  594   Wednesday, February 05, 2014, 14:12 Travis CaveSpent Target VaultStandard Operation  Targets moved from mini storage to F-308sAll targets in the mini storage (4) have
been moved from there and placed into the
F-308s and those have been moved to the mech
  
  595   Friday, February 07, 2014, 10:29 chad fisherSouth Hot-CellRepairTM2 TM2 C.B. and circuit DContainment box has been removed and the
blank off from circuit D has been removed
for inspection of both the blank off and
 TM2_20140207_1.jpgTM2_20140207_2.jpg 
  596   Tuesday, February 11, 2014, 13:56 chad fisherSouth Hot-CellRepairTM2 waterblock cleaningNew cleaning and polishing pads have been
inserted onto the hot cell as well as rubber
bungs and a new blank off.
 TM2_20140207_2.jpgTM2_20140211_2.jpg 
  597   Thursday, February 13, 2014, 09:24 David WangSouth Hot-CellRepairTM2 Leak check TM2 tube heater (+) water line with rubber insert blocked WB in SHCChad and I  did the Leak checked TM2
tube heater (+) water line  with rubber
insert plugged water block on " D" 
 001.JPG002.JPG003.JPG004.JPG 
  598   Thursday, February 13, 2014, 13:30 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.Chad and I did the pressure test on TM2tube
heater+(D) water  line at SHC with shop
air.We tested from 30psi to 80psi on both
  
  599   Thursday, February 13, 2014, 14:15 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.

    

       
            
 007.JPG008.JPG013.JPG 
  600   Thursday, February 13, 2014, 14:23 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(elastic seal) installed on WB.Chad and I did the leak check on TM2 tube
heater (+) water line  with blank off(
+ elastic o ring seal) installed on "D" 
 005.JPG001.JPG 
  601   Monday, February 17, 2014, 09:32 David WangConditioning StationRepairTM2 helium pressure test on TM2 tube heater +(D) water line.I did the helium pressure test on Tube
heater+ line this morning. The  vacuum on
CS and TM2 are very good. The base lake rate
 6x 
  602   Tuesday, February 18, 2014, 11:26 David WangConditioning StationRepairTM2 I stopped turbo pumps and disconnected vacuum system on TM 2 and CSI stopped turbo pumps and disconnected
vacuum system on TM2 and CS. The TM2 will
be moved to SHC for C seal installation on
  
  604   Thursday, February 20, 2014, 11:04 chad fisherSouth Hot-CellRepairTM2 Readying TM2 for C-Seal Leak CheckContainment box has been removed and water
block jig installed.
 TM2_20140220_01.jpg 
  605   Monday, February 24, 2014, 11:05 chad fisherSouth Hot-CellRepairTM2 Circuit D blank offThe blank off with the o-ring has been
removed, manipulator fixed, circuit D water
block sealinhg surfaces cleaned and blank
  
  606   Monday, February 24, 2014, 12:09 chad fisherSouth Hot-CellRepairTM2 C-seal blank off testCircuit D has passed the vacuum leak check.
Jig has been removed and containment box
re-installed for move to conditioning station.
 TM2_20140224_1.jpg 
  608   Tuesday, February 25, 2014, 06:53 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(C-seal) installed on WB.Chad and I did the leak check   on
TM2 tube heater (+) water line  with
blank off and C-seal  installed on 
  
  609   Tuesday, February 25, 2014, 10:00 David WangConditioning StationRepairTM2 helium pressure test on TM2 tube heater (+) water line with blank off(C-seal) installed on WB.I did the helium pressure  test 
on TM2 tube heater (+) water line  with
blank off(C-seal) installed on  water
 10x 
  612   Thursday, March 06, 2014, 06:28 David WangConditioning StationMaintenanceTM1 TM1 had been moved from silo to CSTM1 has been successfully moved from silo
to CS. The CS vacuum system is connected 
to TM1. Turbo pumps on TM1 and CS have been
  
  613   Thursday, March 06, 2014, 06:58 David WangITEMaintenanceTM3 ITE vacuum and leak check on ITE BL2A window flange.ITE and TM3 Turbo pumps have been started
successfully yesterday. The vacuum reading
on all ITE high vacuum gauges are at low
  
  614   Thursday, March 06, 2014, 12:59 David WangConditioning StationMaintenanceTM1 Restart TM1 and CS TPs Restarted TM1 and CS turbo pumps after
the power off. Everything is fine .
  
  615   Thursday, March 06, 2014, 14:12 David WangConditioning StationStandard OperationTM1 TM1 air to vacuum and water lines leak check at CS.TM1 air to vacuum and water lines leak
check at CS are finished this afternoon.
The leak detector  is hooked directly
 8x 
  616   Friday, March 07, 2014, 12:45 David WangITEStandard OperationTM3 TM3 and ITE air to vacuum leak check and TM3 water lines helium test.With TM3 located in ITE, All air to vacuum
seals  on ITE primary and secondary
vacuum vessel have been leak  checked
 001.JPG002.JPG003.JPG010.JPG013.JPG 
  618   Tuesday, March 11, 2014, 10:47 Travis CaveITERepair  entrance module moveITE entrance module has been moved from
the east station to the south east silo.
  