ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1391   Thursday, November 03, 2016, 09:01 David WangConditioning StationStandard OperationTM4 TCS water system has been started for TM4.The system works fine. All water signals
to TM4 at TCS are normal. HV cover is installed
on to TM4 at TCS.
  
  1393   Tuesday, November 08, 2016, 07:47 David WangConditioning StationStandard OperationTM4 TCS water and vacuum pumps are switched offTCS is vented. TM4 is disconnected and
TCS.
  
  1396   Tuesday, November 08, 2016, 14:45 David WangITEMaintenanceTM4 TM4 has been moved to ITE and connected there.All ITE and TM4  turbo pumps are started.
The east station pumping down is good so
far.
  
  1397   Tuesday, November 15, 2016, 07:53 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)Update TH schedules . See attachments  Target_Hall_shedule_131_Sep_to_Dec.pdfTarget_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131__Sep_to_Dec_2016.pdf 
  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched offTCS will be vented tomorrow morning for
TM2 moving.
  
  1403   Wednesday, November 23, 2016, 16:10 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I leak checked TM2 HS line with
new UCx target installed. Helium spray 
2 seconds on each joint and 10seconds flushing
  
  1404   Wednesday, November 23, 2016, 16:21 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.All vacuum pumps have been started. Air
ballast 50seconds on roughing pump. Everything
is good  so far.
  
  1406   Thursday, November 24, 2016, 10:30 David WangConditioning StationStandard OperationTM2 HV cover is installed on TM2 at TCSInterlock key  are returned back to
B2 level.TM2 is ready for HV conditioning
and heating up at TCS.
  
  1408   Tuesday, November 29, 2016, 06:27 David WangConditioning StationStandard OperationTM2 TCS water pumps are stoppedArgon venting on TCS and TM2 is processing   
  1409   Tuesday, November 29, 2016, 07:50 David WangConditioning StationStandard OperationTM2 TM2 is disconnected at TCS.Argon venting is done.   
  1410   Tuesday, November 29, 2016, 12:57 David WangITWStandard OperationTM2 TM2 is connected in ITWAll turbo pumps are started. Water system
and water signals have been checked. Pumping
down on ITW and TM2 is good so far.
  
  1412   Wednesday, November 30, 2016, 16:31 David WangConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.All water circuits are by passed on the
top of TM3. Water pumps and vacuum turbo-
pumps are started. Everything is ready for
  
  1413   Saturday, December 03, 2016, 10:01 David WangITWRepairTM2 venting ITW and TM2 with argon.A short between TM2 EE and bias is produced
yesterday during tube heater ramp up. 
Alex asked for an argon venting on ITW to
  
  1415   Monday, December 05, 2016, 10:10 David WangITWStandard OperationTM2 Five shielding blocks have been transferred from ITE to ITW. The ITW is configured to take proton beam.   
  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pumpTCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S.
We will use TCS to take TM2 tomorrow afternoon.
  
  1419   Thursday, January 12, 2017, 14:24 David WangITWStandard OperationTM2 ITW primary and secondary vacuum vessel winter shut down leak check.TM2 is located in ITW for this leak check.
Leak detector is installed between ITW BV2s
as before. LD base leak rate 0.0XE-9atm.cc/sec,
  
  1420   Monday, January 16, 2017, 09:32 David WangITWStandard OperationTM2 Helium pressure test on TM2 water llines at ITWTM2 helium pressure test result at ITW.
70 psi helium 3 minutes on each circuit.
LD base LR0.0XE-9atm.cc/sec  BP 0.0XE-4torr. 
  
  1422   Wednesday, January 18, 2017, 09:55 David WangITEStandard OperationTM4 ITE and TM4 2017 winter shut down leak check.ITE and TM4 2017 winter shut down leak
check are finished. All ITE primary, secondary
vacuum vessel and TM4 water lines are good.
  
  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut downUpdated target hall schedule for 2017 winter
shut down. See attachments 1,2
Update schedule after Febiad beam
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1425   Tuesday, January 24, 2017, 15:24 David WangConditioning StationStandard OperationTM2 TM2 electrical check and leack check.I did electrical check before and after
Fefiad target installation on TM2. The RU
(coil) Is till short to 60KV as before. Other
  