1102
|
Wednesday, October 14, 2015, 14:49 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Install new high current cables to TM2 |
I installed a set of new high current cables for TM2 Febiad run. The top of TM2 is configured to Febiad mode. See attachments |
Attachment 1: TM2_Febiad_High_current_cables_047.JPG
|
|
Attachment 2: TM2_Febiad_High_current_cables_048.JPG
|
|
Attachment 3: TM2_Febiad_High_current_cables_049.JPG
|
|
|
1103
|
Thursday, October 15, 2015, 08:07 |
David Wang | South Hot-Cell | Standard Operation | TM2 | no target | TM2 no target electrical check at SHC. |
I did a TM2 no target electrical check at SHC this morning. A to RU at 500v is 250K which is low. anode- x pin is dead short to 60kv bias. RU is dead short to 60kv bias( as before). see attachment |
Attachment 1: TM2_electrical_check_2015-10-16_no_target.pdf
|
|
|
1124
|
Monday, November 16, 2015, 08:04 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Update TH schedule according to changes. See attachment 1,2 .
update TH schedule weekly. See attachments 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1127
|
Monday, November 16, 2015, 10:37 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 has been disconnected at TCS. |
I stopped the TM3 and TCS vacuum pumps and water system. The TM3 is disconnected and vented. It will be moved to silo this afternoon. |
|
1138
|
Thursday, November 26, 2015, 06:25 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 vacuum has been connected in TCS. |
TM4 vacuum has been connected in TCS. All vacuum pumps were started yesterday. The pumping down of TM4 and TCS are good so far. |
|
1139
|
Thursday, November 26, 2015, 07:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Helium pressure test on TM4 HS line at CS |
I did helium pressure test on TM4 HS line at TCS this morning. 70psi helium 3 minutes, 0.0xE-9 atm.cc/sec base leak rate. No response. No leak. |
|
1140
|
Thursday, November 26, 2015, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 has been connected at CS |
TM4 has been connected at TCS. The water system is started. The TCS HV cover for TM4 is installed also. Basically, The TM4 is ready for conditioning. |
|
1142
|
Monday, November 30, 2015, 11:46 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Weekly update TH schedule according to changes. see attachment 1,2 .
Update TH schedule before the weekend. see attachment 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1143
|
Tuesday, December 01, 2015, 06:41 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Turned off TCS all vacuum pumps and water pumps. |
I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition. |
|
1146
|
Tuesday, December 01, 2015, 14:30 |
David Wang | ITE | Standard Operation | TM4 | UCx 13 | TM4 has been connected in ITE |
TM4 has been connected in ITE. All turbo-pumps are started. Everything is good so far. |
|
1153
|
Friday, January 22, 2016, 14:24 |
David Wang | South Hot-Cell | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule (sketch) |
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
|
|
1154
|
Friday, February 12, 2016, 13:00 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
2016 Winter shut down target hall schedule. See attachments1,2.
update the schedule weekly. Everything is on time so far. see attachment 3,4.
Update the schedule according to beam new beam schedule and target process. see attachment 5,6 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 5: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 6: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
|
1156
|
Thursday, February 25, 2016, 06:48 |
David Wang | ITE | Standard Operation | | | 4 Shielding blocks have been transferred from ITE to block storage area. |
Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now. |
|
1157
|
Thursday, February 25, 2016, 06:52 |
David Wang | Conditioning Station | Standard Operation | | | stop CS vacuum pumps. |
I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting. |
|
1158
|
Thursday, February 25, 2016, 09:27 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been disconnected in ITW |
TM2 has been disconnected in ITW (except vacuum lines). The vacuum system is still operating. |
|
1159
|
Thursday, February 25, 2016, 09:29 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been disconnected in ITE. |
TM4 has been disconnect in ITE(except vacuum lines). The ITE vacuum system is still operating. |
|
1160
|
Wednesday, March 02, 2016, 09:51 |
David Wang | ITW | Standard Operation | TM2 | | all water lines on TM2 and TM4 are purged. |
All water lines on TM2 and TM4 are purged for upcoming water lines helium pressure test. |
|
1161
|
Wednesday, March 02, 2016, 10:04 |
David Wang | ITW | Standard Operation | TM2 | | Leak check on ITW and TM2. |
Dan and I leak checked TM2 and ITW primary vacuum vessel. It was found a 1X E-7 atm.cc/sec leak on top T flange seal between TM2 and dump module in first time check. But it is not a repeatable leak. I checked the same spot and around area two more times with increased helium volume.It did not show up again. The first response could be a helium drift to dry scroll pump. I will check it again later. The primar vacuum vessel on ITW and TM2 are leak free.
Dan and I found a small leak on ITW dump module top flange seal. The leak detector got a response to 7xE-9 atm.cc/sec when I spray the helium to west side of dump module top flange. We tested again, and got same result. The o-ring which seals ITW dump module top flange is deteriorating. It need to be replaced at a proper time. This is the only air to vacuum leak we confirm so far on primary and secondary vacuum vessel on TM2 and ITW. The module and station no other air to vacuum leak.
The TM2 water lines helium pressure tested started in ITW. The helium pressure 70psi. The result so far is: Window: good, GE: huge leak directly shoot over E-7 atm.cc/sec( need to be confirmed tomorrow), HS: good, EE: good, MSP: tiny leak which is response to 3-4xE-9 atm.cc/sec. Coil 1 : small leak which is response to 1.3XE-8 atm.cc/sec. Tomorrow, We will test the rest water lines on TM2which are TA+, TA-, Tube+, Tube-, and coil 2. And We will confirm the GE huge leak at the last.
Finished the helium pressure test on TM2 water line.70 psi helium, The result of the rests 5 circuits: coil 1: leak 7.2xE-8atm.cc/sec,Ta(+): small leak 1.7XE-8 atm.cc/sec, Ta(-) small leak 8.7xE-9atm.cc/sec,Tube(-) 1.5 x E-8 atm.cc/sec. Tube(+)small leak 3.7xE-8 atm.cc/sec. We repeated the helium pressure test on GE. There is a huge leak on TM2 GE circuit. The leak detector shoot up to E-7 atm.cc/sec right after the helium was applied.It went up to E-6 range in less than 1 minutes.
|
|
1162
|
Friday, March 04, 2016, 12:34 |
David Wang | ITE | Standard Operation | TM4 | | TM4 ITE annual leak check |
Dan and I finished TM4 and ITE annual leak check on primary and secondary vacuum vessel. We found one leak on a KF25 blank off which is located on the top of the service cap. It is a low E-7 atm.cc/sec range leak. But, it is very close to turbo-pumps so ITE IG1 and other gauges are not affected by it very much. It is an easy fix. TheKF -25 center ring on the blank off will be replaced after vent . It be will leak checked again at CS after replacement. That is only leak we found on TM4 and ITE primary and secondary vessel air to vaccum leak check.
Dan and I also finished the helium pressure test on all TM4 using water circuits. 70 psi helium. base LR 0.0xE-9 atm.cc/sec. All of them are leak free. No any response has been found on leak detector during test. |
|
1163
|
Friday, March 04, 2016, 13:58 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
Update Schedule according to changes.See attachment1, 2.
Re-post it after some minor correction See attachment 3,4.
Update schedule according changes. See attachments 5,6
update schedule according to changes. See attachment 7,8 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 5: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 6: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 7: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 8: 2016_winter_shut_down__target_hall_schedule.mpp
|