Tuesday, June 25, 2013, 14:24, Travis Cave, Conditioning Station, Standard Operation, TM1, UC#6, module move
|
Module moves of TM#1 with Ta#39 from ITW to SHC then TM#1 with UCx#6 from SHC to the conditioning station moves went well. |
Tuesday, June 25, 2013, 14:56, Bevan Moss, Conditioning Station, Standard Operation, TM1, UCx#6, Roughing Pumps Started
|
The roughing pumps have been started on the conditioning station. As it is late in the day for David he will make the turbo pump connections tomorrow. |
Wednesday, June 26, 2013, 11:03, David Wang, South Hot-Cell, Standard Operation, TM1, , Leak check on TM1 UCx target heat shield
|
Chad and I leak checked the TM1 UCx target heat shield at SHC. No leak has been found so far. |
Thursday, June 27, 2013, 14:21, chad fisher, South Hot-Cell, Standard Operation, TM1, Ucx#6, Ucx#6 installed Ta#39? rewmoved
|
Ucx#6 was installed on TM1 on Wednesday.
Ta#39 was removed. |
Thursday, June 27, 2013, 14:23, chad fisher, South Hot-Cell, Standard Operation, TM1, Ta#39, Ta#39 Autopsy performed
|
An autopsy of Ta#39 was performed yesterday and today. Ta#39 will be sent to the spent target storage vault on Tuesday.
|
Tuesday, July 02, 2013, 10:58, Travis Cave, Conditioning Station, Standard Operation, TM1, UC#6, module move
|
TM#1 with UC#6 has been moved from the conditioning station to the west target station, move went well. |
Thursday, July 04, 2013, 11:37, David Wang, ITW, Standard Operation, TM1, UCx, I reconnected TM1 to ITW.
|
I reconnected TM1 to ITW on 02 July.The pumping down is good so far. TM1 water interlock check is good also. |
Tuesday, July 09, 2013, 14:26, David Wang, ITW, Standard Operation, TM1, UCx, 5 shielding blocks had been transferred from ITE to ITW
|
5 shielding blocks had been transferred from ITE to ITW. The ITW is configured to take proton beam. |
Tuesday, August 27, 2013, 11:54, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#6, module move
|
TM#1 with UCx #6 has been moved to the south hot cell. |
Tuesday, August 27, 2013, 11:56, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#7, Electrical check
|
TM#1 with UCx#7 electrical check, numbers look good, see PDF for details. |
Tuesday, August 27, 2013, 14:14, Travis Cave, ITW, Standard Operation, TM1, UC#7, module move
|
TM#1 with UCx#7 has been moved from the south hot cell to the west target station. |
Wednesday, September 11, 2013, 09:35, David Wang, ITW, Standard Operation, TM1, UCx, 5 shielding blocks have been moved to ITW
|
I moved 5 shielding blocks to ITW this morning .I checked the water signals in electrical room before the moving, and everything is fine. The argon venting systemin ITW and electrical room is ready also. |
Tuesday, October 22, 2013, 11:18, Travis Cave, ITW, Standard Operation, TM1, UC#7, module move
|
TM#1 with UC#7 has been moved from the ITW to the south west silo. |
Wednesday, October 23, 2013, 09:28, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#7, module move
|
TM#1 with UC #7 has been moved from the south west silo to the south hot cell. |
Wednesday, October 23, 2013, 12:07, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, module move
|
TM#1 with no target has been moved back to the south west silo from the south hot cell. |
Thursday, March 06, 2014, 06:28, David Wang, Conditioning Station, Maintenance, TM1, , TM1 had been moved from silo to CS
|
TM1 has been successfully moved from silo to CS. The CS vacuum system is connected to TM1. Turbo pumps on TM1 and CS have been started yesterday afternoon . The starting of TM1 turbos was easy. The pumping down over night is good so far. |
Thursday, March 06, 2014, 12:59, David Wang, Conditioning Station, Maintenance, TM1, , Restart TM1 and CS TPs
|
Restarted TM1 and CS turbo pumps after the power off. Everything is fine . |
Thursday, March 06, 2014, 14:12, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 air to vacuum and water lines leak check at CS. 8x
|
TM1 air to vacuum and water lines leak check at CS are finished this afternoon. The leak detector is hooked directly to TM1 service cap so the base LR at LD is 0.0xE-9 atm.cc/sec. I sprayed helium to all air to vacuum seal on the service cap, also applied 70 psi to all water lines(except HS) for 2 minutes each. There is no any tiny response had been found on LD. So All TM1 water lines(except HS) and air to vacuum seals are leak free. The HS circuit can not be tested at this time since the VCR caps are not installed. The turbo pumps at CS and TM1 will be turned off before I leave. See attachment pictures. |
Thursday, March 20, 2014, 08:19, Travis Cave, Conditioning Station, Standard Operation, TM1, no target, module move
|
TM#1 with no target moved from the conditioning station to north west silo. |
Monday, June 02, 2014, 10:52, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, module move
|
TM#1 with no target has been moved from the north west silo to the south hot cell. |
|