Entry  Friday, September 07, 2012, 12:11, Friedhelm Ames, NB#7, LP-SIS, , , , , In progress, mass scan started 
Entry  Friday, September 07, 2012, 14:34, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , Problems/Solutions, Insulator ITD0342 overheated - swelling Nb#7_swelling_insulator.pdf
Entry  Tuesday, September 11, 2012, 13:13, Friedhelm Ames, Nb#7, LP-SIS, , , , , In progress, start cool down 
Entry  Wednesday, September 12, 2012, 08:02, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Venting 
Entry  Wednesday, September 12, 2012, 17:04, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Pumping down - w/replaced insulators 
Entry  Thursday, September 13, 2012, 08:24, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Water on 
Entry  Thursday, September 13, 2012, 13:05, Friedhelm Ames, Nb#7, LP-SIS, , , , , , heater ramping up started 
Entry  Friday, September 14, 2012, 15:27, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , Done, Venting 
Entry  Thursday, October 25, 2012, 13:02, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , In progress, Pumping down 
    Reply  Friday, October 26, 2012, 08:29, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , Done, Target ready for conditioning 
Entry  Thursday, November 01, 2012, 11:16, Aurelia Laxdal, TiC#3, LP-SIS, ITW, TM1, , , , TiC#3-LP-SIS Startup 
Entry  Thursday, November 01, 2012, 14:57, Aurelia Laxdal, TiC#3, LP-SIS, ITW, TM1, , , , TSH:TGHT readback stopped at 264.5A (for a higher setpoint) 
Entry  Friday, November 02, 2012, 14:20, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , , Mass scan done 
Entry  Friday, November 02, 2012, 15:40, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , Done, SiC#3 cooldown started 
Entry  Monday, November 05, 2012, 09:47, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , Done, TPS optics cannot be turned off.  
Entry  Monday, November 05, 2012, 13:26, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , Done, Venting the Test Stand 
Entry  Monday, November 05, 2012, 14:41, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , Done, Target Removed 
Entry  Monday, March 25, 2013, 11:39, Anders Mjos, Ta#39, LP-SIS, ITW, TM1, , , Done, Ta#39 commissioning 
Entry  Monday, March 17, 2014, 19:10, Anders Mjos, Ta#42, LP-SIS, ITW, TM4, 40282-1, 39956-1 / 39956-9 (base / lid), In progress, Conditioning Ta#42_Test_Stand.docxOMEGA_OM-DAQPRO-5300_21-Mar-14_13.56.35.dlp
Entry  Friday, April 04, 2014, 17:01, Rick Maharaj, UC#9, LP-SIS, ITW, TM1, , 39230-3, Done, Conditioning Heatshield for UCx#9 