2082
|
Thursday, March 12, 2020, 13:42 |
David Wang | ITE/ITW | Development | | | New ITE IGLIS cables installation | New IGLIS cables installation is done.
Two bundle of new cables are pulled from
ITE to electrical room. They are in one PVC |
|
203
|
Tuesday, November 06, 2012, 11:34 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | | Nb#7 Removal | Attached are pre-removal pictures of NB#7
and the inside face of the containment box
cover before cleaning. |
![IMG_0797[1].JPG IMG_0797[1].JPG](attachment.png) ![IMG_0798[1].JPG IMG_0798[1].JPG](attachment.png) |
210
|
Thursday, November 08, 2012, 09:37 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#7 | Nb#7 Autopsy | Nb#7 was dismantled and ready for inspection. |
|
2627
|
Thursday, June 27, 2024, 09:49 |
David Wang | North Hot-Cell | Standard Operation | | Nb#10 | Nb#10target has been remotely transferred from NHC to SHC. | Nb#10target has been remotely transferred
from NHC to SHC. |
|
2668
|
Tuesday, August 20, 2024, 11:53 |
Carla Babcock | South Hot-Cell | Standard Operation | | Nb#10 | Nb#10 PIE | Nb#10 never worked online - repeller had
no effect on the beam and one of the RF wires
was touching HVC. Max 60pA was seen on the |
|
182
|
Tuesday, September 18, 2012, 13:47 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#7 | Nb #7 install Cover Baseline | Nb #7 was installed and tested today.
Inside face of the containment box
cover was cleaned with methanol and a baseline |
 |
2429
|
Monday, April 03, 2023, 07:55 |
chad fisher | North Hot-Cell | Standard Operation | | | NHC, SHC field check | NHC is 1.26 mSv/h inside approximately
.5m from table surface, between manipulators
|
|
1416
|
Friday, December 09, 2016, 14:58 |
Isaac Earle | North Hot-Cell | Development | | | NHC service area floor and top of roof block painted | The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted |
 |
1859
|
Friday, January 18, 2019, 10:26 |
Isaac Earle | North Hot-Cell | Development | | | NHC sealing improvements and repeat of RH test for LED lights | The following NHC development work was
completed under WP I2019-01-09-4:
Location of RH feature |
|
1443
|
Thursday, March 02, 2017, 15:02 |
Isaac Earle | North Hot-Cell | Development | | | NHC roughing filter installed | The roughing filter assembly (RFM0001D)
has been installed at the ventilation exhaust
hole on the NHC partition wall. The |
  |
1533
|
Thursday, May 11, 2017, 16:10 |
Isaac Earle | North Hot-Cell | Development | | | NHC roof block to TH north wall gap sealed | The gap between the north face of
the NHC roof block and the target hall north
wall in the area where the NHC inlet ducting |
|
1839
|
Monday, December 10, 2018, 15:31 |
Isaac Earle | North Hot-Cell | Development | | | NHC remote connection testing with manipulators | The following tests have been successfully
completed using the NHC manipulators:
Ventilation pre-filter |
|
1518
|
Tuesday, May 02, 2017, 09:48 |
Isaac Earle | North Hot-Cell | Development | | | NHC polycarbonate window cover panel installed | The window cover panel has been installed
on the hot side of the NHC shielding window
according to drawing IRH1638. It was |
    |
1423
|
Wednesday, January 18, 2017, 11:53 |
Isaac Earle | North Hot-Cell | Development | | | NHC partition wall installation complete | The final panels of the partition
wall were installed today as per drawing
IRH1609. Sealing, finishing, and painting |
|
1635
|
Friday, October 06, 2017, 11:12 |
Isaac Earle | North Hot-Cell | Development | | | NHC module port shield block and TCS vessel shield block installed | The NHC module port shield block
(IRH1645) and the TCS vessel shield block
(IRH1646) were installed yesterday in the |
    |
1564
|
Friday, June 23, 2017, 17:28 |
Isaac Earle | North Hot-Cell | Development | | | NHC module flange and cameras installed | The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing |
    |
1841
|
Tuesday, December 18, 2018, 11:13 |
Isaac Earle | North Hot-Cell | Development | | | NHC manipulator slave-end swap, RH test, and various other work | The following
North Hot Cell work was completed over the
last week under work permit I2018-12-12-1: |
|
1664
|
Friday, December 01, 2017, 16:42 |
Isaac Earle | North Hot-Cell | Repair | | | NHC manipulator service visit | Pete Dudley, manipulator service technician
from CRL, was on site from Nov 27-30 to service
the NHC Model N manipulators (See E-log entry |
 |
1440
|
Friday, February 24, 2017, 15:12 |
Isaac Earle | North Hot-Cell | Development | | | NHC interior walls/floor/ceiling re-finished, sealed, and painted | The North Hot Cell interior walls, floor,
and ceiling were re-finished, sealed, and
painted by Omni Coating from Feb 6 - 17 under |
8x |
1560
|
Thursday, June 15, 2017, 11:29 |
Isaac Earle | North Hot-Cell | Development | | | NHC inlet ducting installed | The North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block. A |
   |