239
|
Friday, June 01, 2018, 17:50 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve coil replaced | Flow stopped through the T1 collimator
cooling loop around the same time as a power
bump this afternoon. The problem was |
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|
84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
152
|
Wednesday, April 22, 2015, 15:15 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 and T2 Cooling Packages Ready | Both cooling packages are running steadily
with the targets in Position 0.
The demin flow (Q2) for both was |
|
308
|
Thursday, January 12, 2023, 10:36 |
Adam Newsome | Maintenance | Target 1 | Water Leak | T1 and T2 - Cooling Package Water Leaks - Ball Valves | Upon uncovering the T1 and T2 areas to
prepare for regular cooling package maintenance,
it was discovered that multiple ball valves |
|
309
|
Monday, January 16, 2023, 09:54 |
Adam Newsome | Standard Operation | Other | Cooling | T1 and T2 - Cooling Package Drained | On Jan. 13, the T1 and T2 cooling package
water reservoirs were drained to the BL1A
holding tank. Water samples were obtained |
|
50
|
Wednesday, July 11, 2012, 17:51 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Swap | BL1A was started yesterday and brought
up to 10 |
|
23
|
Friday, March 23, 2012, 14:50 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Leak - Update | The T1-MK2 target was transferred from
the beam line to the hot cell. Water
was seen in the bottom of the target pipe |
|
76
|
Tuesday, April 09, 2013, 17:06 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Electronics Check | The T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013. The response from |
|
360
|
Thursday, January 23, 2025, 17:09 |
Albert Kong | Maintenance | Other | Cooling | T1 T2 water solenoid valves rubber gasket and o-ring exchange | All rubber components on the T1 T2 water
solenoid valves were exchanged on Jan 22,
2025. |
|
362
|
Monday, February 10, 2025, 16:46 |
Albert Kong | Maintenance | Other | Other | T1 T2 ASCO Air Solenoid Valve Rebuild | The compressed air ASCO valves for the
M9BB, M20BB, T1 Profile Monitor (2x 8342C1
[rebuild kit 306-191] + 1x 8320G216 [rebuild |
|
143
|
Friday, February 27, 2015, 18:06 |
Isaac Earle | Development | Target 1 | Target | T1 Rotary Collimator Water and Air Line Investigation | Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary |
|
21
|
Wednesday, March 21, 2012, 17:28 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | The water level in the T1 cooling
package expansion tank was checked again
today approximately 24 hours after it was |
|
22
|
Thursday, March 22, 2012, 13:58 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | Vacuum group pumped down on the T1
& T2 volumes (because there is no cold
trap on the T1 pump) for approximately 1 |
|
87
|
Monday, September 09, 2013, 16:22 |
Isaac Earle | Repair | Target 1 | Cooling | T1 P1 Transducer Replaced | The BL1A tunnel was accessed today
to assess a faulty reading from the T1 cooling
package inlet pressure transducer (T1P1). |
|
327
|
Thursday, April 06, 2023, 13:35 |
Albert Kong | Maintenance | Target 1 | Controls | T1 Motor Controller Hearbeat Trip (+T2 Heartbeat Trip) | The T1 motor controller hearbeat tripped
(noticed this morning).
This does not seem prevent beam delivery |
   |
214
|
Thursday, January 19, 2017, 08:55 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 MRO work complete | The following work was completed on
the T1 cooling package:
- water drained to BL1A holding |
|