  331   Tuesday, July 18, 2023, 09:14 Adam NewsomeOtherTarget 1CoolingT1 Cooling Package: target flow (FGTGT) sensor noise issuesBetween 1:00 pm and 6:00 pm on July 17,
2023, the T1 target cooling water flow rate
sensor exhibited some noise which resulted
 1.PNG2.PNG 
  315   Wednesday, February 01, 2023, 14:23 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning.
 IMG_1038.JPEG 
  317   Thursday, February 02, 2023, 15:14 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package: Leaked Valve InspectionA 0.75" SwageLok ball valve that was
taken out from the T1 cooling package was
inspected (SS-45S12).
 CompiledPictures.pdf 
  112   Thursday, April 03, 2014, 16:35 Isaac EarleStandard OperationTarget 1CoolingT1 Cooling Package Started The T1 cooling package was started
around 2pm today.  There was no change
to the T1 volume vacuum during startup.
  
  310   Monday, January 16, 2023, 15:01 Adam NewsomeMaintenanceTarget 1CoolingT1 Cooling Package MRO - 2023 ShutdownT1 Cooling Package MRO began Jan. 16, 2023.
 
The following maintenance tasks have
 T1_2023-03-06.PNG 
  85   Friday, August 23, 2013, 10:39 Isaac EarleRepairTarget 1CoolingT1 Cooling Package Inlet Pressure (P1) Sensor The T1 cooling package inlet pressure
(P1) has been dropping since approximately
May 5, 2013 from the regular operating pressure
 T1_P1_plot_(may-aug).jpgT1_P1_plot.jpg 
  316   Thursday, February 02, 2023, 10:35 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package Draining (Prep for Valve Replacement)Water reservoir in T1 started draining
at ~7.30 am, will leave till tomorrow or
overnight to fully drain. 
  
  138   Tuesday, January 27, 2015, 17:38 Isaac EarleRepairTarget 1CoolingT1 Cooling Package 3/4" Valves Rebuilt - T1 MRO Complete- Both 3/4" ball valves on the T1
cooling package target water circuit were
rebuilt, leak tested with house air pressure,
  
  20   Tuesday, March 20, 2012, 10:31 Isaac EarleRepairTarget 1CoolingT1 Cooling Package - Potential Water LeakThe T1 expansion tank warning level sensor
had tripped and the level was approximately
1cm from the base of the tank.  No trip
  
  78   Friday, April 12, 2013, 17:33 Isaac EarleDevelopmentTarget 1CoolingT1 & T2 high-temp limit switch installation, wiring, and commissioning completeInstallation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed
  
  256   Wednesday, February 05, 2020, 14:53 Isaac EarleMaintenanceTarget 1CoolingT1 & T2 cooling package MRO work completed Annual MRO work on the T1 and T2
cooling packages is now complete.  The
following tasks were performed:
  
  160   Tuesday, May 12, 2015, 21:20 Grant MinorStandard OperationTarget 1TargetT1 & T2 Targets moved from pos. 0 to pos. 4Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm.
  
  45   Tuesday, June 26, 2012, 09:05 Isaac EarleMaintenanceTarget 1CoolingT1 & T2 Target Water Flow Transducers Serviced The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to
 T1_&_T2_water_flow.jpg 
  142   Friday, February 20, 2015, 13:55 Isaac EarleStandard OperationTarget 2TargetT1 & T2 Target Moves- The T1-MK1 target was moved from the
hot cell to storage pit hole #3 (ready as
T1 spare)
  
  182   Tuesday, October 13, 2015, 10:52 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Target Ladder Moves The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the
  
  61   Wednesday, October 24, 2012, 17:38 Isaac EarleRepairTarget 2TargetT1 & T2 Target Ladder Control System Status During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller
  
  155   Thursday, April 23, 2015, 16:29 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Profile and Protect Monitors Electrical Check CompletedAn electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell.  They
  
  29   Thursday, April 05, 2012, 15:22 Isaac EarleMaintenanceTarget 1TargetT1 & T2 Profile and Protect "Blip" Test Diagnostics group completed their
"blip" signal response tests on
the T1 and T2 profile and protect monitors.
  
  82   Tuesday, May 14, 2013, 13:26 Isaac EarleDevelopmentTarget 1TargetT1 & T2 Profile ScanThe T1 and T2 profile monitors were used
during today's development shift.  Target
ladder movement for T1 was done at the panel
  
  28   Thursday, April 05, 2012, 12:14 Isaac EarleRepairTarget 1TargetT1 & T2 Profile MonitorsControls Group replaced the wiring and
wire harness for the profile monitor limit
switches on T2.  The monitor was actuated
  