ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015Weekly update Target Hall schedule 2015-06-15.
See attachment 1,2
 2015-06-19, Update the schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf 
  953   Friday, June 19, 2015, 11:43 David WangITWRepairTM1 ITW external water leak on dump circuitThere was an external water leak in ITW
during the last beam running time. The leak
started after the shielding blocks transfer(May
 6x 
  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.5 shielding blocks have been transferred
from ITW to ITE. The ITE is configured to
take proton beam.
  
  961   Wednesday, June 24, 2015, 13:49 David WangSouth Hot-CellRepairTM2 TM2 new source tray vacuum leak check.All water blocks seals and joints have
been leak checked. No leak has been found
on any of them. See attachment
 TM2_new_source_tray_water_block_leak_check_at_SHC.pdf 
  962   Friday, June 26, 2015, 08:27 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015Update the Target hall Schedule after some
changes on TM2 refurbishment. See attachment
1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp 
  965   Friday, June 26, 2015, 14:33 David WangConditioning StationStandard OperationTM2 TM2 have been moved from SHC to CSBill and I mover TM2 from SHC to CS. The
move is smooth. I connected the CS vacuum
system after the move, and started the roughing.
  
  967   Monday, June 29, 2015, 10:51 David WangConditioning StationRepairTM2 leak on TM2 side panelThere is an air to vacuum leak on TM2 service
cap side panel which we moved out during
the TM2 wiring job. The CS pumps are stopped
  
  971   Tuesday, June 30, 2015, 15:41 David WangITWStandard OperationTM1 TM1 was disconnected in ITW this morning.TM1 was disconnected in ITW  this
morning. The ITW was vented with argon last
night.
  
  972   Tuesday, June 30, 2015, 15:53 David WangConditioning StationDevelopmentTM2 leak on TM2 at CS I leak checked TM2 at CS this afternoon
which including air to vacuum check on service
cap and helium pressure test on water lines.
 TM2_leak_check_2015-06-30.pdfleak_check_2015-06-30_007.JPGleak_check_2015-06-30_009.JPG 
  978   Friday, July 03, 2015, 09:41 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015Updated the schedule before the weekend
2015-07-03. See attachment 1,2
Updated the schedule according to
 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp 
  982   Tuesday, July 07, 2015, 12:12 David WangConditioning StationRepair  CS TP1S replacementCS TP1S had been replaced with a new TP-301
pump this morning.The old pump was broken
last week.
  
  984   Wednesday, July 08, 2015, 14:05 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC Chad and I leak checked coil line(R,U)
on TM2 at SHC yesterday. The leak detector
was pumped down to 0.0Xe-9 atm.cc/sec before
  
  985   Wednesday, July 08, 2015, 14:24 David WangSouth Hot-CellRepairTM2 TM2 pressure bubble test on RU water blocks.July-06, 2015. Chad , Grant and I did the
bubble test on R,U water blocks. We suspected
the leak on the R,U circuit is from C seals
  
  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CSTM1 and CS  vacuum system are connected.
All turbo-pumps are started. The new TP1S
works fine also. The pumping down looks good
  
  998   Wednesday, July 15, 2015, 11:18 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHCChad and I leak checked the coil 1 circuit(R,U)
after rebuilt coil line is installed on TM2
source tray. The pumping down on the circuit
 007.JPG008.JPG 
  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015Update the TH schedule according to present
TM2 refurbishment process. See attachments
1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filterTarget pit Hepa filter has been replaced
today. There is 500 counts on swipe which
is taken inside of the replaced filter. The
  
  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.The leaking 1/8 NPT(M)-1/4NPT(F) adapter
on the ITW dump circuit is replaced.
  
  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Update Target Hall schedule after the changing
on TM2 process. See attachment 1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.Dan and I moved 5 shielding blocks from
ITE to block storage area. The move is smooth.
  