1303
|
Wednesday, August 03, 2016, 09:56 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) | Update schedule weekly. See attachments
1,2 |
 |
|
1309
|
Tuesday, August 09, 2016, 07:15 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx17 | TM4 has been disconnected at TCS | I stopped TCS water pumps this morning
. The argon venting for TCS is in processing. |
|
|
1313
|
Wednesday, August 10, 2016, 11:30 |
David Wang | ITE | Standard Operation | TM4 | UC#17 | TM4 has been connected at ITE | Dan and I connected TM4 in ITE yesterday.
It is pumping down at ITE now. Everything
is fine so far. |
|
|
1316
|
Thursday, August 11, 2016, 10:37 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 service tray cover plate ITA2108 has been removed. | Requested by Aurelia, and approved by Friedhelm,
TM3 service tray cover plate ITA2108 has
been remove out of the module. The plated |
|
|
1319
|
Monday, August 15, 2016, 10:08 |
David Wang | ITE | Standard Operation | TM4 | UC#17 | 5 Shielding blocks have been transferred from ITW to ITE. | Dan and I transferred 5 shielding blocks
from ITW to ITE. The ITE is configured to
take proton beam. |
|
|
1320
|
Monday, August 15, 2016, 10:15 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) | Weekly update target hall schedule. Everything
on schedule are finished on time.
See attachment. |
 |
|
1322
|
Tuesday, August 16, 2016, 12:35 |
David Wang | Conditioning Station | Repair | TM3 | | CS vacuum pumps have been stopped | The TCS is venting now. The TM3 blue insulator
replacement job will be started soon. |
|
|
1331
|
Wednesday, August 24, 2016, 10:41 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was disconnected in ITW yesterday. | TM2 was disconnected in ITW yesterday and
moved to SHC. |
|
|
1332
|
Wednesday, August 24, 2016, 10:44 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. | Chad and I leak checked Tm2 Hs line with
new target installed. Base LR 0.0Xe-9 atm.cc/sec.
No leak has been found. This line will be |
|
|
1333
|
Wednesday, August 24, 2016, 10:45 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 vacuum system has been connected at TCS | Start of roughing now. |
|
|
1337
|
Thursday, August 25, 2016, 08:36 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 HS water lline | I did a helium pressure test on TM2 HS
water line at TCS. Leak detector base leak
rate only could get to 1.8x e-8 atm.cc/sec |
|
|
1338
|
Thursday, August 25, 2016, 08:43 |
David Wang | Conditioning Station | Standard Operation | TM2 | | All TM2 connections to TCS are done. | The HV cover is installed. The Faraday
cage at B2 level is locked also.The TCS and
TM2 are still pumping down. Everything is |
|
|
1339
|
Thursday, August 25, 2016, 13:59 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep, 2016) | Weekly update schedule. See attachment
1,2. |
 |
|
1341
|
Monday, August 29, 2016, 13:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been disconnected at TCS | I stopped TCS water pumps and vacuum pumps
also. TM2 and TCS will be vented tomorrow
morning. |
|
|
1343
|
Tuesday, August 30, 2016, 13:17 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected at ITW | ITW turbo pumps have been
started. |
|
|
1344
|
Tuesday, September 06, 2016, 10:05 |
David Wang | ITW | Standard Operation | TM2 | | 5 Shielding blocks have been transferred from ITE to ITW. | 5shielding blocks have been transferred
from ITE to ITE. ITW is configured to take
proton beam. |
|
|
1347
|
Thursday, September 08, 2016, 16:28 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 blue insulators have been replaced. | All TM3 blue insulators except Gas,EL,
and 60 KV common on top of the module
have been replaced with new designed insulators. |
|
|
1348
|
Thursday, September 08, 2016, 16:30 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. | start of roughing now.
start of TCS and TM3 turbo-pumps.
Everything is good so far. |
|
|
1349
|
Monday, September 12, 2016, 09:25 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 leak checked at TCS | After blue insulators replacement, TM3
service cap are leak checked. LD base leak
rate 0.0xe-9 atm.cc/sec. I sprayed lots helium |
|
|
1351
|
Wednesday, September 14, 2016, 11:54 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 is disconnected at TCS. | TM3 is disconnected at TCS and ready
to be moved to silo. |
|