Friday, May 01, 2015, 13:48, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 update 
|
Target Hall Scheduled Activities April 07 - June 26 2015 update. 2015-05-01. All TH scheduled jobs are finished on time this week. |
Monday, May 11, 2015, 11:20, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 6x
|
The schedule has some changes due to new TM2 source tray coil cooling line leaking at test stand. Now,It is re-scheduled in such an estimation that TM2 source tray could be ready at teat stand by this Friday(May-15th). see attachment 1,2.
2015-05-12, Changed and updated the TH activity schedule according to Dons new beam schedule which is re-arranged after the coil line leaking issue. See attachments 3,4. No major conflicts has been found on the new schedule.
2015-05 25, Updated the TH activity schedule according to present TM2 job processing. See attachment 5,6. |
Friday, May 22, 2015, 15:44, David Wang, ITW, Standard Operation, TM1, UCx12, 5 Shielding blocks have been transferred from ITE to ITW.
|
5 shielding blocks have been transferred from ITE to ITW. I checked all ITW water signals, and they are good. ITW is configured to take proton beam. |
Tuesday, June 02, 2015, 06:51, David Wang, South Hot-Cell, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 
|
Target Hall schedule weekly update. All jobs are finished on time so far. |
Tuesday, June 02, 2015, 14:32, David Wang, South Hot-Cell, Standard Operation, TM4, SiC #31, Leak check on TM4 HS water line with new SiC #31 target. at SHC  
|
Chad and I leak checked TM4 HS water line with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec. No leak. The line will be helium pressurized at CS later.
2015-06-03, helium pressure test the line at CS. 70psi 3 minutes. leak rate 0.0xE-9 atm.cc/sec. No leak. See attachments |
Tuesday, June 02, 2015, 14:38, David Wang, Conditioning Station, Repair, TM4, , replace broken TM4 IG1 
|
TM4 IG1 filament was broken during last run at ITE. The broken filament is replaced with a new one today when TM4 is located at CS.
2015-06-03 , Leak checked the new 25 conflat gasket today. No leak. See attachments |
Tuesday, June 02, 2015, 14:39, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 and CS turbo- pumps are started .
|
TM4 and CS turbo-pumps are started this afternoon. Everything is good so far. |
Wednesday, June 03, 2015, 11:22, David Wang, Conditioning Station, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015   
|
I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.
2015-06-04, Updated the schedule with new PDF view. See attachments 3, 4 |
Wednesday, June 03, 2015, 13:51, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 is connected at CS   
|
TM4 has been connected at CS. CS HV cover is installed.I made a pair of new cooling lines for TM window cooling at CS. The TM4 containment box window cooling line is connected to the HVC spare circuit now. I checked water flow visually, and it is good. The TM4 is ready for conditioning.See attachment for window cooling modification.
|
Wednesday, June 10, 2015, 11:49, David Wang, ITE, Standard Operation, TM4, SiC #31, TM4 has been connected in ITE
|
Dan and I connected TM4 in ITE. At this stage, water is supplied to TM4 only. We checked the TM4 water signals from electrical room.They are good. The turbo-pumps will be started today once the roughing is done. |
Wednesday, June 10, 2015, 13:17, David Wang, ITE, Standard Operation, TM1, , Target Hall Scheduled Activities April 07 - July 26 2015 
|
Weekly update the schedule after some jobs have been finished in this week. |
Friday, June 12, 2015, 13:27, David Wang, South Hot-Cell, Standard Operation, , , TM2 new source tray has been remotely transferred from TH into SHC successfully.
|
TM2 new source tray has been remotely transferred into SHC successfully. The transfer table has been moved back to TH within 1 hour. I swiped the table and found about 150counts contamination. It is much better comparing to last time using since we removed this table out of SHC as quick as we can. The table will be cleaned with windex after Target Hall is surveyed. |
Monday, June 15, 2015, 14:14, David Wang, South Hot-Cell, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015   
|
Weekly update Target Hall schedule 2015-06-15. See attachment 1,2
2015-06-19, Update the schedule on the end of the week. See attachment 3,4 |
Friday, June 19, 2015, 11:43, David Wang, ITW, Repair, TM1, , ITW external water leak on dump circuit 6x
|
There was an external water leak in ITW during the last beam running time. The leak started after the shielding blocks transfer(May 22). It cause a constantly water level drop on S-tank(0.5 "/day average). Today , after the blocks are moved , the leak source has been found. Water seeped through a fitting on ITW dump circuit pressure gauge. The leak water slowly flow around the TM1 on the tank flange. most of them are dried out, but left some stain on dump module and tank flange. By closing the supply and return water valves on the ITW dump circuit, the leak is stopped now. We will fix this problem after the module is moved out and the radioactive field is low. See attachments. |
Friday, June 19, 2015, 11:52, David Wang, ITE, Standard Operation, TM4, SiC #31, 5 Shielding blocks have been transferred from ITW to ITE.
|
5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam. |
Wednesday, June 24, 2015, 13:49, David Wang, South Hot-Cell, Repair, TM2, , TM2 new source tray vacuum leak check.
|
All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment |
Friday, June 26, 2015, 08:27, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015   
|
Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2
2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4. |
Friday, June 26, 2015, 14:33, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 have been moved from SHC to CS
|
Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing. |
Monday, June 29, 2015, 10:51, David Wang, Conditioning Station, Repair, TM2, , leak on TM2 side panel
|
There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will be vented soon. The seal on this panel has to been changed.
2016-06-30. The o-ring seal on this panel(PNG1 and steerers) is replaced and leak checked. No leak now. |
Tuesday, June 30, 2015, 15:41, David Wang, ITW, Standard Operation, TM1, , TM1 was disconnected in ITW this morning.
|
TM1 was disconnected in ITW this morning. The ITW was vented with argon last night. |
|