Entry  Wednesday, January 04, 2017, 14:27, David Wang, Conditioning Station, Standard Operation, , , started TCS vacuum pump 
TCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S. We will use TCS to take TM2 tomorrow afternoon.
Entry  Thursday, January 12, 2017, 14:24, David Wang, ITW, Standard Operation, TM2, , ITW primary and secondary vacuum vessel winter shut down leak check. 
TM2 is located in ITW for this leak check. Leak detector is installed between ITW BV2s as before. LD base leak rate 0.0XE-9atm.cc/sec, base pressure
0.0XE-4 Torr. First , I leak checked dump module top flange seal which a small leak was found in last year winter shut down. This time,all ITW  turbo-pumps
cooling fans are switched off during the check. Lots helium are sprayed around the dump module top flange this time. I did not see any response on LD. 
Entry  Monday, January 16, 2017, 09:32, David Wang, ITW, Standard Operation, TM2, , Helium pressure test on TM2 water llines at ITW 
TM2 helium pressure test result at ITW. 70 psi helium 3 minutes on each circuit. LD base LR0.0XE-9atm.cc/sec  BP 0.0XE-4torr.  ITW IG1 1.22Xe-7
torr, ITW IG1S 1.31XE-7torr, ITW PNG4 2.66XE-6Torr(ITW TP4 off).
 
Entry  Wednesday, January 18, 2017, 09:55, David Wang, ITE, Standard Operation, TM4, , ITE and TM4 2017 winter shut down leak check. 
ITE and TM4 2017 winter shut down leak check are finished. All ITE primary, secondary vacuum vessel and TM4 water lines are good. No any leak has been
found.
Entry  Thursday, January 19, 2017, 10:15, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for 2017 winter shut down 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf
Updated target hall schedule for 2017 winter shut down. See attachments 1,2
Update schedule after Febiad beam schedule changed to ITE. See attachments 3,4
Entry  Tuesday, January 24, 2017, 15:24, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 electrical check and leack check. 
I did electrical check before and after Fefiad target installation on TM2. The RU (coil) Is till short to 60KV as before. Other result are good. After
Febiad target is installed, Tm2 HS line is leak checked. On leak detector, base leak rate pumping down is much slow  than before.  The base pressure
still could be pumped down to 0.0XE-4 torr.  After a long time wait, Chad and I leak checked at 2.2XE-8 atm.cc/sec base leak rate. Chad sprayed lots
Entry  Tuesday, January 24, 2017, 15:29, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved to TCS . 
I connected TCS vacuum system to TM2. The station is under roughing now. All turbo pumps will be started soon.
Entry  Tuesday, January 24, 2017, 15:32, David Wang, ITW, Standard Operation, TM2, , TM2 was moved from ITW to SHC this morning. 
The move is smooth. Yasmine and Travis did the move.
Entry  Friday, January 27, 2017, 10:52, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved from TCS to ITE 
The move is successful.
Entry  Wednesday, February 01, 2017, 12:23, David Wang, ITE, Standard Operation, TM2, , TM2 has been connected in ITE. 
TM2 has been connected in ITE. The SST window water lines in ITE can not be connected properly to TM2. The water line connector on TM2 window is 90 degree
CCW installed in direction comparing to TM4.This caused the problem. Solution: Two piece of flexible lines and extra male QC adapters have been used to
fix this issue.  HV cover and HV fence in ITE work  with TM2. Other connections are good as well.
Entry  Friday, February 03, 2017, 11:49, David Wang, Conditioning Station, Standard Operation, , , Update 2017 winter shutdown TH schedule. 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf
Update 2017 winter shut down target hall schedule. See attachments
Entry  Tuesday, February 07, 2017, 10:34, David Wang, ITW, Maintenance, , , ITW clean up 
ITW has been cleaned up today.  All station are vacuum cleaned. I wiped all HV cover and HV area including conductors and insulators. The black
foams which are used to wrap around TP back up line are degrading now. I removed most of these foams. Also, Some obsolete  water lines  are moved
our of station. All waste are bagged . they will be surveyed and  stored(or disposed) according to radio-active level.
Entry  Thursday, February 09, 2017, 09:24, David Wang, Conditioning Station, Development, , , Target module window cooling lines at TCS. 
Target module window  cooling lines at TCS has been modified to use spare 2 channel in TCS: WFB1. The old cooling lines used a spare channel in
TCS WFB2(HVC channel) are removed and capped. After change, TCS window cooling lines will be interlocked with heaters. The test run on new lines are good.
No leak  on all fittings, and signals on flow and temperature are good.   Control people will be noticed on this change for their following up
Entry  Friday, February 10, 2017, 09:56, David Wang, Conditioning Station, Standard Operation, , , water has been refilled to TCS:TK2  
TCS:TK2 , Water has been refilled to 28.5" level. It was 15.1". Fall protection equipment  are used during the job.
Entry  Monday, March 06, 2017, 08:01, David Wang, Cooling, Repair, , , HALCW resin tank replacement. 11x
HALCW resin tank has been replaced. The old tank is stored in middle-west silo now. The field on old resin tank bottom is about 3.5 msv/ hr(on contact).
By shielding it into silo and putting two lead blankets on the top cover of the silo,The general field 1 feet above this silo is 25usv/hr. And, The field
around the silo area are less affected. This old tank will stay there as long as possible.  For the new resin tank during preparation, It was found
Entry  Tuesday, March 07, 2017, 09:25, David Wang, ITW, Repair, , , ITW HALCW 2" return line ball valve seals replacement. 
Leaking seals on ITW HALCW 2" return line ball valve have been replaced. 8 liter waters are drained out for this job. Water are drained into a thick
plastic bag.  The bag is tie strapped , labeled, and put into a yellow garbage bin in MAA. Water sample is given to RPG. After analyzing, RPG will
give instruction on how to deal with it. Since we just refilled NALCW to system before this job, the active level on sample is very low. We may dump them
Entry  Tuesday, March 07, 2017, 14:41, David Wang, ITE, Maintenance, , , ITE dump plug water circuit is closed for ITE IG1S small surge. 
It is closed @ 2:35PM by closing supply side valve first , the return side valve of ITE dump plug .
Opened ITE dump plug circuit valves @4:28PM. ITE IG1S still at 1XE-6. No change before and after of circuit closing and reopeneing.
Entry  Wednesday, March 08, 2017, 14:09, David Wang, ITE, Maintenance, TM2, , ITE IG1S increasing. ITE_IGIS_surge.pngITE_IG1S_and_PNG4.pngITE_IG1S_back_to_normal_overnight.pngITE_IG1S_behavior_from_Feb_08th_to_Mar_10th.png
By retrieving data further, It has been found no directly relationship between IG1S surging and dump plug water opening. Vacuum surging is 10minutes
ahead dump water supply to circuit. SEE attachment 1. Also, The ITE IG1S start to behavior unusual in middle of Feburary. See attachment 2. Today, 
ITE IG1S is still slowly climbing up. I decide to leak check ITE vacuum vessel. Before  leak check, for more information and trouble shooting. I closed
Entry  Thursday, March 16, 2017, 10:32, David Wang, Spent Target Vault, Repair, TM4, , TM4 and its silo rust photos 13x
I watched rust on TM4 and its silo. Most of rust are on est side of module and silo. See attachments
Entry  Tuesday, March 21, 2017, 11:59, David Wang, Conditioning Station, Repair, TM4, , Rust inpsection on TM4 service cap inside surface and shielding plug surface.  11x
Yasmine and I did a rust inpsection on TM4 service cap inide surface and shielding plug surface. No rust has been found. Also, all steel bolts on this
surface look fine. The inside of silo held this module are rust free as well.  See attachments