546
|
Monday, November 18, 2013, 16:42 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Testing | The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this |
 |
|
547
|
Monday, November 18, 2013, 16:44 |
Bevan Moss | Conditioning Station | Standard Operation | | | Testing of cooling package | I have tested all of the compressors
for TCS. All are operational and cycled as
they should. |
|
|
549
|
Tuesday, November 19, 2013, 14:24 |
David Wang | ITE | Repair | | | ITE TP3 | Hi
all, The old ITE TP3 pump is
moved out and the new pump is in |
|
|
550
|
Tuesday, November 19, 2013, 16:55 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV conditioning | HV conditioning of TM2 continued
today. At ~53.5kV the module started to spark
externally to the HV cover. This is the first |
   |
|
553
|
Wednesday, November 20, 2013, 13:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV testing of TM2 | HV testing without the cover continued
today. With the EINZEL lens at 30kV the target
module was able to achieve 58.7kV. At this |
 |
|
557
|
Tuesday, November 26, 2013, 14:10 |
Travis Cave | Crane | Maintenance | | | Thermal relay replaced | The bad thermal motor protection relay
for the crane has been replaced with a new
unit. Crane was tested in pendant(local) |
|
|
558
|
Wednesday, November 27, 2013, 12:50 |
Bevan Moss | South Hot-Cell | Standard Operation | TM3 | | Ground devices wiring check | Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V |
|
|
559
|
Wednesday, November 27, 2013, 15:24 |
Bevan Moss | South Hot-Cell | Maintenance | TM3 | | Wiring Harness Electrical Test | Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction |
|
|
560
|
Friday, November 29, 2013, 11:54 |
chad fisher | South Hot-Cell | Repair | TM3 | | Steerer short investegation | Using in cell camera and transit the suspect
line on the steerers was inspected as best
as possible. An existing photo of the complete |
  |
|
561
|
Friday, November 29, 2013, 11:57 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Steerer short investegation |
|
|
|
563
|
Tuesday, December 03, 2013, 09:58 |
David Wang | ITW | Standard Operation | TM4 | | I moved 5 shielding blocks from ITW to block storage area. | I moved 5 shielding blocks from ITW to
block storage area. |
|
|
564
|
Tuesday, December 03, 2013, 10:35 |
Travis Cave | ITW | Standard Operation | | | fields above and in the target station with blocks off | The blocks have been removed from the west
target station. The fields at the top of
the target pit at the railing at waist level |
|
|
565
|
Tuesday, December 03, 2013, 14:14 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV conditioning | It was attempted to HV condition
TM2 to 55kV and leave it operating there
for an hour to demonstrate stability. Unfortunately |
|
|
568
|
Wednesday, December 04, 2013, 11:15 |
David Wang | ITE | Repair | TM4 | | New bolts are installed on ITE TP3. | I installed 8 new bolts(3/8-16 UNC x1.25
STL) on the ITE TP3. The ITE TP3 replacement
job is done. Everything is connected back |
|
|
573
|
Thursday, December 05, 2013, 14:55 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Leak check on TM4 target heat shield | Chad and I leak checked TM4 heat shied
water circuit at SHC. The pumping down was
very good.Base leak rate 0.0xe-9 atm.cc/sec. |
|
|
574
|
Thursday, December 05, 2013, 14:57 |
David Wang | ITE | Standard Operation | TM4 | | Connected TM4 in ITW | I connected TM4 in ITE. All turbo pumps
have been started and wok fine including
new TP3. Everything is good so far. |
|
|
575
|
Friday, December 06, 2013, 15:09 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | TM2 no source tray 55kV 1 hour | Today 55kV was applied to TM2 and held
for over 1 hour with the EINZEL at 27.5kV.
There were 2 sparks and the current was unstable |
 |
|
577
|
Monday, December 09, 2013, 14:47 |
David Wang | ITE | Standard Operation | TM4 | | I moved 5 shielding blocks from block storage area to ITE. | I moved 5 shielding blocks to ITE. The
ITE is configured to take proton beam. |
|
|
578
|
Thursday, December 12, 2013, 11:14 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Chase Electrical Test | While under vacuum Travis and I completed
diagnostics of the HV chase. Majority of
the lines showed OL at 1kV but there were |
|
|
579
|
Thursday, January 09, 2014, 11:07 |
chad fisher | South Hot-Cell | Maintenance | | | Field Level | I have managed to reduce the field at the
broken manipulator from 12 mSv/h to 400 uSv/h. |
|