1231
|
Friday, May 13, 2016, 10:08 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 HS and window line at CS with new Lp Ta target |
These two lines are passed helium pressure test this morning. The LD base leak rate 0.0 X E-9 atm.cc/sec. The base pressure 0.0 X E-4 torr. Helium pressure 70 psi. applied helium to both line for 5minutes each. No response on LD during the test. |
1232
|
Friday, May 13, 2016, 10:12 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 water lines, heaters, EE, and EL are connected at TCS. |
The HV cover is installed on to TM2 after the connections. The HV key is returned back to B2 level. The TCS Faraday cage is locked. |
1234
|
Monday, May 16, 2016, 11:16 |
David Wang | ITW | Standard Operation | TM1 | | ITW, TM1 turbo-pumps are swithched off |
I let isac opp switched off ITW turbo-pumps. The argon vent valve in electrical room is opened. The ITW argon venting will be started soon. |
1240
|
Friday, May 20, 2016, 08:13 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#48 | I switched off TCS and TM2 water system |
Disconnected TM2 at TCS(vacuum system still on). Purged all TM2 water lines for helium pressure test. |
1241
|
Friday, May 20, 2016, 10:38 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#48 | Helium pressure test on TM2 with new Lp Ta target |
LD base LR: 0.0 X E-9. Base pressure:0.0 X E-4. 70 psi helium. 5 minutes each circuit.
window |
0.0X E-9 |
|
HS |
0.0X E-9 |
|
EE |
0.0X E-9 |
|
Ta+ |
0.0X E-9 |
|
Ta- |
0.0X E-9 |
|
coil1 R-U |
0.0X E-9 |
|
Coil2 P-Q |
5.0X E-9 |
|
Tube- |
5.1X E-9 |
|
Tube+ |
1.1X E-8 |
|
MSP |
3.5X E-9 |
|
The bigger leak found on MSP before was gone. Leak rate are smaller on all circuits comparing to before.
The leak rate on 1 hour total lines test at 70 psi is better also which is 6.6 XE-8 atm.cc/sec this time. |
1242
|
Tuesday, May 24, 2016, 10:39 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#48 | TM2 and TCS turbo-pumps have been switched off this morning. |
The TCS and TM2 are still under vacuum without venting |
1243
|
Tuesday, May 24, 2016, 10:42 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Weekly update the TH schedules. See attachments 1, 2,3. |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.xlsx
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
1246
|
Wednesday, May 25, 2016, 14:08 |
David Wang | ITW | Standard Operation | TM2 | Ta#48 | TM2 has been connected in ITW |
TM2 has been connected in ITW by Dan.M and David.W. All turbo-pumps have been started. Everything is good so fine. |
1249
|
Thursday, June 02, 2016, 11:59 |
David Wang | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment. |
Attachment 1: 5K_mega_check_on_TM3.pdf
|
|
1253
|
Tuesday, June 07, 2016, 11:36 |
David Wang | ITE | Standard Operation | TM4 | Ta#47 | TM4 has been disconnected in ITE. |
Dan and I disconnected TM4 in ITE. HS water lines has been purged. |
1254
|
Tuesday, June 07, 2016, 11:37 |
David Wang | ITE | Standard Operation | TM4 | Ta#47 | TM4 has been moved from ITE to SHC |
Bill and Yasmine did the move. Everything is good. |
1255
|
Tuesday, June 07, 2016, 11:42 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#47 | electrical check on TM4 with old Ta target at SHC. |
I did an electrical check on TM4 with the old target still installed. The number is a little bit low on 500V mega check between chassis and 60KVbias which is 146Mohm. Others are good. See attachment
I wrote all OL to 0 in attachment 1 ohmmeter check. Please See attachment 2 for correction. |
Attachment 1: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
Attachment 2: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
1256
|
Tuesday, June 07, 2016, 17:11 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 UCx16 electrical check and leak check at SHC |
Chad and I finished the TM4 UCx6 electrical check and leak check at SHC. Leak check result on HS line is good. There is a dead short between "Z" repellor and HS during the first time electrical check. The dead short disappeared after re- installation of UCx 14 target onto TM4. See attachment
Anders and I did another electrical check on TM4 at TCS under vacuum. See attachment 2 |
Attachment 1: UCX_16_electrical_test.pdf
|
|
Attachment 2: electrical_check._TM4_UCx16_at_TCS..pdf
|
|
1257
|
Tuesday, June 07, 2016, 17:14 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 with UCx16 target has been moved from SHC to TCS. |
Bill and Yasmine did the move remotely this afternoon. The move is successful. |
1258
|
Tuesday, June 07, 2016, 18:17 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 and TCS turbo pumps are started. |
TM4 and TCS vacuum system are connected. Turbo pumps are started. Everything is fine so far. |
1260
|
Thursday, June 09, 2016, 08:37 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 with UCx16 helium pressure test at TCS |
I did a helium pressure test on TM4 at TCS with UCX16 target installed on the module. No leak has been found on all using water lines in TM4. See attachment for detail. |
Attachment 1: TM4_withUCx16_helium_pressure_test_at_TCS.pdf
|
|
1261
|
Thursday, June 09, 2016, 09:44 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 has been connected at TCS |
It is ready for HV conditioning/ heating. |
1262
|
Thursday, June 09, 2016, 10:04 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Weekly update . |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
1263
|
Tuesday, June 14, 2016, 08:04 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 has been disconnected at TCS |
The TM4 and TCS are vented with argon. |
1265
|
Tuesday, June 14, 2016, 11:20 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE |
TM4 and ITE are under roughing now. |