutions, RMP0A and FC6 gains signal redirection to another channel 
After submitting a fault report (FR - ISAC Fault 12461) a Work Permit was issued (WP - C2019-07-19-1),
Controls tunnel the faulty signal to another ADC by removing signal no longer used at the Test Stand.
Test successful with a constant current power supply in the range 1 nA-40 nA.
Entry  Wednesday, August 07, 2019, 15:19, Fernando Maldonado, , , , , , , Problems/Solutions, Test stand inspection 
Wednesday, August 07, 2019, 15:12:  Arthur helped inspected the electric connections on the TS.
One of the coil  positive waterlines  was touching a HS waterline. Manually adjusted them to have a  better clearance.
 
Entry  Thursday, August 08, 2019, 09:12, Aaron Schmidt, , LP-FEBIAD, , , , 42752-7, In progress, P2N Setup - LP-FEBIAD target 8x
Inserted a used (heating) LP-FEBIAD target with a basic heat shield assembly with no end plate foil on the window side to observe heating. The P2N Coil
/ TGHT connections were added.
Test whether the TS connections are affecting the P2N heating or if it's the P2N target itself.
Entry  Tuesday, August 13, 2019, 12:03, Aaron Schmidt, , , , , , , Problems/Solutions, Replace RP1 vac.PNGcurr.PNG
Tuesday, August 13, 2019, 11:55: Close PV1. Turn off RP1.
Tuesday, August 13, 2019, 12:02: RP1 replaced.
Tuesday, August 13, 2019, 13:24: TS exhaust / screen cleaned out.
Entry  Thursday, August 15, 2019, 16:33, Fernando Maldonado, , , , , , , Problems/Solutions, 9-pin connection modification 
Thursday, August 15, 2019, 16:17: Q FT undone to remove the connection to the 9-pin
The idea is to change the cables to have individual signals. This will allow 4 thermocouple readings.
NB: The FT is not vacuum tight as of now  (gasket needs to be replaced and flange needs to be tight)
Entry  Thursday, August 29, 2019, 14:47, Fernando Maldonado, , , , , , Ferran's heat shield, Problems/Solutions, Rewiring-Baking out 
Thursday, August 29, 2019, 14:47 : Changing back to the nominal wiring 
Thursday, August 29, 2019, 17:01: TIS changed to Ferran's heat shield. 
Thursday, August 29, 2019, 17:02: 9-pin FT redone.
Entry  Monday, September 16, 2019, 10:05, Fernando Maldonado, , , , , , , Problems/Solutions, Alignment pin reinstalled 20190916_095937.jpg
 Monday, September 16, 2019, 10:03: The rightmost alignment pin has been reinstalled (see picture attached). It was previously removed for Ferran's
test. 
Entry  Thursday, September 26, 2019, 11:30, Aaron Schmidt, , , , , , , Problems/Solutions, Replace CANBUS board TSG:CB1 
Thursday, September 26, 2019, 11:28: The control board to TSG:CB1 was removed and replaced.  
Thursday, September 26, 2019, 11:30: All optics & steering operational. Board replacement successful.
Entry  Friday, September 27, 2019, 11:54, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-6, , Conditioning UC#(29) HS 
Using broken LP-FEBIAD oven. TBHT off.
Friday, September 27, 2019, 11:53: Roughing.
Friday, September 27, 2019, 13:14: Turbo pumps on.
Entry  Wednesday, October 02, 2019, 13:42, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-9, In progress, Conditioning UC#(30) HS UC#30.docx
Wednesday, October 02, 2019, 13:42: Roughing.
Wednesday, October 02, 2019, 14:13: Turbo Pumps started.
Wednesday, October 02, 2019, 14:19: Ion gauge on.
Entry  Wednesday, October 23, 2019, 09:51, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak in Magnet PS 
Wednesday, October 23, 2019, 09:50:
Fault: 12797 
WP: C2019-10-23-2
Entry  Friday, October 25, 2019, 12:04, Anders Mjos, , , , , , , Problems/Solutions, ISG:TP1A found stopped  
Restarted TP. Note that CG1A is above 50 mTorr. CG1B shows 15 mTorr
Entry  Monday, October 28, 2019, 09:24, Fernando Maldonado, , , , , , , Problems/Solutions, TSG:CG1A checked with local reader 
Monday, October 28, 2019, 09:22: The local reader indicated 42 mTorr while EPICS showed 51mTorr.
CG1B showed 8.9mTorr while EPICS shows 14mTorr. 
After reconnecting CG1A, EPICS shows 16mTorr. Anthony suggest replacing the gauge.
Entry  Wednesday, October 30, 2019, 14:50, Fernando Maldonado, , , , , , , Problems/Solutions, Cathode bias mode configuration 
Wednesday, October 30, 2019, 14:49: John C. changed the polarity of the anode power supply to negative, and Fernando M. rewired the cabling on the service
cap.