331
|
Tuesday, July 18, 2023, 09:14 |
Adam Newsome | Other | Target 1 | Cooling | T1 Cooling Package: target flow (FGTGT) sensor noise issues | Between 1:00 pm and 6:00 pm on July 17,
2023, the T1 target cooling water flow rate
sensor exhibited some noise which resulted |
|
|
315
|
Wednesday, February 01, 2023, 14:23 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge | Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning. |
|
|
317
|
Thursday, February 02, 2023, 15:14 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: Leaked Valve Inspection | A 0.75" SwageLok ball valve that was
taken out from the T1 cooling package was
inspected (SS-45S12). |
|
|
112
|
Thursday, April 03, 2014, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 Cooling Package Started | The T1 cooling package was started
around 2pm today. There was no change
to the T1 volume vacuum during startup. |
|
|
310
|
Monday, January 16, 2023, 15:01 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 Cooling Package MRO - 2023 Shutdown | T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have |
|
|
85
|
Friday, August 23, 2013, 10:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package Inlet Pressure (P1) Sensor | The T1 cooling package inlet pressure
(P1) has been dropping since approximately
May 5, 2013 from the regular operating pressure |
|
|
316
|
Thursday, February 02, 2023, 10:35 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package Draining (Prep for Valve Replacement) | Water reservoir in T1 started draining
at ~7.30 am, will leave till tomorrow or
overnight to fully drain. |
|
|
138
|
Tuesday, January 27, 2015, 17:38 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package 3/4" Valves Rebuilt - T1 MRO Complete | - Both 3/4" ball valves on the T1
cooling package target water circuit were
rebuilt, leak tested with house air pressure, |
|
|
20
|
Tuesday, March 20, 2012, 10:31 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package - Potential Water Leak | The T1 expansion tank warning level sensor
had tripped and the level was approximately
1cm from the base of the tank. No trip |
|
|
78
|
Friday, April 12, 2013, 17:33 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 high-temp limit switch installation, wiring, and commissioning complete | Installation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed |
|
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
|
160
|
Tuesday, May 12, 2015, 21:20 |
Grant Minor | Standard Operation | Target 1 | Target | T1 & T2 Targets moved from pos. 0 to pos. 4 | Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm. |
|
|
45
|
Tuesday, June 26, 2012, 09:05 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 Target Water Flow Transducers Serviced | The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to |
|
|
142
|
Friday, February 20, 2015, 13:55 |
Isaac Earle | Standard Operation | Target 2 | Target | T1 & T2 Target Moves | - The T1-MK1 target was moved from the
hot cell to storage pit hole #3 (ready as
T1 spare) |
|
|
182
|
Tuesday, October 13, 2015, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Target Ladder Moves | The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the |
|
|
61
|
Wednesday, October 24, 2012, 17:38 |
Isaac Earle | Repair | Target 2 | Target | T1 & T2 Target Ladder Control System Status | During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller |
|
|
155
|
Thursday, April 23, 2015, 16:29 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Profile and Protect Monitors Electrical Check Completed | An electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell. They |
|
|
29
|
Thursday, April 05, 2012, 15:22 |
Isaac Earle | Maintenance | Target 1 | Target | T1 & T2 Profile and Protect "Blip" Test | Diagnostics group completed their
"blip" signal response tests on
the T1 and T2 profile and protect monitors. |
|
|
82
|
Tuesday, May 14, 2013, 13:26 |
Isaac Earle | Development | Target 1 | Target | T1 & T2 Profile Scan | The T1 and T2 profile monitors were used
during today's development shift. Target
ladder movement for T1 was done at the panel |
|
|
28
|
Thursday, April 05, 2012, 12:14 |
Isaac Earle | Repair | Target 1 | Target | T1 & T2 Profile Monitors | Controls Group replaced the wiring and
wire harness for the profile monitor limit
switches on T2. The monitor was actuated |
|