7
|
Thursday, January 05, 2012, 10:21 |
Isaac Earle | Maintenance | Target 1 | Cooling | Defeated T1 and T2 cooling package vacuum interlocks. | Defeated T1 and T2 cooling package
vacuum interlocks at 1-C panel on South mezzanine
in Meson Hall to allow cooling packages to |
|
8
|
Friday, January 06, 2012, 15:37 |
Isaac Earle | Maintenance | Target 2 | Target | Transferred M20 beam blocker to hot cell | Uncovered T2 monolith and transferred M20BB to hot cell using flask. |
|
9
|
Thursday, January 12, 2012, 11:34 |
Isaac Earle | Maintenance | Target 2 | Target | Replaced M20 Beam Blocker Vacuum Seal O-Rings | Replaced M20 beam blocker vacuum
seal o-rings. Old o-rings were noticeably
harder, but not brittle or cracked. Applied |
|
14
|
Wednesday, January 25, 2012, 13:26 |
Isaac Earle | Maintenance | Target 2 | Target | M9BB Returned to Beam Line | M9 beam blocker returned to beam line.
T2 target disconnected, picked up
using flask, and returned to beam line as |
|
15
|
Monday, January 30, 2012, 16:44 |
Isaac Earle | Maintenance | Target 1 | Cooling | Completed T1 Cooling Package MRO | Replaced
all o-rings and filters on the T1 cooling
package. Replaced resin can. Refilled |
|
26
|
Tuesday, April 03, 2012, 15:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1 Ladder Position Look-up Tables Updated | Graham Waters has activated the appropriate
target ladder position look-up tables for
the T1-MK1 target which was installed in |
|
29
|
Thursday, April 05, 2012, 15:22 |
Isaac Earle | Maintenance | Target 1 | Target | T1 & T2 Profile and Protect "Blip" Test | Diagnostics group completed their
"blip" signal response tests on
the T1 and T2 profile and protect monitors. |
|
31
|
Thursday, April 12, 2012, 15:19 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Target Water Drained | In preparation for extended periods
of the T2 volume being vented during the
M20 repair, the T2 water package was shut-off, |
|
37
|
Wednesday, June 06, 2012, 08:58 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Monolith Leak Check | While leak checking components in
the M20 front end on May 25th, the top of
the T2 monolith was also checked by flooding |
|
44
|
Friday, June 22, 2012, 13:54 |
Isaac Earle | Maintenance | Target 2 | Target | Air Amplifier Rebuild Complete | A full rebuild of the upper air amplifier
was completed. New anodized aluminum
barrels were installed (replacing the old |
|
45
|
Tuesday, June 26, 2012, 09:05 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 Target Water Flow Transducers Serviced | The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to |
|
57
|
Thursday, September 13, 2012, 18:09 |
Isaac Earle | Maintenance | Target 1 | Cooling | September Shutdown T1 & T2 MRO | The following tasks were performed
during the 2012 September Shutdown:
- Both targets moved to position |
|
64
|
Monday, December 10, 2012, 15:42 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK2 Target Maintenance | - T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor |
|
66
|
Tuesday, January 08, 2013, 10:52 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK1 Target Maintenance | - T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed |
|
71
|
Tuesday, January 29, 2013, 15:55 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 H.E. Transported to Warm Cell | Friday Jan 25:
- Both sides of heat exchanger drained,
disconnected, and capped |
|
72
|
Tuesday, February 05, 2013, 09:50 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 target moved from beam line to hot cell | The T2-MK2 target was transported from
the beam line to the RH hot cell. The
profile monitor was secured in the 'in' position |
|
73
|
Wednesday, March 06, 2013, 12:13 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 Heat Exchanger MRO | - The new tube array was picked up from
Kaltech on Feb 8th (observed vessel holding
60psi on hydro test at their shop) |
7x |
74
|
Monday, March 18, 2013, 15:17 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 Target Maintenance and Re-Wiring | - T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed |
|
75
|
Tuesday, March 26, 2013, 10:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 Re-wiring and MRO Complete | The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed |
|
108
|
Friday, March 28, 2014, 13:59 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 P1 Transducer and T2 Q1 Flow Meter Replaced | The T2 P1 pressure transducer (Omega PX315-100GI)
and T2 Q1 Proteus flow meter (0150SSTF3)
have been replaced with new units to address |
|