  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015

See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.

Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  890   Monday, April 20, 2015, 07:27 David WangITEStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015

Weekly target hall schedule update.2015-04-20

weekly target hall schedule update 2015-04-27 attachments 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  900   Monday, April 27, 2015, 17:09 Grant MinorITEDevelopmentTM2 TM2 - New Source Tray - Water Block Seal Groove Inspection Report

The water blocks soldered to the TM2 cooling lines (see Ref. Assy. ITA6144) were inspected.

See attached inspection reports and drawings.

It was found that only 18% of the seal groove diameters and 55% of the depths were in spec.

The source tray must be tested on the test stand with c-seals to ensure that these blocks will seal properly on the module.

Attachment 1: IMG_1859.JPG
IMG_1859.JPG
Attachment 2: TM2_New_Source_Tray_Water_Block_Inspection_Results_24_April_2015.pdf
TM2_New_Source_Tray_Water_Block_Inspection_Results_24_April_2015.pdf
Attachment 3: TM2_water_block_inspect_24Apr2015.pdf
TM2_water_block_inspect_24Apr2015.pdf TM2_water_block_inspect_24Apr2015.pdf TM2_water_block_inspect_24Apr2015.pdf TM2_water_block_inspect_24Apr2015.pdf
Attachment 4: TM2_New_Source_Tray_Water_Block_Inspection_Results_April_2015.xlsx
  921   Monday, June 01, 2015, 11:23 Travis CaveITEStandard OperationTM4Ta#45Module moved

TM#4 with Ta#45 has been moved from the east target station to the south hot cell.

  938   Wednesday, June 10, 2015, 10:02 Travis CaveITEStandard OperationTM4SiC#31Module moved

TM#4 has been moved from the conditioning station to the east target station.

  939   Wednesday, June 10, 2015, 11:49 David WangITEStandard OperationTM4SiC #31TM4 has been connected in ITE

Dan and I connected TM4 in ITE. At this stage, water is supplied to TM4 only. We checked the TM4 water signals from electrical room.They are good. The turbo-pumps will be started today once the roughing is done.

  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015

Weekly update the schedule after some jobs have been finished in this week.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.

5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.

  1016   Monday, July 27, 2015, 15:34 David WangITEStandard OperationTM4 Leak check on TM4 HS water line with new UCX target. at SHC

Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow.

  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replaced

Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken  pump is bagged and stored at west end of TH.

  1025   Wednesday, July 29, 2015, 08:59 Travis CaveITEStandard OperationTM4UC#13Module moved

TM#4 with UC#13 has been moved from the conditioning station to the east target station.

  1026   Wednesday, July 29, 2015, 10:14 David WangITEStandard OperationTM4 TM4 has been connected in ITE

Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good.

  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Weekly update of Target Hall schedule after so many jobs have been finished in this week.  See attachment 1, 2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015

Weekly update target hall schedule and activities. See attachment 1,2

Update and extend Target Hall schedule to Sep 08.  See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1072   Tuesday, September 22, 2015, 11:12 Travis CaveITEStandard OperationTM4UC#13Module moved

TM#4 with UC#13 has been moved from the east target station to the south hot cell.