  1354   Monday, September 19, 2016, 08:28 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)Post new  target hall Excel sheet
schedule for beam schedule 131. See attachment
1,2
 Target_Hall_shedule_131__Sep_to_Dec_2016.pdfTarget_Hall_shedule_131__Sep_to_Dec_2016.xlsxTarget_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf 
  1356   Tuesday, September 20, 2016, 11:41 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.TM4 has been disconnected in ITE. No water
line purge on HS and 3 water circuits are
looped after disconnection. The HALCW system
  
  1357   Tuesday, September 20, 2016, 11:48 David WangAssembly/Bench TestDevelopment  A silo and blue steel frame are removed out of TH A silo and blue steel frame are removed
out of TH this morning. They are transferred 
through ante room, and moved to experimental
  
  1358   Thursday, September 22, 2016, 13:04 David WangSouth Hot-CellStandard OperationTM4 SHC, TM4 leak check on HS line.Chad and I leak checked the TM4 HS line
after new target installation. base leak
rate:0.0Xe-9 atm.cc/sec.  No response
  
  1359   Friday, September 23, 2016, 07:49 David WangConditioning StationStandard OperationTM4 TM4 has been moved and connected at TCSAll TCS and TM4 turbo-pumps were started
yesterday. Overnight pumping down is good
so far.
  
  1363   Tuesday, September 27, 2016, 07:30 David WangConditioning StationStandard OperationTM4 TM4 has been disconnected at TCSTCS water system and vacuum system are
turned  off this morning. The TCS and
TM4 are vented.
  
  1365   Wednesday, September 28, 2016, 13:43 David WangITEStandard OperationTM4 TM4 has been connected at ITEAll ITE turbo pumps have been started since
yesterday afternoon. The ITE and TM4 pumping
down is good so far.
  
  1366   Wednesday, September 28, 2016, 13:47 David WangConditioning StationStandard Operation  TCS pumping down during mini-shut down.A steel plate  is covered on TCS.
TCS roughing pump  is started now. The
TCS will be pumping down during mini-shut
  
  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016) Weekly update TH schedule for beam schedule
131. See attachments 1,2
 Target_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf 
  1368   Tuesday, October 04, 2016, 09:18 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1370   Wednesday, October 12, 2016, 10:00 David WangITWStandard OperationTM2 TM2 was disconnected at ITWTM2 was disconnected at ITW. 3 water circuits
in ITW gave been looped to keep 75 GPM water
flow to ITW. HS line was purged at HS. RPG
  
  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stoppedArgon venting is started   
  1381   Monday, October 24, 2016, 14:54 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I did the leak check on TM2 heat
shield line. LD base leak rate:0.0xE-9atm.cc/sec.
Base pressure:0.0X E-9 torr. The line is
  
  1383   Tuesday, October 25, 2016, 15:10 David WangITWStandard OperationTM2 TM2 has been connected at ITWAll turbo pumps are started. Two gas valves
for Febiad run are opened. Pumping down is
good so far.
  
  1384   Wednesday, October 26, 2016, 12:33 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)Update TH schedule after job delay on TM2
Febiad target. Everything should be back
to schedule on last two targets. See attachments.
 Target_Hall_shedule_131__Sep_to_Dec_2016.pdfTarget_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf 
  1385   Tuesday, November 01, 2016, 14:53 David WangITEStandard OperationTM4 TM4 was disconnected at ITETM4 was disconnected at ITE this morning.
It was moved to SHC  after. No alpha
alarm issue has been happened during and
  
  1386   Tuesday, November 01, 2016, 14:54 David WangITEStandard OperationTM4 TM4 was disconnected at ITETM4 was disconnected at ITE this morning.
It was moved to SHC  after. No alpha
alarm issue has been happened during and
  
  1387   Tuesday, November 01, 2016, 14:58 David WangSouth Hot-CellStandard OperationTM4 SHC, TM4 leak check on HS line.Chad and I did a leak check on TM4 HS line
with new Ta target installed. Base leak rate
0.0xE-9 atm.cc/sec. base pressure 0.0XE-4.  
  
  1389   Wednesday, November 02, 2016, 13:41 David WangConditioning StationStandard OperationTM4 TM4 has been connected at TCS. All turbo-pumps are started. The pumping
down is good so far.
  
  1390   Thursday, November 03, 2016, 08:57 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at TCS70 psi helium ,2minutes to  TM4 HS
line. LD base leak rate 0.0xE-9 atm.cc/sec.
No leak.
  