Entry  Wednesday, September 14, 2011, 15:33, John Wong, Test#1, HP-SIS, ITW, TM1, test, test, In progress, testing elog for test stand 
Wednesday, September 14, 2011, 15:33
blah blah blah...
Entry  Sunday, July 28, 2019, 14:22, Luca Egoriti, P2N - 1, HP-FEBIAD, ITE, TM2, p2n - test1, p2n - test1, Problems/Solutions, p2n heating test 3 20190728_-_p2n_heating_3.PNG
Friday. July 26th 2019 
A new electrical configuration of the test stand was decided and installed. The TGHT and TBHT were parallelized in order to deliver up to 600 +
600 Amperes to the p2n target.
Entry  Tuesday, June 26, 2012, 18:04, Anders Mjos, FEBIAD anode end cap test, , , , Tube only, 38307-9, In progress, FEBIAD anode end cap test - ready 
Testing FEBIAD anode end cap as per dwg ITD0304 REV C
Target with TUBE ONLY. Do not use target heater.

Tuesday, June 26, 2012, 18:03: Roughing
Entry  Friday, July 19, 2013, 14:14, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test 
Friday, July 19, 2013, 14:14 : Stopping Turbos. Vacuum at 1.3E-7 T 
Friday, July 19, 2013, 15:14:  Venting
Friday, July 19, 2013, 16:22: Target installed. Roughing.
Entry  Tuesday, August 20, 2013, 08:24, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test 
Tuesday, August 20, 2013, 08:13: Roughing gas lines
Tuesday, August 20, 2013, 08:22: Gas lines roughed. Valve closed
Entry  Wednesday, September 18, 2013, 16:18, Anders Mjos, , HP-FEBIAD, , , Tube only, 38307-9, Done, Test Target - FEBIAD COIL 
Wednesday, September 18, 2013, 16:18: Starting turbos
Wednesday, September 18, 2013, 16:26 : Turbos at speed
Wednesday, September 18, 2013, 16:28 : Vacuum at 2.8 E-5 T
Entry  Friday, October 31, 2014, 14:57, Anders Mjos, , LP-FEBIAD, , , Tube only, 38307-9, In progress, Test test20141103.pngtest20141103-2.png
Friday, October 31, 2014, 14:47: Starting turbos
Friday, October 31, 2014, 14:57: Turbos at speed. Vacuum at 2.9E-5 T

Monday, November 03, 2014, 10:08 : Opened HS water circuit. Vacuum stable at 1.7E-7 T
Entry  Friday, December 12, 2014, 14:09, Anders Mjos, , LP-FEBIAD, , , Tube only, , In progress, HV BIAS Test 2014-12-17_60_kV_3h.png60_kV_Test.docx
BIAS current limit pot changed from 2.40 to 0.25
EZL current limit pot changed from 0.50 to 0.20
Testing max HV bias with Ray
Entry  Thursday, April 25, 2013, 13:32, Anders Mjos, Empty, LP-FEBIAD, , , Tube Only, 38307-9 , In progress, FEBIAD Coil test 2014-04-30_FEBIAD_COIL_AWG18.PNG2014-05-01_FEBIAD_COIL_AWG18.PNGTarget_Assembly.pdf
Same target as in e-log entry https://elog.triumf.ca/TIS/Test-Stand/106
Thursday, April 25, 2013, 13:54: Roughing
Thursday, April 25, 2013, 14:25: Started turbos 
Entry  Wednesday, June 26, 2019, 11:34, Aaron Schmidt, Test Ta, HP-SIS, , TM4, No Target oven #, 42972-4, In progress, Test target for TM4 checks 
The HP-SIS uses the older center block. No serial number found. 
Loaded with Tantalum. Rough Target description:
Comment on the bag - 0.9 cm space
Entry  Friday, August 10, 2012, 12:44, Pierre Bricault, NA, LP-FEBIAD, , , NA, NA, In progress, FEBIAD test 
Rick put the helium bottle back in the rack.
Waiting for status of the gas lines.
 
Entry  Friday, August 10, 2012, 15:29, Pierre Bricault, NA, LP-FEBIAD, , , NA, NA, , finishing the gas installation and its pump 
1524H Start small pump.
1529H stop the pump.
 
Entry  Saturday, August 11, 2012, 13:34, Pierre Bricault, NA, LP-FEBIAD, , , NA, NA, In progress, Test FEBIAD anode bias 120 V 
 
Entry  Friday, August 10, 2012, 11:29, Pierre Bricault, NA, , , , N A, NA, In progress, Test FEBIAD 
The helium bottle was found empty.
Rick will refill it and hook the leak detector on the system to find out
if we have a leak on the line.
Entry  Friday, August 25, 2023, 17:21, Aaron Schmidt, Nb#11, LP-IG-LIS, ITW, TM2, 45447-9, 42132-4, In progress, Conditioning Nb#11 Nb#11_Conditioning.docx
Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum taking a while to rough down. Vacuum @ 1.034T. Opened FS#5.
Entry  Thursday, July 06, 2023, 16:55, Aaron Schmidt, Nb#10, LP-IG-LIS, ITW, TM2, 45447-7, 42132-2, In progress, Conditioning Nb#10 Nb#10_Conditioning.docx
Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B on.
Thursday, July 06, 2023, 16:47: TP1A on.
Entry  Friday, April 26, 2024, 13:49, Aaron Schmidt, TiC#7, HP-FEBIAD, ITW, TM4, 45447-5, 45235-15, In progress, Conditioning TiC#7 
FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B started.
Entry  Friday, February 16, 2024, 10:30, Aaron Schmidt, SiC# (Stock), HP-FEBIAD, , , 45447-4, 45235-21, In progress, Conditioning stock SiC HP FEBIAD Stock_SiC_Elog_996_HP-FEBIAD_Cathode_BM_-_HV_&_Coil.docxHP-FEBIAD_Elog_996_-_Ramp_up_&_mass_scans.docxStock_SiC_Elog_996_HP-FEBIAD_Cathode_BIAS_mode_-_2.docx
Friday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38: TP1B on. 
Friday, February 16, 2024, 17:47: TP1A on. 
Entry  Wednesday, June 19, 2024, 15:50, Brady Borrmann, TiC#9, HP-SIS, , , 45447-29, 45235-19, In progress, Conditioning TiC#9 2024-06-21_HPTiC-24C_target_characterization.docx
Wednesday, June19, 2024, Spare TiC HP-SIS target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing
Wednesday, June19, 2024, 17:25:  TP1B started.
Entry  Tuesday, September 10, 2024, 16:24, Dave Neilson, TiC #24D, HP-SIS, ITW, TM3, 45447-27, 45235-25, , Back up target testing and conditioning 2024-09-11_HPTiC-24D_target_characterization.docx
Tuesday, September 10, 2024, 16:21:   Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: roughed down and turbo pumps now on.
Tuesday, September 10, 2024, 20:27   Pressure at 4.9e-6, increasing TGHT TBHT to 580A/230A at 1A/30s