  1288   Monday, July 18, 2016, 14:14 David WangConditioning StationRepairTM3 TM3 leak checked at TCS

Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good.  Helium pressure test on  TM3 water lines(except GE, HS, and Window) were done. Leak detector has no response at 0.0xE-9 atm.cc/sec. They are leak free.

  1290   Friday, July 22, 2016, 10:57 David WangConditioning StationRepairTM3 TM3 has been moved and connected at TCS

I started vacuum system.

I started TCS water system. The chiller does not work properly still. But, It will not affect the TM3 HV conditioning.  HV cover is installed on TM3 in TH. The module is ready for HV conditioning.

  1298   Tuesday, August 02, 2016, 15:22 David WangConditioning StationStandard OperationTM4UC#17TM4 with new target has been connected at TCS

It is being pumped now at TCS.

  1301   Wednesday, August 03, 2016, 09:45 David WangConditioning StationStandard OperationTM4UC#17Helium pressure test on TM4 HS line at TCS

Helium pressure test on TM4 HS line at TCS  is done.Leak detector 0.0X E-9atm.cc/sec.  5minutes, 70psi helium.    No response on LD.

  1302   Wednesday, August 03, 2016, 09:49 David WangConditioning StationStandard OperationTM4 TM4 is ready for conditioing at TCS.

I started TCS water system and installed HV cover onto TM4.  The TM4 containment box is supplied with water also. TM4 is ready for conditioning at TCS.

  1303   Wednesday, August 03, 2016, 09:56 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)

Update schedule weekly. See attachments 1,2

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.mpp
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
  1309   Tuesday, August 09, 2016, 07:15 David WangConditioning StationStandard OperationTM4UCx17TM4 has been disconnected at TCS

I stopped TCS water pumps this morning . The argon venting for TCS is in processing.

  1313   Wednesday, August 10, 2016, 11:30 David WangITEStandard OperationTM4UC#17TM4 has been connected at ITE

Dan and I connected TM4 in ITE yesterday. It is pumping down at ITE now. Everything is fine so far.

  1316   Thursday, August 11, 2016, 10:37 David WangConditioning StationRepairTM3  TM3 service tray cover plate ITA2108 has been removed.

Requested by Aurelia, and approved by Friedhelm, TM3 service tray cover plate ITA2108 has been remove out of the module. The plated is checked for active and contamination after removal. Then,It is double bagged, sealed ,  tagged, and placed downstairs in TH between south wall and green block . The ram contact reading on the plate is about 10 usv/hr.  We will do anther TM3 HV test at TCS without this cover plate.

  1319   Monday, August 15, 2016, 10:08 David WangITEStandard OperationTM4UC#175 Shielding blocks have been transferred from ITW to ITE.

Dan and I transferred 5 shielding blocks from ITW to ITE. The ITE is configured to take proton beam.

  1320   Monday, August 15, 2016, 10:15 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)

Weekly update target hall schedule. Everything on schedule are finished  on time.   See attachment.  

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
  1322   Tuesday, August 16, 2016, 12:35 David WangConditioning StationRepairTM3  CS vacuum pumps have been stopped

The TCS is venting now. The TM3 blue insulator replacement job will be started soon.

  1331   Wednesday, August 24, 2016, 10:41 David WangITWStandard OperationTM2 TM2 was disconnected in ITW yesterday.

TM2 was disconnected in ITW yesterday and moved to SHC.

  1332   Wednesday, August 24, 2016, 10:44 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.

Chad and I leak checked Tm2 Hs line with new target installed. Base LR 0.0Xe-9 atm.cc/sec.   No leak has been found. This line will be helium pressured at TCS later.

  1333   Wednesday, August 24, 2016, 10:45 David WangConditioning StationStandard OperationTM2 TM2 vacuum system has been connected at TCS

Start of roughing now.

  1337   Thursday, August 25, 2016, 08:36 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 HS water lline

I did a helium pressure test on TM2 HS water line at TCS. Leak detector base leak rate only could get to 1.8x e-8 atm.cc/sec at this moment. Applied 5 minutes 70psi helium on it. No leak has been found at this level. I connected water to this circuit after the test for weekend TM2 conditioning at TCS.

I will do another helium pressure test after the conditioning. The LD base leak rate should be 0.0Xe-9 atm.cc/sec at that time.

2016-08-29: LD Base leak rate 0.0xe-9atm.cc/sec.TM2 HS line helium pressure check again after conditioning. 70psi helium 5minutes. no response on LD. HS line is perfectly sealed.

  1338   Thursday, August 25, 2016, 08:43 David WangConditioning StationStandard OperationTM2 All TM2 connections to TCS are done.

The HV cover is installed. The Faraday cage at B2 level is locked also.The TCS and TM2 are still pumping down. Everything is good so far.

  1339   Thursday, August 25, 2016, 13:59 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep, 2016)

Weekly update schedule.  See attachment 1,2.

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
  1341   Monday, August 29, 2016, 13:34 David WangConditioning StationStandard OperationTM2 TM2 has been disconnected at TCS

I stopped TCS water pumps and vacuum pumps also.   TM2 and TCS will be vented tomorrow morning.

  1343   Tuesday, August 30, 2016, 13:17 David WangITWStandard OperationTM2 TM2 has been connected at ITW

  ITW turbo pumps  have been started.