84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
|
152
|
Wednesday, April 22, 2015, 15:15 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 and T2 Cooling Packages Ready | Both cooling packages are running steadily
with the targets in Position 0.
The demin flow (Q2) for both was |
|
|
308
|
Thursday, January 12, 2023, 10:36 |
Adam Newsome | Maintenance | Target 1 | Water Leak | T1 and T2 - Cooling Package Water Leaks - Ball Valves | Upon uncovering the T1 and T2 areas to
prepare for regular cooling package maintenance,
it was discovered that multiple ball valves |
|
|
309
|
Monday, January 16, 2023, 09:54 |
Adam Newsome | Standard Operation | Other | Cooling | T1 and T2 - Cooling Package Drained | On Jan. 13, the T1 and T2 cooling package
water reservoirs were drained to the BL1A
holding tank. Water samples were obtained |
|
|
50
|
Wednesday, July 11, 2012, 17:51 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Swap | BL1A was started yesterday and brought
up to 10 |
|
|
23
|
Friday, March 23, 2012, 14:50 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Leak - Update | The T1-MK2 target was transferred from
the beam line to the hot cell. Water
was seen in the bottom of the target pipe |
|
|
76
|
Tuesday, April 09, 2013, 17:06 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Electronics Check | The T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013. The response from |
|
|
143
|
Friday, February 27, 2015, 18:06 |
Isaac Earle | Development | Target 1 | Target | T1 Rotary Collimator Water and Air Line Investigation | Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary |
|
|
21
|
Wednesday, March 21, 2012, 17:28 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | The water level in the T1 cooling
package expansion tank was checked again
today approximately 24 hours after it was |
|
|
22
|
Thursday, March 22, 2012, 13:58 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | Vacuum group pumped down on the T1
& T2 volumes (because there is no cold
trap on the T1 pump) for approximately 1 |
|
|
87
|
Monday, September 09, 2013, 16:22 |
Isaac Earle | Repair | Target 1 | Cooling | T1 P1 Transducer Replaced | The BL1A tunnel was accessed today
to assess a faulty reading from the T1 cooling
package inlet pressure transducer (T1P1). |
|
|
327
|
Thursday, April 06, 2023, 13:35 |
Albert Kong | Maintenance | Target 1 | Controls | T1 Motor Controller Hearbeat Trip (+T2 Heartbeat Trip) | The T1 motor controller hearbeat tripped
(noticed this morning).
This does not seem prevent beam delivery |
|
|
214
|
Thursday, January 19, 2017, 08:55 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 MRO work complete | The following work was completed on
the T1 cooling package:
- water drained to BL1A holding |
|
|
186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
|
276
|
Thursday, February 17, 2022, 13:03 |
Matthew Gareau | Maintenance | Target 1 | Target | T1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening | this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and |
|
|
26
|
Tuesday, April 03, 2012, 15:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1 Ladder Position Look-up Tables Updated | Graham Waters has activated the appropriate
target ladder position look-up tables for
the T1-MK1 target which was installed in |
|
|
330
|
Tuesday, June 06, 2023, 15:42 |
Albert Kong | Standard Operation | Target 1 | Cooling | T1 Heat Exchanger Low Flow Diagnostics | On May 31, the low active water in BL1A
was turned off briefly and upon re-starting,
the flow to the T1 heat exchanger was very |
|
|
216
|
Monday, March 27, 2017, 16:15 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Target Water Return Hose Damaged | The 18' shielding block which lies west
of the T1 cooling package was removed on
Friday Mar 24 so that vacuum equipment could |
|
|
209
|
Friday, September 30, 2016, 16:59 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Inlet Pressure Transducer Replaced | The T1 cooling system inlet pressure
transducer (EPICS ID: B1A:T1CS:PGIN, Omega
part # PX315-100GI) began failing in August |
|