  RH-ISAC, Page 98 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject
  808   Tuesday, December 02, 2014, 13:33 David WangSouth Hot-CellDevelopmentTM2 Leak check on TM2 tube heater +(D) at SHC

Chad and I leak checked TM2 tube heater+(D) circuit at SHC with water bypass loop and new seals installed on the water block. The LD base LR 0.0xE-9 atm.cc/sec,base pressure0.0xE-4 torr. Chad sprayed helium on the leak check area in SHC for 5 seconds. No any response has been found on LD during 1minutes waiting time. The test was repeated again and the result is same. NO LEAK at this stage!  After the TM2 is moved to CS , The D line will be pressured with 80 psi helium for helium pressure leak test before any hot water is circuited through it.  

Attachment 1: 2014-12-02_003.JPG
2014-12-02_003.JPG
Attachment 2: 2014-12-02_001.JPG
2014-12-02_001.JPG
Attachment 3: 2014-12-02_004.JPG
2014-12-02_004.JPG
  807   Tuesday, December 02, 2014, 10:15 chad fisherSouth Hot-CellRepairTM2 TM2 Reburb. Loop Install

Final polish, clean with methanol and clean compressed air.

Loop installed and torqued to 90 in lbs.

Minimum of approximately 1"  between loop and containment box at closest point.

Attachment 1: TM2_20141202_01.jpg
TM2_20141202_01.jpg
Attachment 2: 20141203_142215.jpg
20141203_142215.jpg
Attachment 3: 20141203_143530.jpg
20141203_143530.jpg
  806   Monday, December 01, 2014, 14:48 Travis CaveSpent Target VaultStandard Operation  F-308s moved

The F-308s have been moved into the target hall,  for filling on wednesday.

  805   Monday, December 01, 2014, 14:06 chad fisherSouth Hot-CellRepairTM2 TM2 REFURB. WATER LOOP TEST

Some issues with the turntable and having to wait for a decision on whether to remove TM2 from the hot cell so that TM4 with dead UCx target could be put in this morning.

Progress on TM2:

  • Containment box has been removed from TM2.
  • Water block jig has been installed.
  • Existing blank off has been removed.
  • Sealing surfaces have been inspected.
  • First stage of sealing surface cleaning has been performed.

Tomorrow:

  • Polish of sealing surfaces.
  • Installation of loop.
  • Vacuum/helium leak check of loop.

TM2_20141201_03 - sealing surfaces before cleaning...kind of dirty

TM2_20141201_05AC - sealing surfaces after cleaning...looks good!

Attachment 1: TM2_20141201_01.JPG
TM2_20141201_01.JPG
Attachment 2: TM2_20141201_02.JPG
TM2_20141201_02.JPG
Attachment 3: TM2_20141201_03.JPG
TM2_20141201_03.JPG
Attachment 4: TM2_20141201_04.JPG
TM2_20141201_04.JPG
Attachment 5: TM2_20141201_05AC.jpg
TM2_20141201_05AC.jpg
  804   Monday, December 01, 2014, 12:05 maicodallavalleSpent Target VaultMaintenance  F-308 Maintenance

F-308's have been serviced and are ready to be filled with spent targets. F-308's witch were serviced are #6,#13,#15,#16,and #19.

  803   Friday, November 28, 2014, 13:06 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule move

TM#2 with no target or source tray has been moved from the north east silo to the south hot cell.

  802   Wednesday, November 26, 2014, 11:11 Travis CaveSpent Target VaultStandard Operation Ta#38, Nb#7, TiC#3, NiO#2, and SiC#29Spent targets moved to mini storage

The following targets have been moved to the mini storage from the target storage vault:

  1. Ta#38
  2. Nb#7
  3. TiC#3
  4. SiC#29
  5. NiO#2

These target will be removed from the mini storage and placed into the F-308's on December 3rd.

  801   Tuesday, November 25, 2014, 12:45 David WangITEStandard OperationTM4UCx115 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  800   Tuesday, November 25, 2014, 11:33 David WangSouth Hot-CellDevelopment  Remove UCX 11 target transfer stand from SHC back to TH.

The stand was used for transferring UCX11 targte from TH to SHC. The stand wit target was craned down from TH into SHC last week and stayed there over weekend. Chad and I removed the stand out of SHC yesterday. It was heavily contaminated. RPG and I spent more than 3 hours to clean this stand. See the emails I pasted below for  detail information.

Thanks, David, for letting me know about this. Here are survey results after my afternoon in Target Hall:

I spent 1.5 hours on additional decon of the stand, crane hook, and area around where David was doing the decon, finding up to 10k cpm (44-2) on some parts at first. Danka came to help after a bit (THANK YOU, DANKA) and we left the items covered in plastic and surveyed the area. Contamination survey results are as follows, numbers are units of cpm on the 44-2/RM14:

Tacky mats inside TMH door: 6000/2000

Tacky mats in hall before TMH door: 200/0

Tacky mats at boot box: 8000/4000

My booties: 50/0

Air sample at the decon area: 50/60 (also 100 cpm on alpha probe)

Floor swipes post-decon of floor: 0/0

Early results from a 10 min assay of the tacky mats shows predominantly Kr-85, Be-7, Sr-85, Rb-83, and Sr-82. A longer assay is underway.

The following measurements were made using the checking cave at the boot box (units of cpm):

David's respirator cartridges: 160

David's respirator: 0

Davids tank suit and booties: 1200

My suit: 100

My respirator: 0

The rags used for the decon work were contained in a bag and left behind the silos by the DST. This bag measured 240 uSv/h OC and 2 uSv/h at 0.5m

Thanks,

Andrew

 

On 11/24/2014 12:57 PM, David Wang wrote:

Hi all, The UCx#11 target transferring stand is moved back from SHC to TH. However, the stand was heavily contaminated. On the first Windex clean up towel, the counts directly shoot over the 500K counts which is the maximum scales on both RM14 and 44-2. After almost 2 hours, more than 20 times cleaning up with Windex spray and paper towel wipe , the counts dropped below 300 now. It is extremely difficult to clean up this stand.  I dont think we should move the target this way again unless we have a solution on the contamination clean up. The stand is still hanging  on the crane, and waiting for RPG checking.                        Thanks    David

  799   Friday, November 21, 2014, 10:40 Travis CaveSpent Target VaultStandard Operation Ta#44Spent target move

The spent Ta#44 target has been removed from the south hot cell, it was placed in pail #121 and placed in spot 4A of the storage vault. It was 276mSv/hr upon removal from the south hot cell.

Attachment 1: Vault_Storage_November_21_2014.pdf
Vault_Storage_November_21_2014.pdf Vault_Storage_November_21_2014.pdf Vault_Storage_November_21_2014.pdf Vault_Storage_November_21_2014.pdf
  798   Thursday, November 20, 2014, 14:13 David WangConditioning StationStandard OperationTM4UCx11CS and TM4 was vented with Argon gas

CS and TM4 was vented with Argon gas this morning before it was moved from CS to ITE.

  797   Thursday, November 20, 2014, 14:12 David WangITEStandard OperationTM4UCx11TM4 is connected in ITE.

TM4 has been connected connect in ITE. Water is supplied to TM4 module only.

  796   Thursday, November 20, 2014, 11:49 Travis CaveITEStandard OperationTM4UC#11module move

TM#4 with UCx#11has been moved from the conditioning station to the east target station.

  795   Wednesday, November 19, 2014, 11:12 David WangConditioning StationStandard OperationTM4 CS roughing pump is started.

CS roughing pump is started for TM4 and UCX 11 target.

  794   Wednesday, November 19, 2014, 09:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#11Electrical check

TM#4 with UC#11 electrical check done. See attached PDF for the results.

Attachment 1: TM4_elec_check_UC11_SHC.PDF
TM4_elec_check_UC11_SHC.PDF
  793   Wednesday, November 19, 2014, 08:49 chad fisherSouth Hot-CellStandard OperationTM4UCx#11Ta#44 Removed Ucx#11 Installed

Ta#44 has been removed from TM4 and UCx#11 has been installed and is ready for testing.

New fasteners were installed for all mounting and current connections.

High current fasteners were torqued to 130in lbs.

  792   Tuesday, November 18, 2014, 11:15 David WangITEStandard OperationTM4Ta#44TM4 has been disconnected in ITE.

Dan and I disconnected TM4 in ITE.

  791   Tuesday, November 18, 2014, 11:14 David WangSouth Hot-CellStandard Operation UCx11crane down UCx 11 target into SHC from TH

I craned down UCx11 target from TH into SHC. Chad was in SHC service area watching on it. The source tray moving jig was installed on the crane for this moving.

  790   Tuesday, November 18, 2014, 10:28 Travis CaveSouth Hot-CellStandard OperationTM4Ta#44module move

TM#4 with Ta#44 has been moved from the east target station to the south hot cell.

  789   Monday, November 17, 2014, 13:45 chad fisherSouth Hot-CellRepair  Jig for roof install of target

Jig for installation of target through hot cell roof has been assembled and placed in the target hall.

Attachment 1: Target_roof_install_20141117_01.jpg
Target_roof_install_20141117_01.jpg
Attachment 2: Target_Roof_install_Jig_20141117_02.jpg
Target_Roof_install_Jig_20141117_02.jpg
Attachment 3: Target_roof_install_20141117_03.jpg
Target_roof_install_20141117_03.jpg
Attachment 4: Target_roof_install_20141117_04.jpg
Target_roof_install_20141117_04.jpg