ID Datedown Author Category Type Module Target/Number Subject
  892   Monday, April 20, 2015, 10:22 David WangConditioning StationStandard OperationTM1UCx12TM1 with UCx12 has been connected to CS and ready for conditioing.

The TH will be locked during the TM1 conditioning time due to  an interference issue between CS HV cover and a gas analysis valve on top of TM1. A work permit has been issued for the conditioning job because of it.

  891   Monday, April 20, 2015, 10:12 Anders MjosConditioning StationStandard OperationTM1UC#12Conditioning UC#12

Monday, April 20, 2015, 09:35: Started cooling water circulation

HV cover did not fit due to interference with the air sampling valve. Target Hall will have to be locked out for conditioning to proceed. WP I2015-04-20-2

Monday, April 20, 2015, 10:09: Started chiller staging

Target hall and HV enclosure has been locked out.

Monday, April 20, 2015, 13:45: 22 kV, 0.04 mA BIAS 

Monday, April 20, 2015, 14:58: No sparks observed. BIAS off


Tuesday, April 21, 2015, 08:26:  Starting heater auto-ramp to 500 / 230 A at 2 A/min

Tuesday, April 21, 2015, 08:32: BIAS/EE to 20 / 1.5 kV

Tuesday, April 21, 2015, 12:59: TGHT / TBHT at 327 / 230 A. Pausing the auto-ramping. Bill will be monitoring TCS while I am off-site.

Tuesday, April 21, 2015, 15:56: Continue auto-ramping

Tuesday, April 21, 2015, 17:34: Auto-ramping finished. TGHT / TBHT at 500 / 230 A


Wednesday, April 22, 2015, 08:43: Vacuum tripped heaters and BIAS over night. Switching off to do a leak check on the service cap.

Wednesday, April 22, 2015, 09:03: Stopping turbo and roughing pump for David. David is preparing a leak check.

Wednesday, April 22, 2015, 09:06: Started roughing pump.

Wednesday, April 22, 2015, 09:22: Roughing pump trips off after a few minutes of pumping.

Wednesday, April 22, 2015, 13:11: Stopped water flow.

Wednesday, April 22, 2015, 16:07: Starting turbos 

Wednesday, April 22, 2015, 16:15: All turbos at speed.


David found a leak on the window line this morning.
https://elog.triumf.ca/TIS/RH-ISAC/896

Thursday, April 23, 2015, 11:12 : Starting cooling pack

Good vacuum limit on IG1 changed from 7E-5 T to 1E-5 T

Thursday, April 23, 2015, 12:53 : Starting heater auto-ramp to 500 / 230 A at 2 A/min. Bad vacuum limit reduced to 8E-6 T

Thursday, April 23, 2015, 13:03 : BIAS/EE to 15/ 1.5 kV

Thursday, April 23, 2015, 13:28 : BIAS/EE to 20/ 1.5 kV. No sparking observed

Thursday, April 23, 2015, 17:23: Auto-ramping finished. TGHT / TBHT at 500 / 230 A

Thursday, April 23, 2015, 17:51: Fault on cooling circuit (Fault 2).. Manually starting CP1

Thursday, April 23, 2015, 18:01: Cycled power of chiller unit. System recovered. Enabled staging.

Thursday, April 23, 2015, 18:42 : One minor spark observed. Starting cool down at 12 and 9 A/min

Thursday, April 23, 2015, 19:51 : Heaters and BIAS off


Friday, April 24, 2015, 08:21 : Water cooling off

  890   Monday, April 20, 2015, 07:27 David WangITEStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015

Weekly target hall schedule update.2015-04-20

weekly target hall schedule update 2015-04-27 attachments 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  889   Friday, April 17, 2015, 14:04 Travis CaveSouth Hot-CellStandard OperationTM1UC#12Module move

TM#1 with UCx#12 has been moved from the south hot cell to the conditioning station.

  888   Friday, April 17, 2015, 11:56 Travis CaveSouth Hot-CellStandard OperationTM1UC#12Electrical check

Electrical check of TM#1 with UCx#12 attached. See attached PDF for details.

Attachment 1: TM1_UC#12_tgt_elec_chk_SHC.PDF
TM1_UC#12_tgt_elec_chk_SHC.PDF
  887   Friday, April 17, 2015, 09:09 Travis CaveSouth Hot-CellStandard OperationTM1No targetModule move

TM#1 with no target has been moved from the south west silo to the south hot cell for the installation of the UCx target.

  886   Wednesday, April 15, 2015, 09:01 Anders MjosConditioning StationDevelopment  Archiver variables added by Controls

 

 

 

 

 

 

 

 

 

 

The following variable have been added to the archiver (as per work request)

TCS:TS5:RDTEMP 
TCS:TCM1:EE:RDTEMP 
TCS:TCM1:COIL1:RDTEMP 
TCS:TCM1:TBHT:RDTEMP 
TCS:TCM1:TGHT:RDTEMP 
TCS:TCM1:MSP:RDTEMP 
TCS:TCM1:HVC1:RDTEMP 
TCS:TCM1:HS:RDTEMP 
TCS:FC:SCALECUR 
TCS:COL:SCALECUR 
TCS:TK2:RDLEVEL 
TCS:TK2:RDLEVEL 
TCS:DIF1:RDFLOW 
TCS:CHILL:RDHRS

The archiver was restarted.

 

 

  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015

See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.

Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  884   Friday, April 10, 2015, 15:40 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.

5 shielding  blocks have been transferred to ITE. The ITE is configured to take proton beam.

  883   Wednesday, April 01, 2015, 13:12 David WangITEStandard OperationTM4Ta#45TM4 has been connected in ITE

TM4 has been connected in ITE. ITE six turbo-pumps have been started. So far so good.

  882   Wednesday, April 01, 2015, 13:08 David WangITEStandard OperationTM4 Replaced ITE tank to module 42X0.275 o-ring

I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new o-ring was installed. It works fine.

Attachment 1: 001.JPG
001.JPG
Attachment 2: 002.JPG
002.JPG
Attachment 3: 004.JPG
004.JPG
Attachment 4: 005.JPG
005.JPG
Attachment 5: 006.JPG
006.JPG
  881   Wednesday, April 01, 2015, 10:52 Travis CaveITEStandard OperationTM4Ta#45Module move

TM#4 with Ta#45 has been moved from the conditioning station to the east target station.

  880   Wednesday, April 01, 2015, 06:56 David WangConditioning StationStandard OperationTM4Ta#45TM4 has been disconnected at CS.

TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday.

  879   Tuesday, March 31, 2015, 11:36 chad fisherSouth Hot-CellDevelopmentTM2 TM2 Optics Tray Complete

TM2 optics tray is complete.

Master alignment tray: 0 up/down, 0 left/right

Optics tray: Front 0 up/down, 0 left/right. Middle 0 up/down, 0 left/right. Back 0 up/down, 0 left right.

 

Attachment 1: 20150331_OPTICS_FRONT.jpg
20150331_OPTICS_FRONT.jpg
Attachment 2: 20150331_OPTICS_MIDDLE.jpg
20150331_OPTICS_MIDDLE.jpg
Attachment 3: 20150331_OPTICS_BACK.jpg
20150331_OPTICS_BACK.jpg
  878   Monday, March 30, 2015, 09:03 Anders MjosConditioning StationStandard OperationTM4Ta#45Ta#45 Conditionoing

Monday, March 30, 2015, 08:59: Reset chiller by switching on off power (fault 2)

Monday, March 30, 2015, 09:02: Switched on CHILL:CP2, TS5 at 34 C

Monday, March 30, 2015, 10:24 : Cage locked. EE to GND. BIAS and EL ON.

Troubleshooting BIAS current limiting. Turned out to be a EPICS initialization issue. Resolved by setting/changing the current limit again in EPICS.

Monday, March 30, 2015, 14:00: BIAS/EL 18 / 9 kV

Monday, March 30, 2015, 14:16: BIAS/EL 24 / 12 kV

Monday, March 30, 2015, 16:03: BIAS/EL 30 / 15 kV. Occasional sparking while stepping up since 26 kV

Monday, March 30, 2015, 16:13: BIAS/EL 30.8 / 15 kV. 110% of scheduled 28 kV. BIAS/EL 0.04 / 0.09 mA

Monday, March 30, 2015, 17:26 : Maintained BIAS over 1 hour. One spark after.

Monday, March 30, 2015, 17:27 : BIAS / EL off.


Tuesday, March 31, 2015, 08:12: Cage access. EE to EE PS. Cage locked.

Tuesday, March 31, 2015, 08:24: BIAS/EL/EE at 30.8 / 15 / 1 kV

Tuesday, March 31, 2015, 08:26 : EE to 2 kV, 1.96 mA

Tuesday, March 31, 2015, 08:46: No sparks for 20 min.

Tuesday, March 31, 2015, 08:48 : BIAS/EL/EE at 20 / 9.3 / 1.5 kV

Tuesday, March 31, 2015, 08:57: Started auto ramping of heaters to 580 / 230 A at 2 A/min.

Tuesday, March 31, 2015, 10:54: TBHT at 230 A

Tuesday, March 31, 2015, 14:05: TGHT at 580 A

Tuesday, March 31, 2015, 14:21: BIAS/EL/EE to 30.8 / 15 / 2 kV

Tuesday, March 31, 2015, 17:48: Source stable for 4h

Tuesday, March 31, 2015, 18:20: Lowered IAS/EL/EE to 20 / 9.3 / 1.5 kV. IG2 at 6.2E-6 T

Tuesday, March 31, 2015, 21:27: Starting ramp down at 15/12 A/min. IG2 at 6.8E-6 T

Tuesday, March 31, 2015, 21:51: BIAS/EL/EE to zero and off. IG2 at 6.6E-6 T

Tuesday, March 31, 2015, 22:17: TGHT and TBHT off

Tuesday, March 31, 2015, 22:41: Turbos off.

Tuesday, March 31, 2015, 22:42: Water off.

Attachment 1: Ta#45_Conditioning.docx
  877   Monday, March 30, 2015, 07:38 David WangITEStandard OperationTM4 TH Shut Down Activities Schedule Feb 23th- Apr 15th update

Updated schedule this morning after last Fridays ISAC facility support group meeting.

Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time  weekly update.

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CS

TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been  installed onto the TM4 service cap.The CS water system is started. All water signals are good so far.   Anders will start  HV and heaters conditioning on next Monday.

Attachment 1: 010.JPG
010.JPG
Attachment 2: 013.JPG
013.JPG
Attachment 3: 012.JPG
012.JPG
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CS

The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all good.

Attachment 1: 001.JPG
001.JPG
Attachment 2: 005.JPG
005.JPG
Attachment 3: 006.JPG
006.JPG
  874   Thursday, March 26, 2015, 09:20 Travis CaveConditioning StationStandard OperationTM4Ta#45Electrical check

Electrical check of TM#4 with Ta#45 at the conditioning station, see attached pdf for details.

Attachment 1: TM4_Ta#45_tgt_elec_chk_CS.PDF
TM4_Ta#45_tgt_elec_chk_CS.PDF
  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .

I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also.