  RH-Meson Hall, Page 7 of 18  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Thursday, May 10, 2018, 15:23, Isaac Earle, Repair, Target 1, Target, T1-MK2 protect monitor and profile monitor replaced 
Entry  Friday, April 13, 2018, 14:21, Isaac Earle, Maintenance, Other, Other, M20 beam blocker MRO and T1/T2 final checks 
Entry  Tuesday, April 10, 2018, 11:20, Isaac Earle, Maintenance, Other, Cooling, T1 and T2 cooling package shutdown MRO work 
Entry  Friday, April 06, 2018, 15:05, Isaac Earle, Standard Operation, Target 2, Target, T2-MK2 target MRO 
Entry  Wednesday, March 28, 2018, 10:12, Isaac Earle, Standard Operation, Other, Other, Five waste pails moved to East Vault Tunnel for storage 
Entry  Thursday, March 22, 2018, 17:24, Isaac Earle, Standard Operation, Other, Active Sump, RH Lab active sump released 
Entry  Wednesday, January 10, 2018, 17:45, Isaac Earle, Standard Operation, Target 2, Target, T2-MK2 beam spot photos, M20BB moved to storage pit T2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018.jpgT2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018_s.jpg
Entry  Thursday, December 07, 2017, 13:54, Isaac Earle, Development, Other, Other, Waste pails transferred from warm cell storage bunker to rad waste pit IMG_0102.JPGIMG_6285.JPGIMG_0102.JPGIMG_6285.JPG
Entry  Thursday, October 26, 2017, 16:12, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve replaced 
Entry  Tuesday, October 10, 2017, 12:09, Isaac Earle, Standard Operation, Target 2, Target, T2-MK2 position 4 target changed 20171005_t2target_0010.jpg20171005_t2target_0015.jpg20171005_t2target_0016.jpg
Entry  Tuesday, August 29, 2017, 12:17, Isaac Earle, Maintenance, Target 1, Target, T1-MK1 and T2-MK1 Hansen water fittings replaced 
Entry  Thursday, July 27, 2017, 09:34, Keith C Ng, Development, Other, Other, test 2 
Entry  Thursday, July 27, 2017, 08:57, Isaac Earle, Other, Target 2, Cooling, Failed T2CS:SVSEC valves investigation 
Entry  Tuesday, July 25, 2017, 19:23, Isaac Earle, Repair, Target 2, Cooling, T2 Heat Exchanger Secondary Side Solenoid Valve Failure (again) 
Entry  Monday, July 10, 2017, 16:20, Keith C Ng, Repair, Target 2, Target, T2 Heat Exchanger Secondary Side Solenoid Valve Failure  20170710_t2_water_package_repair.pdf
Entry  Monday, May 15, 2017, 16:55, Isaac Earle, Other, Target 2, Target, T2 profile monitor actuation issue 
Entry  Tuesday, May 09, 2017, 16:35, Isaac Earle, Repair, Target 2, Cooling, T2 target water flow gauge paddle wheel changed T2CS_FGTGT_strip.jpg
Entry  Friday, May 05, 2017, 15:09, Isaac Earle, Development, Target 2, Target, T2-MK2 beam spot check in hot cell T2MK2_Position_1_and_2_Exit.JPGT2MK2_Position_2_Entrance.JPGT2MK2_Position_2_Exit.JPGT2-MK2_profile_monitor_dislodged.JPG
Entry  Tuesday, April 11, 2017, 17:31, Isaac Earle, Development, Target 2, Target, T2-MK2 target MRO and alignment of T2 devices T2-MK2_-_2017.pdf
Entry  Tuesday, April 11, 2017, 17:02, Isaac Earle, Maintenance, Target 2, Cooling, T2 Cooling System MRO 