Tuesday, October 13, 2015, 16:04, Anders Mjos, , , , , , , Problems/Solutions, IV4 timed out
|
Contacted Graham W. (controls) to have a look. It turned out to be a limit switch problem. Removed and reinstalled limit switch solved the time out issue. |
Friday, October 02, 2015, 08:35, Anders Mjos, , , , , , , Problems/Solutions, Venting beam line for TP exchange
|
Friday, October 02, 2015, 08:35: Turbo stopped |
Wednesday, September 30, 2015, 16:28, Anders Mjos, Test Target wrapped with heat shields, LP-SIS, , , , , In progress, New centre block test
|
T1
Probe Inside Target Left
T2
|
Friday, September 18, 2015, 11:35, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP6 nor working
|
found in fault state this morning. Edi consulted and fault report submitted. |
Thursday, September 17, 2015, 14:05, Anders Mjos, Test Target, LP-SIS, , , , , In progress, New centre block test
|
T1
Probe Inside Target
Left
T2
Centre block attached outside
|
Monday, September 14, 2015, 08:38, Anders Mjos, , , , , , , Problems/Solutions, RP2 increased pressure
|
e-fault submitted and vacuum group (Edi) notified.
Monday, September 14, 2015, 09:33: RP2 replaced by vacuum group |
Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning
|
EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0: Roughing
Friday, September 11, 2015, 12:12: Turbos started. |
Wednesday, September 09, 2015, 08:54, Anders Mjos, , , , , , , In progress, Venting
|
Wednesday, September 09, 2015, 08:53: Turbos stopped
Friday, September 11, 2015: Vented |
Saturday, August 29, 2015, 14:33, Anders Mjos, , , , , , , Problems/Solutions, Restarted IOC after power outage
|
Saturday, August 29, 2015, 15:50: Turbos started |
Monday, August 10, 2015, 18:01, Anders Mjos, , LP-SIS, , , , , In progress, Testing new center block target
|
Installed thermocouples:
T1: TGHT tube left side, inside
T2: TBHT restraint |
Tuesday, August 04, 2015, 13:37, Anders Mjos, , , , , , , Problems/Solutions, Equipment for outgassing measurements removed
|
|
Monday, July 13, 2015, 17:19, Anders Mjos, , LP-SIS, , , , , In progress, SIS Cup insulator clamping test
|
Monday, July 13, 2015, 17:09: Roughing
Monday, July 13, 2015, 17:51: Turbos started
Monday, July 13, 2015, 18:01: Turbos at speed. Vacuum at 3.7E-5 T |
Monday, July 06, 2015, 14:26, Anders Mjos, , , , , , , , Pumping down empty chamber
|
Monday, July 06, 2015, 14:26: Roughing
Wednesday, July 08, 2015, 09:26: Venting
Thursday, July 09, 2015, 11:42: Roughing |
Monday, July 06, 2015, 09:29, Anders Mjos, , , , , , , Problems/Solutions, Replaced out gassing gauge on the backing line
|
|
Tuesday, June 30, 2015, 14:51, Anders Mjos, ZrC#7, LP-SIS, , TM2, 41177-2, , In progress, ZrC#7 Conditioning 2 
|
Tuesday, June 30, 2015, 14:51: Roughing
Tuesday, June 30, 2015, 16:14: Started turbos. CG1 at 0.075 T
Tuesday, June 30, 2015, 16:23 : Turbos at speed. Vacuum at 1.4E-5 T |
Monday, June 29, 2015, 16:51, Friedhelm Ames, , , , , , , Problems/Solutions, TSG:BV1B closed
|
found TSG:TP1B tripped off. Closed TSG:BV1B as pressure at TSG:iG1 was rising. Pressure is coming down again.
Tuesday, June 30, 2015 by AM
Found the control cable not completely inserted. Inserted cable, which tripped TP1A. Started both turbo pumps again. |
Thursday, June 25, 2015, 09:00, Anders Mjos, , LP-FEBIAD, , TM2, , , , TM2 FEBIAD Test
|
Thursday, June 25, 2015, 09:00: Water on HS. No vacuum response.
Thursday, June 25, 2015, 11:48: Started auto ramping heaters.
Thursday, June 25, 2015, 17:14: Target at 580/275 A. BIAS/EZL/EE at 30 / 13.5 / 1.5 kV |
Monday, June 22, 2015, 15:49, Anders Mjos, , , , , , , In progress, Installed new 9-pin feed through
|
No wires connected yet.
Monday, June 22, 2015, 15:48: Roughing
Tuesday, June 23, 2015, 09:05: Roughing vacuum does not go below 0.9 T. Venting to investigate. |
Monday, June 15, 2015, 14:09, Anders Mjos, ZrC#7, LP-SIS, , TM2, 41177-1, , In progress, ZrC#7 Conditioning 
|
Monday, June 15, 2015, 14:05 Roughing
Monday, June 15, 2015, 14:39: Turbos started.
Monday, June 15, 2015, 14:49: Turbos at speed. Vacuum at 5.3E-5 T |
Monday, June 15, 2015, 14:07, Anders Mjos, , , , , , , Problems/Solutions, Test Stand Source Tray installed
|
Monday, June 15, 2015
Remaining items to do
ANODE wire not yet attached
FEBIAD COILS not yet reconfigured
Tuesday, June 16, 2015: |
|