ID Date Authordown Category Type Module Target/Number Subject
  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

Weekly update Target Hall schedule 2015-06-15. See attachment 1,2

 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
  953   Friday, June 19, 2015, 11:43 David WangITWRepairTM1 ITW external water leak on dump circuit

There was an external water leak in ITW during the last beam running time. The leak started after the shielding blocks transfer(May 22). It cause a constantly water level drop on S-tank(0.5 "/day average). Today , after the blocks are moved , the leak source has been found. Water seeped through a fitting on ITW dump circuit pressure gauge. The leak water slowly flow around the TM1 on the tank flange. most of them are dried out, but left some stain on dump module and tank flange. By closing the supply and return water valves on the ITW dump circuit, the leak is stopped now. We will fix this problem after the module is moved out and the radioactive field is low.  See attachments.

Attachment 1: 2015-06-19_ITW_dump_water_external_leak_001.JPG
2015-06-19_ITW_dump_water_external_leak_001.JPG
Attachment 2: 2015-06-19_ITW_dump_water_external_leak_002.JPG
2015-06-19_ITW_dump_water_external_leak_002.JPG
Attachment 3: 2015-06-19_ITW_dump_water_external_leak_003.JPG
2015-06-19_ITW_dump_water_external_leak_003.JPG
Attachment 4: 2015-06-19_ITW_dump_water_external_leak_004.JPG
2015-06-19_ITW_dump_water_external_leak_004.JPG
Attachment 5: 2015-06-19_ITW_dump_water_external_leak_006.JPG
2015-06-19_ITW_dump_water_external_leak_006.JPG
Attachment 6: 2015-06-19_ITW_dump_water_external_leak_005.JPG
2015-06-19_ITW_dump_water_external_leak_005.JPG
  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.

5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  961   Wednesday, June 24, 2015, 13:49 David WangSouth Hot-CellRepairTM2 TM2 new source tray vacuum leak check.

All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment

Attachment 1: TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
  962   Friday, June 26, 2015, 08:27 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2

2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
  965   Friday, June 26, 2015, 14:33 David WangConditioning StationStandard OperationTM2 TM2 have been moved from SHC to CS

Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing.

  967   Monday, June 29, 2015, 10:51 David WangConditioning StationRepairTM2 leak on TM2 side panel

There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will be vented soon. The seal on this panel has to been changed.

2016-06-30.  The o-ring seal on this panel(PNG1 and steerers)  is replaced and leak checked. No leak now.

  971   Tuesday, June 30, 2015, 15:41 David WangITWStandard OperationTM1 TM1 was disconnected in ITW this morning.

TM1 was disconnected in ITW  this morning. The ITW was vented with argon last night.

  972   Tuesday, June 30, 2015, 15:53 David WangConditioning StationDevelopmentTM2 leak on TM2 at CS

 I leak checked TM2 at CS this afternoon which including air to vacuum check on service cap and helium pressure test on water lines. There is a small leak on water line R ,U (COIL1) during the helium pressure test.. Below 20 psi helium, there is no leak on it. But , once the helium pressure is increased over 20 psi, it showed up on Leak Detector. At 60 psi helium, the leak rate is 9.4xE-9 atm.cc/sec. For detail information, See attachment.  All other water lines and air to vacuum seals are good.

Attachment 1: TM2_leak_check_2015-06-30.pdf
TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf
Attachment 2: leak_check_2015-06-30_007.JPG
leak_check_2015-06-30_007.JPG
Attachment 3: leak_check_2015-06-30_009.JPG
leak_check_2015-06-30_009.JPG
  978   Friday, July 03, 2015, 09:41 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Updated the schedule before the weekend 2015-07-03. See attachment 1,2

Updated the schedule according to present TM2 refurbishment process. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
  982   Tuesday, July 07, 2015, 12:12 David WangConditioning StationRepair  CS TP1S replacement

CS TP1S had been replaced with a new TP-301 pump this morning.The old pump was broken last week.

  984   Wednesday, July 08, 2015, 14:05 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked coil line(R,U) on TM2 at SHC yesterday. The leak detector was pumped down to 0.0Xe-9 atm.cc/sec before the check. Chad sprayed helium on the soldering joints connecting the cooling copper lines to the small holding blocks for the coil terminal(R,U).  After sprayed helium 2 seconds, I saw the leak rate on LD started to climbed up. The highest leak rate is 4.0xE-8 atm.cc/sec. It is a very positive response. We waited the leak detector pumped back to 0.0xE-9am.cc/sec, and tested again on the same joints. The result is same. Chad also sprayed helium on the R,U water blocks to check the C-seal. I saw a delayed tiny response on LD ( from 0.0 to 1.3xE-9atm.cc/sec). We think this tiny response is caused by the helium drifting to the leak soldering joint, but not a real C seal leak.

  985   Wednesday, July 08, 2015, 14:24 David WangSouth Hot-CellRepairTM2 TM2 pressure bubble test on RU water blocks.

July-06, 2015. Chad , Grant and I did the bubble test on R,U water blocks. We suspected the leak on the R,U circuit is from C seals on the water blocks so we did this test first. I applied both air and helium to R,U circuit , Chad applied snoop soap on the R,U water blocks.The air and helium pressure was increased from 40 psi to 90 psi Max step by step.Chad did not see any bubbles on the water blocks during the test. Since we did not find the leak source, we decided to do vacuum helium check on the all joints and c-seals of the R,U lines later.  Finally, We found the leak by vacuum helium spray the day after this bubble test. See other e-log.

  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CS

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

  998   Wednesday, July 15, 2015, 11:18 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked the coil 1 circuit(R,U) after rebuilt coil line is installed on TM2 source tray. The pumping down on the circuit is very quick and smooth. The LD base lake rate 0.0xE-9 atm.cc/sec. Base pressure0.0xE-4 torr.

Chad sprayed lots helium on the R( coil 1+)and U(coil 1 -) water blocks. During  1 minute waiting time, there is no any response on LD. The R and U water blocks and C-seals are leak tight.

Attachment 1: 007.JPG
007.JPG
Attachment 2: 008.JPG
008.JPG
  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.