  Test-Stand, Page 31 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O#down Status Subject
  370   Friday, April 04, 2014, 08:24 Anders MjosTiC#4HP-SISITETM3  In progressVenting

 

Aurelia Laxdal wrote:

HV and Heaters Conditioning had finished. The target was cooled down and it's ready for the on-line installation.

 

Friday, April 04, 2014, 08:23: Target bias, EE and EZL to zero. Turbos off.

Friday, April 04, 2014, 10:14: Venting 

Friday, April 04, 2014, 10:48: Target removed - By R.M.

  372   Wednesday, April 23, 2014, 09:37 Anders Mjos      Problems/SolutionsStarted Sources archiver

The archiver was not running

  373   Wednesday, April 23, 2014, 14:16 Anders Mjos      DoneCu-strip cleaning test - sample #1, not cleaned

Wednesday, April 23, 2014, 14:15: Roughing

Wednesday, April 23, 2014, 14:34 : Starting turbos

Wednesday, April 23, 2014, 14:42 : Turbos at speed

Wednesday, April 23, 2014, 14:44 : Vacuum at 8.3E-6 T


Thursday, April 24, 2014, 09:12: Opened water for HS loop. Vacuum stable at1.6E-7 T

Thursday, April 24, 2014, 09:25: Started heating TGHT to 580A at 2A/min

Thursday, April 24, 2014, 14:07: Aborted autoramping. Cu-strip glowing. Started Target Cooldown.


Monday, April 28, 2014, 08:36: Stopped turobs. Vacuum at 1.2E-7 T

Attachment 1: Front_2014-04-24_2_05_56_PM.jpg
Front_2014-04-24_2_05_56_PM.jpg
Attachment 2: Side_2014-04-24_2_06_12_PM.jpg
Side_2014-04-24_2_06_12_PM.jpg
  374   Monday, April 28, 2014, 10:23 Anders Mjos      In progressCu-strip cleaning test - sample #2, cleaned

Monday, April 28, 2014, 10:23: Started roughing

Monday, April 28, 2014, 10:48: Started turbos. CG1 at ~0.3 T 

Monday, April 28, 2014, 10:56 : Turbos at speed

Monday, April 28, 2014, 10:58 : Vacuum at 7.2E-6 T


Tuesday, April 29, 2014, 09:15: Vacuum over night was somewhat erratic with a couple of excursions. Venting to redo door seal and inspect chamber. 

Tuesday, April 29, 2014, 13:18: Venting 

Aborted venting.


Wednesday, April 30, 2014, 10:15: Vented. Cleaned front door o-ring and groove. Inspected VCR joint on HS water loop. No visible issues.

Wednesday, April 30, 2014, 10:15: Roughing

Wednesday, April 30, 2014, 10:35 : Starting turbos

Wednesday, April 30, 2014, 10:44 : Turbos at speed

Wednesday, April 30, 2014, 10:45 : Vacuum at 6.5E-6 T


Thursday, May 01, 2014, 08:44: Vacuum erratic over night. Small burst of pressure increase in vacuum with ~2 hours intervals. Leak found on HS cooling circuit by purging the water line.

Thursday, May 01, 2014, 08:46: Stopping turbos. Vacuum at 2.7E-7 T

HS water line should be purged again before breaking VCR seal.

Thursday, May 01, 2014, 09:59: Venting

Thursday, May 01, 2014, 10:45: Removed HS loop.

Thursday, May 01, 2014, 10:45: Roughing

Thursday, May 01, 2014, 11:11: Starting turbos. CG1 ~ 0.1 T

Thursday, May 01, 2014, 11:19: Turbos at speed

Thursday, May 01, 2014, 11:21 : Vacuum at 5.2E-6 T


Monday, May 12, 2014, 10:03  : Turbos stopped. Vacuum at 1.22 E-7 T

Monday, May 12, 2014, 13:34: Venting

 

  375   Thursday, May 08, 2014, 15:09 Anders Mjos      Problems/SolutionsSOURCES archiver reported stopped

 Archiver restarted.

  376   Friday, May 09, 2014, 10:48 Anders Mjos      Problems/SolutionsEPICS white-out e-fault 7380

Monday, May 12, 2014, 10:02: Jane R. power cycled the hardware. EPICS is back up. Sources archiver required a restart.

  378   Thursday, May 15, 2014, 14:58 Anders Mjos      Problems/SolutionsIOC rebooted to recover from white-out.

Restarted archivers.

  379   Tuesday, May 20, 2014, 11:17 Anders Mjos      Problems/SolutionsBurnt off GND connection on Service Cap

The ground connection between B and F (ISK4523D Rev 6) was found burnt off. It will be switched out as per CATHODE BIAS configuration (ISK4563D Rev 3) by Ray D.

  380   Tuesday, May 20, 2014, 12:39 Anders Mjos      DoneFEBIAD Cathode Negative BIAS configuration

As per ISK4562 Rev 3 and ISK4563 Rev 3

By Ray D. and co.

  381   Wednesday, May 21, 2014, 17:05 Aurelia LaxdalSiC#30HP-FEBIADITETM3  In progressSiC#30 HV and Heaters conditiong

As per Friedhelm the conditioning settings are:

TGHT 580A

TBHT 290A

COIL 80A

ANODE 200V

 

Ramped up completed:

 

TGHT 580A/5.683V

TBHT 242A/2.295V (EPICS settings) and 289A/2.29V at the PS

COIL 80A

Current on the Anode = 13.431mA

 

 

  382   Monday, May 26, 2014, 14:15 Aurelia LaxdalSiC#30HP-FEBIADITETM3  DoneSiC#30 HV and Heaters Conditioning

HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation.

Attachment 1: SiC#30_Conditioning_2nd_time.docx
  383   Thursday, June 12, 2014, 09:28 Anders Mjos      Problems/SolutionsElevated backing pressure on ISAC Test Stand TMS:RP2

Anders Mjos wrote:

The performance of the roughing pump has gradually gone down. Notably after the system has been vented. See attached screenshot from the archiver.

E-fault 7258.

 

 Edi replaced the backing pump on June 5th.

  385   Monday, June 16, 2014, 09:12 Anders Mjos      In progressEmpty chamber

Monday, June 16, 2014, 09:12: Roughing


Tuesday, June 17, 2014, 14:38: Venting 

  387   Wednesday, June 18, 2014, 09:23 Anders Mjos      Problems/SolutionsTSH:MB1 Trip & MB1 June 10th water leak

A water leak on MB1 was found and reported by operations on June 10th e fault 7429

MB1 can not be switched on due to an TSH:MB1 water flow trip. Paddle wheel is rotating.

Wednesday, June 18, 2014, 14:03: Paddle wheel replaced with a used one from beam lines. Model SST150. Signal recovered.

  388   Thursday, June 19, 2014, 10:48 Anders Mjos      Problems/SolutionsFC0 did not retract from beam line

Upon inspection it was found that the bolt attaching the FC to the actuator had fallen off. The bolt was reattached and FC0 can be actuated in/out again.

  389   Friday, June 20, 2014, 11:44 Anders Mjos      In progressPumping down empty chamber

Friday, June 20, 2014, 11:44: Roughing

Friday, June 20, 2014, 13:00: Strarting turbos 

Friday, June 20, 2014, 13:09: Turbos at speed.

Friday, June 20, 2014, 13:10 : Vacuum at 1.3E-5


Thursday, June 26, 2014, 08:52 : Turbos stopped. Vacuum at 1.3E-7 T

Thursday, June 26, 2014, 15:34: Venting 

  391   Tuesday, July 08, 2014, 09:05 Anders Mjos      In progressEmpty chamber

Tuesday, July 08, 2014, 09:05: Roughing

Tuesday, July 08, 2014, 13:23: Starting turbos

Tuesday, July 08, 2014, 13:30 : Turbos at speed

Tuesday, July 08, 2014, 13:33 : Vacuum at 2.8E-6 T

  392   Wednesday, July 09, 2014, 14:08 Anders Mjos      Problems/SolutionsFEBIAD ANODE current readback

The read back of the ANODE current was confirmed to be working today with help of Ray D. using a 1kOhm resistor. There is an offset in the read back which can explain why no current was seen on SiC#30. The resistor between CATHODE and GND was changed from 100 kOhm to 50kOhm.

  393   Friday, July 18, 2014, 08:19 Anders Mjos       Venting

Friday, July 18, 2014, 08:19: Stopped turbos

Friday, July 18, 2014, 10:58: Venting

  395   Wednesday, July 23, 2014, 14:34 Anders Mjos      In progressEmpty chamber

Wednesday, July 23, 2014, 14:34: Roughing
Wednesday, July 23, 2014, 15:03: Starting turbos.
Wednesday, July 23, 2014, 15:11: Turbos at speed
Wednesday, July 23, 2014, 15:13: Vacuum at 7.4E-6 T