  Test-Stand, Page 35 of 53  Not logged in ELOG logo
  ID Date Author Target/No.# Source Stationdown Module Target Oven W.O# Heat Shield W.O# Status Subject
  608   Tuesday, October 10, 2017, 13:10 Aaron Schmidt       Gas bottles

Tuesday, October 10, 2017, 09:30:  Install/swap gas bottles. Elog.

Removed smallest Neon leak. Neon Bottle Serial #11231. Leak rate calibrated @ 1.59e-07 atm*CC/sec (02/09/2016)

In use:

Neon Bottle Serial #09572. Leak rate calibrated @ 1.82e-06 atm*CC/sec (02/09/2016)

Argon Bottle Serial #09937. Leak rate calibrated @ 1.35 x10-6 Atm-CC/sec (08/06/2003)

Tuesday, October 10, 2017, 10:12: Gas bottles opened. Pump not on? Vacuum spiked into e-04T. All closed. Await vacuum stabilization.

Tuesday, October 10, 2017, 10:36: Power on. Pump on Gas bottles opened. Await vacuum stabilization.

pump off.

  609   Tuesday, October 10, 2017, 14:56 Aaron Schmidt      In progressFEBIAD Anode bias configuration

Unable to hold Anode voltage after power supply change out.

Tuesday, October 10, 2017, 14:55: The Test Stand has been configured for Anode bias and the electrical connections have been wired according to ISK4523D REV 6.

At this current point in time John Chow has removed the power supply (PS). Will update once polarity is switched (if required) and is re-installed to the test stand.


Wednesday, October 11, 2017, 10:25: Polarity was switched  and PS is installed on the test stand. Sources/power switched on.

  611   Monday, October 16, 2017, 11:46 Aaron Schmidt      In progressPump down empty chamber Test EE

Monday, October 16, 2017, 11:45: Roughing.

Monday, October 16, 2017, 12:05: Turbo pumps started.

Monday, October 16, 2017, 12:10; Ion gauge on.


Tuesday, October 17, 2017, 10:43: Waterlines opened. RGA not on. Vacuum ok @ 1.53e-07T. Power/sources on.

Tuesday, October 17, 2017, 10:45: RGA on.

Tuesday, October 17, 2017, 10:50: BIAS / EZL / EE @ 30 / 13 / 1.5 kV .

   

      

Tuesday, October 17, 2017, 14:44: EE Current Stable.

Tuesday, October 17, 2017, 14:52: Power/sources off.

Tuesday, October 17, 2017, 14:54: Waterlines purged.

 

 

  612   Tuesday, October 24, 2017, 11:38 Anders Mjos       FEBIAD coil magnetic field measurment

with Fernando

Tuesday, October 24, 2017: Testing setup with triple coil

Wednesday, October 25, 2017: Field mapping at 70 A and current/field measurements on triple coil.

Attachment 1: FEBIAD_Coil_Field_Measurement_2017-10-25.xlsx
Attachment 2: 171025-First-Run.xlsx
  613   Monday, October 30, 2017, 08:54 Anders Mjos      Problems/SolutionsTMS:TP6 shut down due to high noise

The turbo pump will need replacement.

  614   Wednesday, November 15, 2017, 10:56 Aaron Schmidt      Problems/SolutionsTMS:TP6 replacement

Turbo pump TP6 requires replacement.

Wednesday, November 15, 2017, 09:55: Turbo (TP2) off. Ion gauge off.

Wednesday, November 15, 2017, 10:55: Venting

  615   Friday, December 01, 2017, 14:31 Aaron Schmidt LP-SIS  (Blank)42752-3In progressSilver plated bolts test / Outgas TS

Chamber 'open state, no turbos' 2 weeks. Testing Silver plated 3/8"-16x1" (SCR, SHC, 18-8, AG) bolt on the TBHT.

Friday, December 01, 2017, 14:26: Roughing. BV1B open.

Friday, December 01, 2017, 14:27: BV1A open

Friday, December 01, 2017, 14:47: Turbo pumps on.

Friday, December 01, 2017, 14:53: Ion gauge on (Vacuum @ 1.44 e-04T)

Friday, December 01, 2017, 14:57: Turbos @ speed. RGA on.


Monday, December 04, 2017, 09:27: System rebooted after weekend power outage.


Tuesday, December 05, 2017, 08:10: RGA on.

Tuesday, December 05, 2017, 08:17: Waterlines opened. Vacuum ok @ 1.56e-06T

Tuesday, December 05, 2017, 08:20: Power on. (Power supplies in off position) Turn power off

Open back. switch power supplies to on.

Tuesday, December 05, 2017, 08:35: Power on

Tuesday, December 05, 2017, 08:37: Auto ramping TGHT / TBHT to 150 / 75 A @ 2A per min.

Tuesday, December 05, 2017, 09:55: Auto ramping TGHT / TBHT to 200 / 75 A @ 2A per min.

Tuesday, December 05, 2017, 10:28: Auto ramping TGHT / TBHT to 400 / 150 A @ 2A per min. Vacuum @ 1.56e-06T.

Tuesday, December 05, 2017, 12:50: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min. Vacuum @ 3.03e-06T.

Tuesday, December 05, 2017, 12:58: Auto ramping halted. Vacuum @ 3.12e-06T. Allow vacuum to improve.


Wednesday, December 06, 2017, 08:03: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min. Vacuum @ 2.65e-06T. Added note*** The Silver bolts are NOT vented ***.

Wednesday, December 06, 2017, 08:30: TGHT / TBHT @ 449 / 199 A. Vacuum @ 3.03e-06T and holding. Auto-ramping continued. No halt.

Wednesday, December 06, 2017, 10:45: Check. TGHT / TBHT @ 449 / 199 A. Vacuum @ 3.36e-06T and holding. Auto-ramping on wait.

Wednesday, December 06, 2017, 14:37: Check. TGHT / TBHT @ 449 / 199 A. Vacuum @ 3.21e-06T and holding. Auto-ramping halted. Allow Vacuum to improve.


Thursday, December 07, 2017, 07:52: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min. Vacuum @ 2.33e-06T.

Thursday, December 07, 2017, 09:00: Check. TGHT / TBHT @ 571 / 200 A. Vacuum @ 3.19e-06T. Auto-ramping halted. Allow Vacuum to improve.


Friday, December 08, 2017, 07:52: Auto ramping TGHT to 580 A from 571 A @ 2A per min. Vacuum @ 2.04e-06T.


Monday, December 11, 2017, 08:00: Auto cooling @ 2A per min.

Monday, December 11, 2017, 13:45: Sources/power off. Water cooling off.


Tuesday, December 12, 2017, 06:35: RGA, Ion gauge, turbo pumps off.

Tuesday, December 12, 2017, 07:45: Venting.

Tuesday, December 12, 2017, 08:23: Doors open.

Attachment 1: 1st_silver_bolts_test.docx
Attachment 2: TS-2017-12-05-08-10.rga
  616   Monday, December 04, 2017, 08:29 Aaron Schmidt      Problems/SolutionsPower outage

Power outage over the weekend. Reboot PLC and systems.

Monday, December 04, 2017, 08:22: Turbo pumps TMS:TP6 & TP2 Restarted.

Monday, December 04, 2017, 08:28: Time out on turbo pump TP1B.

Monday, December 04, 2017, 09:25: Turn off/restart TSG:TP1B Maincontrol.

Monday, December 04, 2017, 09:26: TMS:IG6 Restarted.

Monday, December 04, 2017, 14:24: Multi gauge controller to TSG:IG1 burned out. Replaced. Vacuum @ 4.45e-06T. Monitor.

Attachment 1: 20171205_103324.jpg
20171205_103324.jpg
  617   Tuesday, December 12, 2017, 08:32 Aaron Schmidt LP-SIS  (Blank)42752-3DonePump down w/ possible outgas

Check achievable vacuum. Watch for spikes on RGA. Silver bolts removed from the chamber. Vented steel screws in.

Tuesday, December 12, 2017, 08:23: Doors open from previous test. (Open for 7 minutes)

Tuesday, December 12, 2017, 08:30: Doors closed. Roughing.

Tuesday, December 12, 2017, 08:50: Turbo pumps on.

Tuesday, December 12, 2017, 08:56: Ion gauge on.


Wednesday, December 13, 2017, 06:46: Check. Vacuum @ 5.44e-07T. RGA Error.

Wednesday, December 13, 2017, 06:49: RGA restarted.

Wednesday, December 13, 2017, 06:52: Water lines opened. Vacuum @ 5.44e-07T

Wednesday, December 13, 2017, 06:54: Power on.

Wednesday, December 13, 2017, 06:56: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.


Friday, December 15, 2017, 13:37: Auto-cooling @ 2A per min


Monday, December 18, 2017, 08:15: Power/source off.


Wednesday, December 20, 2017, 09:07: RGA off.

Wednesday, December 20, 2017, 09:08: Both Ion gauges and all 4 turbo pumps off.

Attachment 1: Empty_Chamber_-_Silver_bolts_removed.docx
Attachment 2: TS-2017-12-12-09-00.rga
Attachment 3: TS-2017-12-13-06-50.rga
  618   Wednesday, December 20, 2017, 09:11 Aaron Schmidt LP-SIS  (Blank)42752-3DoneHoliday Shut Down

Power/sources already off. The water cooling is currently left on.

Wednesday, December 20, 2017, 09:07: RGA off.

Wednesday, December 20, 2017, 09:08: Both Ion gauges and all 4 turbo pumps off.

Wednesday, December 20, 2017, 11:21: Valves closed. Roughing pumps off.

Wednesday, December 20, 2017, 11:22: RGA shut off completely.

  619   Thursday, December 21, 2017, 15:12 Anders Mjos       Powered down devices

Powered down vacuum gauge and turbo pump controllers

  620   Tuesday, January 02, 2018, 09:18 Anders Mjos      Problems/SolutionsStarting system

Tuesday, January 02, 2018

Cycled power for TCSIOC and PLCIOC

TP2 and TP6 started

TP1B does not start. TP1B controller does not start up correctly - controller will have to be replaced. E-fault submitted (10739).

Controller for PS for Q1,6 was switching constantly. Unplugged and plugged back in resolved the problem

TP1A started


(Aaron Schmidt)

Wednesday, January 03, 2018, 08:15:  TSG:TP1B Still non-responsive.

Wednesday, January 03, 2018, 08:20: Power/sources on. Add Voltage/Amp and check power supplies.

BIAS - 300V Reads 290V - OK

EE - 300V Reads 298V - OK

EZL - 300V Reads 293 V - OK

CB1 - 10V Reads 10V - OK

VCB1 - 10V Reads 10V - OK

CBC (both)  - 10V Reads 9V - OK

TBHT - 10A Reads 9.9A (009 direct off PS) - OK

TGHT - 10A Reads 9.8A (007 direct off PS) - OK

Optics Check:

Magnet ok - Some optics start, some do not respond. Submit fault report for communications issues.

Fault Report submitted - 10742

 


Thursday, January 04, 2018, 14:38:

Kyle and Dave were able to get all the canbus optics for ISAC test stand re-configured except one device: TMS:Q2

"We investigated and it looks like the controller board for the TMS:Q2 supply is toast. Unfortunately these boards are a very old style so we don't have a surplus of replacements on hand. Our electronics shop did have some spares but the spares are not ready for use and need to have a few components soldered on. " - Kyle

The repaired controller board should be ready for next week.


Wednesday, January 10, 2018, 13:22: TS optics all fixed. Turbo pump TP1B is still out.

  621   Monday, January 22, 2018, 09:04 Aaron Schmidt      DonePower outage & Controller replacement.

Computer, TS, epics, restarted. Power checks

Monday, January 22, 2018, 09:00: ISAC PLC TLCIOC Restarted. 

Turbo pumps restarted.

Monday, January 22, 2018, 09:26: New controller for TSG:TP1B brought in.

(Connect) Global reset. Resart Turbo pumps.

Monday, January 22, 2018, 09:40: Both turbo pumps @ speed.

Vacuum controls ok

Sources ok

Optics -  Issues. Some restart, others do not.

 

  622   Friday, January 26, 2018, 11:10 Aaron Schmidt      DoneHelium tank replacement

Friday, January 26, 2018, 11:08: New Helium tank installed inside the Test Stand.

-The 'Full' tag remains. The He tank was not opened.

-The old tank was placed beside the Test Stand beneath/beside the power switch.

  623   Friday, January 26, 2018, 13:59 Aaron Schmidt LP-SIS  (Blank)42752-3DoneHV test 1

Friday, January 26, 2018, 14:00: BIAS/EZL/EE ramp up.

Friday, January 26, 2018, 14:06: BIAS/EZL/EE @ 30/13/1.5 kV.

Friday, January 26, 2018, 14:09: BIAS/EZL/EE @ 35/13/1.5 kV.

Spark at BIAS 30 kV and 40kV

Friday, January 26, 2018, 14:12: BIAS/EZL/EE @ 40/13/1.5 kV.

Friday, January 26, 2018, 14:15: BIAS/EZL/EE @ 45/13/1.5 kV.

Audible sparks, but none showing on the strip tool.

Friday, January 26, 2018, 14:19: BIAS/EZL/EE @ 45/19/1.5 kV.

Friday, January 26, 2018, 14:22: BIAS/EZL/EE @ 47/22/1.5 kV. Sparks @ 47000 to 47250 V.

Sparks observed on EE feed through in cage.

Friday, January 26, 2018, 14:27: BIAS/EZL/EE @ 50/22/1.7 kV.

Friday, January 26, 2018, 14:39: BIAS/EZL/EE @ 55/23.5/1.8 kV.

Bias controls 55 kV Actual @ 50 kV.

Friday, January 26, 2018, 14:44: Spark free 5 min.

Friday, January 26, 2018, 14:49: Spark free 10 min.

Attachment 1: 2018_HV_test_1.docx
  624   Monday, January 29, 2018, 10:07 Aaron Schmidt LP-SIS  (Blank)42752-3DonePower outage / HV test 2

HV test 2 cancelled.  9:38: BIAS/EZL/EE @ 30/13/1.5 kV

Monday, January 29, 2018, 09:40 (Roughly) Power went out completely

Monday, January 29, 2018, 10:00: Power up TS

Monday, January 29, 2018, 10:07:Turbos on.

Monday, January 29, 2018, 10:11: Ion gauge on Vacuum @ 3.3e-06T

Monday, January 29, 2018, 11:47; Power cycled. PLC and Canbus reset/cfg.

Monday, January 29, 2018, 11:54: Optics & Sources ok/reset.

 

Monday, January 29, 2018, 13:27: BIAS/EZL/EE @ 30 / 13 / 1.5 kV.

Monday, January 29, 2018, 13:30: BIAS/EZL/EE @ 40 / 17 / 2 kV.

Monday, January 29, 2018, 13:33: BIAS/EZL/EE @ 45 / 19.5 / 2.25 kV.

Monday, January 29, 2018, 13:36: BIAS/EZL/EE @ 50 / 21.5 / 2.5 kV.

Monday, January 29, 2018, 13:40: BIAS/EZL/EE @ 55 / 23.8 / 2.75 kV.

Monday, January 29, 2018, 13:43: BIAS/EZL/EE @ 60 / 26 / 3 kV.

SPARKS*

Monday, January 29, 2018, 13:48: BIAS/EZL/EE @ 55 / 23.8 / 2.75 kV.

Monday, January 29, 2018, 13:51: BIAS/EZL/EE @ 57.5 / 26 / 2.9 kV.

Sparks

Monday, January 29, 2018, 13:57: BIAS/EZL/EE @ 58 / 27 / 2.95 kV.

Monday, January 29, 2018, 14:03: Holding.

Monday, January 29, 2018, 14:07: BIAS/EZL/EE @ 59 / 28 / 3.1 kV.

Monday, January 29, 2018, 14:14: Spark*

Monday, January 29, 2018, 14:45: Holding

Monday, January 29, 2018, 14:56: BIAS/EZL/EE @ 0. Test Complete

Attachment 1: 2018_HV_test_2.docx
  625   Tuesday, January 30, 2018, 06:51 Aaron Schmidt LP-SIS  (Blank)42752-3DoneHV test 3

Tuesday, January 30, 2018, 06:50: BIAS / EZL / EE @ 30 / 13 / 1.5

Tuesday, January 30, 2018, 06:52: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Tuesday, January 30, 2018, 06:58: Optics on / set

Tuesday, January 30, 2018, 06:59: IV4 opened.

RGA switched completely off and unplugged.

Tuesday, January 30, 2018, 13:15: BIAS / EZL / EE @ 40 / 17 / 2

Tuesday, January 30, 2018, 13:20: BIAS / EZL / EE @ 50 / 21.8 / 2.5

Tuesday, January 30, 2018, 13:50: Half hour wait. Ok. No sparks.

Tuesday, January 30, 2018, 13:55: BIAS / EZL / EE @ 55 / 24 / 2.8

15 minute wait. No sparks.

Tuesday, January 30, 2018, 14:10: BIAS / EZL / EE @ 57.5 / 27 / 3.1

Tuesday, January 30, 2018, 14:23: BIAS / EZL / EE @ 60 / 28 / 3.1

Tuesday, January 30, 2018, 14:35: No sparks.

Tuesday, January 30, 2018, 15:05: BIAS / EZL / EE @ 0

Tuesday, January 30, 2018, 15:06: Auto-cooling started.


Wednesday, January 31, 2018, 06:59: Power/sources off.

 

Attachment 1: 2018_HV_test_3.docx
  626   Wednesday, January 31, 2018, 09:53 Aaron Schmidt    (Blank)42752-3DoneWire moved.

Wednesday, January 31, 2018, 09:50: A wire (B - F) was too close (Almost touching) to the EZL and had visible sparks during HV tests 1 & 2. The wire was adjusted to sit higher. and away from the EZL

  627   Wednesday, January 31, 2018, 12:58 Aaron Schmidt LP-SIS  (Blank)42752-3In progressHV test 4

Wednesday, January 31, 2018, 12:53: Power/sources on.

Wednesday, January 31, 2018, 12:58: BIAS / EZL / EE @ 40 / 17 / 2

Wednesday, January 31, 2018, 13:02: BIAS / EZL / EE @ 40 / 17 / 2

Wednesday, January 31, 2018, 13:05: BIAS / EZL / EE @ 50 / 22 / 2.5

Wednesday, January 31, 2018, 13:08: BIAS / EZL / EE @ 55 / 24 / 2.8

Wednesday, January 31, 2018, 13:10: BIAS / EZL / EE @ 57.5 / 27 / 3.0

Wednesday, January 31, 2018, 13:14: BIAS / EZL / EE @ 60 / 28 / 3.1

Wednesday, January 31, 2018, 13:34: No Sparks.

Wednesday, January 31, 2018, 14:14: No sparks after one hour.

Wednesday, January 31, 2018, 14:44: Spark free at 1-1/2 hours.

Wednesday, January 31, 2018, 14:45: Bringing down voltage.

Wednesday, January 31, 2018, 14:56: BIAS / EZL / EE @ 0

Wednesday, January 31, 2018, 14:57: Sources off.

Attachment 1: 2018_HV_test_4.docx
  628   Monday, February 05, 2018, 09:17 Aaron Schmidt      Problems/SolutionsEpics loss

Monday, February 05, 2018, 09:10: the epics program was in 'White-out'. Turbo pumps tripped.

Unplug, re-plug PLC.

Monday, February 05, 2018, 09:16: Restart Turbo pumps on chamber & beamline.

Monday, February 05, 2018, 09:21: Ion gauges on.


Tuesday, February 06, 2018, 09:00: TSG:CB1 noted to be red. Attempts to restart/reconfigure failed. Alive displays red MAJOR. Fault submitted.