  Test-Stand, Page 34 of 53  Not logged in ELOG logo
Entry  Tuesday, August 04, 2015, 13:37, Anders Mjos, , , , , , , Problems/Solutions, Equipment for outgassing measurements removed 
 
Entry  Monday, August 10, 2015, 18:01, Anders Mjos, , LP-SIS, , , , , In progress, Testing new center block target 
Installed thermocouples:
T1: TGHT tube left side, inside
T2: TBHT restraint
Entry  Saturday, August 29, 2015, 14:33, Anders Mjos, , , , , , , Problems/Solutions, Restarted IOC after power outage 
 Saturday, August 29, 2015, 15:50: Turbos started
Entry  Wednesday, September 09, 2015, 08:54, Anders Mjos, , , , , , , In progress, Venting 
 Wednesday, September 09, 2015, 08:53: Turbos stopped

Friday, September 11, 2015: Vented
Entry  Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning Ta#46.docx
EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0: Roughing
Friday, September 11, 2015, 12:12: Turbos started.
Entry  Monday, September 14, 2015, 08:38, Anders Mjos, , , , , , , Problems/Solutions, RP2 increased pressure 
 e-fault submitted and vacuum group (Edi) notified.
Monday, September 14, 2015, 09:33: RP2 replaced by vacuum group
Entry  Thursday, September 17, 2015, 14:05, Anders Mjos, Test Target, LP-SIS, , , , , In progress, New centre block test 
 

    
        
            T1
            Probe Inside Target
Left
        
        
            T2
            Centre block attached outside
        
        
    
Entry  Friday, September 18, 2015, 11:35, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP6 nor working 
found in fault state this morning. Edi consulted and fault report submitted.
Entry  Wednesday, September 30, 2015, 16:28, Anders Mjos, Test Target wrapped with heat shields, LP-SIS, , , , , In progress, New centre block test 
 

    
        
            T1
            Probe Inside Target Left
        
        
            T2
             
Entry  Friday, October 02, 2015, 08:35, Anders Mjos, , , , , , , Problems/Solutions, Venting beam line for TP exchange 
 Friday, October 02, 2015, 08:35: Turbo stopped
Entry  Wednesday, October 07, 2015, 11:16, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32.docx
Wednesday, October 07, 2015, 11:15: roughing
Wednesday, October 07, 2015, 12:09 Turbos started
Wednesday, October 07, 2015, 12:18: Turbos at speed. Vacuum at 1.7E-5 T
    Reply  Tuesday, October 13, 2015, 07:47, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32-2.docx
Target was pumped down on Friday.

Tuesday, October 13, 2015, 07:47: Opened water for HS. No response on RGA. Vacuum stable at 2.2E-7 T
Tuesday, October 13, 2015, 07:59: Gas lines open.
Entry  Tuesday, October 13, 2015, 16:04, Anders Mjos, , , , , , , Problems/Solutions, IV4 timed out 
Contacted Graham W. (controls) to have a look. It turned out to be a limit switch problem. Removed and reinstalled limit switch solved the time out issue.
    Reply  Tuesday, October 13, 2015, 17:23, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32-3.docxEmittance.zipNeEfficiecy.xlsx
Tuesday, October 13, 2015, 17:22: Roughing
Tuesday, October 13, 2015, 18:07: Started turbos.
Tuesday, October 13, 2015, 18:15: Turbos at speed. Vacuum at 1.9E-5 T
Entry  Wednesday, October 14, 2015, 16:13, Anders Mjos, , , , , , , Problems/Solutions, TMS:RP2 replaced 
 by vacuum group. The pump was making more noise than usual.
Entry  Thursday, October 15, 2015, 11:19, Anders Mjos, , , , , , , Problems/Solutions, Right side TGHT connector block removed Photo_2015-10-16_11_57_45_AM.jpgPhoto_2015-10-16_11_57_51_AM.jpg
The keensert has been worn out and will be replaced.
The keensert was re-tapped and the block re-installed. New bolts used for TGHT connection (2x). Swagelok T connections shortened (pluged).
Entry  Friday, October 16, 2015, 12:26, Anders Mjos, Target tube only, , , , , 41120-4, In progress, Conditioning HS for UC#14 2015-10-22_TS_Leak.docx
Friday, October 16, 2015, 12:20: Roughing.
Friday, October 16, 2015, 13:06: Started turbos.
Friday, October 16, 2015, 13:25: Turbos at speed. Vacuum at 3.2E-5 T
Entry  Monday, October 19, 2015, 09:45, Anders Mjos, , , , , , , Problems/Solutions, IG1 filament dead 
Will went chamber to replace the filament.
See e-fault 8501 
Monday, October 19, 2015, 09:43: turbos stopped
    Reply  Monday, October 19, 2015, 15:39, Anders Mjos, , , , , , , Problems/Solutions, Exhaust came off the new RP2 


    
        
            Anders Mjos wrote:
        
        
            
             by vacuum group. The pump was making more noise than usual.
Entry  Monday, November 02, 2015, 12:47, Anders Mjos, , , , , , , Problems/Solutions, Removed Swagelok T from rioght TGHT water lines 
Mico replaced the T's with copper tube and leak checked.
Monday, November 02, 2015, 12:46: Roughing
Monday, November 02, 2015, 13:19: Starting turbos