Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 92 of 140  Not logged in ELOG logo
Entry  Tuesday, June 23, 2015, 10:55, chad fisher, South Hot-Cell, Repair, , , Left Manipulator Repair 
The master wrist/tong cable has been replaced on the left manipulator. Everything appears to function well so far.
Entry  Tuesday, June 23, 2015, 14:19, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Water Block Jigs Removed 20150623_140917.jpg
Both halves of the water block jigs have been removed and the module is now ready for base vacuum leak and electrical checks.
During removal of the jigs the fiberglass that had been "shoved" by hand in between two of the lines in the early 2000's fell out again.
Entry  Tuesday, June 23, 2015, 16:49, Anders Mjos, Conditioning Station, Development, , , TCS is beeing migrated to ISAC 
by controls group (Dave Morris).

Friday, June 26, 2015
TCS has been migrated to ISAC controls. Access is possible on a per user basis from isacepics1.triumf.ca
Entry  Wednesday, June 24, 2015, 10:16, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Vacuum Leak Check 
The following circuits have been vacuum leak checked and have not registered any leaks:
Circuit D, C, B, A, Coil2, EE, Ground Electrode, Mounting Support plate, Coil 1.
Left are Heat Shield and Window circuits which will be checked after blank offs are installed on the vcr terminations.
Entry  Wednesday, June 24, 2015, 13:49, David Wang, South Hot-Cell, Repair, TM2, , TM2 new source tray vacuum leak check. TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment
Entry  Friday, June 26, 2015, 08:27, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2
2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4.
Entry  Friday, June 26, 2015, 09:44, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Retrofit Status 20150625_075616_1.jpg20150625_083457.jpg20150625_105735.jpg20150625_110053.jpg
On June 25th the following work was completed:
Optics tray was installed into TM2. The lower fastener on the vertical cable tray (IRH1585) needed to be removed and vertical cable tray rotated
upwards as optics tray would not clear cable tray. Optics tray was intstaled, cable tray repositioned and screw re-inserted.
Entry  Friday, June 26, 2015, 09:45, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status 
Containment box window waterlines have been connected and leak checked and new containment box cover installed.
Module ready for transport just before 9am.
Entry  Friday, June 26, 2015, 14:33, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 have been moved from SHC to CS 
Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing.
Entry  Friday, June 26, 2015, 15:38, Anders Mjos, Conditioning Station, Development, TM2, , Leak check and HV test 
Roughing started by David.
Friday, June 26, 2015, 15:31: Started TP1S
Friday, June 26, 2015, 15:38: Started  TP1 & TP2
Entry  Monday, June 29, 2015, 10:51, David Wang, Conditioning Station, Repair, TM2, , leak on TM2 side panel 
There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will
be vented soon. The seal on this panel has to been changed.
2016-06-30.  The o-ring seal on this panel(PNG1 and steerers)  is replaced and leak checked. No leak now.
Entry  Tuesday, June 30, 2015, 09:47, chad fisher, South Hot-Cell, Repair, , , manipulator repair 
The right hand manipulator has been repaired. It took 43 minutes and I received ~ 0.56 mSv
Entry  Tuesday, June 30, 2015, 15:41, David Wang, ITW, Standard Operation, TM1, , TM1 was disconnected in ITW this morning. 
TM1 was disconnected in ITW  this morning. The ITW was vented with argon last night.
Entry  Tuesday, June 30, 2015, 15:53, David Wang, Conditioning Station, Development, TM2, , leak on TM2 at CS TM2_leak_check_2015-06-30.pdfleak_check_2015-06-30_007.JPGleak_check_2015-06-30_009.JPG
 I leak checked TM2 at CS this afternoon which including air to vacuum check on service cap and helium pressure test on water lines. There is a
small leak on water line R ,U (COIL1) during the helium pressure test.. Below 20 psi helium, there is no leak on it. But , once the helium pressure is
increased over 20 psi, it showed up on Leak Detector. At 60 psi helium, the leak rate is 9.4xE-9 atm.cc/sec. For detail information, See attachment. 
Entry  Thursday, July 02, 2015, 10:22, Anders Mjos, Conditioning Station, Maintenance, TM2, , TP1S failed 
 See e-fault 8233. Edi assisted in diagnosing the problem. The pump will have to be replaced.
Entry  Friday, July 03, 2015, 09:27, Anders Mjos, Conditioning Station, Development, , , Controls working on access control in EPICS 
 Some reboots will be done.
Entry  Friday, July 03, 2015, 09:41, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Updated the schedule before the weekend 2015-07-03. See attachment 1,2
Updated the schedule according to present TM2 refurbishment process. See attachment 3,4
Entry  Friday, July 03, 2015, 11:33, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Coil Leak Progress TM2_coil_leak_20150703_11.jpg20150703_111248.jpg
First thing this morning the hot cell was "cleaned up" in preparation for the return of TM2 for attempted verification and locating of leak
on R/U coil circuit.
Containment box has been removed and front cover reinstalled to provide some modicum of shielding form the entrance and exit windows. Box was placed
Entry  Friday, July 03, 2015, 13:29, chad fisher, South Hot-Cell, Repair, TM2, , Hot Cell/ Module Fields 
Field measured at block "R" through tool port with pole monitor is 6.65 mSv/H.
There are three air hoods and two air lines currently available.
Entry  Tuesday, July 07, 2015, 10:50, Anders Mjos, Conditioning Station, Development, , , EPICS migration update - archiver 

    The archiver is now merged with ISAC - data available under Utilities - Archiver Retrieval
    Old archiver data is
available under Utilities -> Archiver Retrieval - old
    Strip tool save/load and export files under /data/tcsdata
 
  Login via isacepics1.triumf.ca. TCS button on ISAC menu
ELOG V2.9.2-2455