ID Date Authordown Category Type Module Target/Number Subject
  908   Friday, May 01, 2015, 13:48 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015 update

Target Hall Scheduled Activities  April 07 - June 26  2015 update.      2015-05-01. All TH scheduled jobs are finished on time this week.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
  914   Monday, May 11, 2015, 11:20 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015

The schedule has some changes due to  new TM2 source tray coil cooling line leaking at test stand. Now,It is re-scheduled in such an estimation  that TM2 source tray could be ready at teat stand by this Friday(May-15th). see attachment 1,2.

2015-05-12,  Changed  and updated the TH activity schedule according to Dons new beam schedule which is re-arranged after the coil line leaking issue. See attachments 3,4. No major conflicts has been found on the new schedule.

2015-05 25, Updated the TH activity schedule according to present TM2 job processing. See attachment 5,6.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 6: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.

5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton beam.

  923   Tuesday, June 02, 2015, 06:51 David WangSouth Hot-CellStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015

Target Hall schedule weekly update. All jobs are finished on time so far.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
  927   Tuesday, June 02, 2015, 14:32 David WangSouth Hot-CellStandard OperationTM4SiC #31Leak check on TM4 HS water line with new SiC #31 target. at SHC

Chad and I leak checked TM4 HS water line with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec.  No leak.  The line will be helium pressurized at CS later.

2015-06-03, helium pressure test the line at CS. 70psi 3 minutes. leak rate 0.0xE-9 atm.cc/sec. No leak.   See attachments

Attachment 1: 003.JPG
003.JPG
Attachment 2: 005.JPG
005.JPG
Attachment 3: 001.JPG
001.JPG
  928   Tuesday, June 02, 2015, 14:38 David WangConditioning StationRepairTM4 replace broken TM4 IG1

 TM4 IG1 filament was broken during last run  at ITE.  The broken filament is replaced with a new one today when TM4 is located at CS.

2015-06-03 , Leak checked the new 25 conflat gasket today. No leak. See attachments

Attachment 1: 002.JPG
002.JPG
Attachment 2: 006.JPG
006.JPG
  929   Tuesday, June 02, 2015, 14:39 David WangConditioning StationStandard OperationTM4SiC #31TM4 and CS turbo- pumps are started .

TM4 and CS turbo-pumps are started this afternoon. Everything is good so far.

  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.

2015-06-04, Updated the schedule with   new PDF view. See attachments 3, 4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
  932   Wednesday, June 03, 2015, 13:51 David WangConditioning StationStandard OperationTM4SiC #31TM4 is connected at CS

TM4 has been connected at CS. CS HV cover is installed.I made a pair of new cooling lines for TM window cooling at CS. The TM4 containment box window cooling line is connected to the HVC spare circuit now. I checked water flow visually, and it is good. The TM4 is ready for conditioning.See attachment for window cooling modification.

 

Attachment 1: 007.JPG
007.JPG
Attachment 2: 009.JPG
009.JPG
Attachment 3: 008.JPG
008.JPG
Attachment 4: 010.JPG
010.JPG
  939   Wednesday, June 10, 2015, 11:49 David WangITEStandard OperationTM4SiC #31TM4 has been connected in ITE

Dan and I connected TM4 in ITE. At this stage, water is supplied to TM4 only. We checked the TM4 water signals from electrical room.They are good. The turbo-pumps will be started today once the roughing is done.

  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015

Weekly update the schedule after some jobs have been finished in this week.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
  945   Friday, June 12, 2015, 13:27 David WangSouth Hot-CellStandard Operation  TM2 new source tray has been remotely transferred from TH into SHC successfully.

TM2 new source tray has been remotely transferred into SHC successfully. The transfer table has been moved back to TH within 1 hour.  I swiped the table and found about 150counts contamination. It is much better comparing to last time using since we removed this table out of SHC as quick as we can. The table will be cleaned with windex  after Target Hall is surveyed.

  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

Weekly update Target Hall schedule 2015-06-15. See attachment 1,2

 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
  953   Friday, June 19, 2015, 11:43 David WangITWRepairTM1 ITW external water leak on dump circuit

There was an external water leak in ITW during the last beam running time. The leak started after the shielding blocks transfer(May 22). It cause a constantly water level drop on S-tank(0.5 "/day average). Today , after the blocks are moved , the leak source has been found. Water seeped through a fitting on ITW dump circuit pressure gauge. The leak water slowly flow around the TM1 on the tank flange. most of them are dried out, but left some stain on dump module and tank flange. By closing the supply and return water valves on the ITW dump circuit, the leak is stopped now. We will fix this problem after the module is moved out and the radioactive field is low.  See attachments.

Attachment 1: 2015-06-19_ITW_dump_water_external_leak_001.JPG
2015-06-19_ITW_dump_water_external_leak_001.JPG
Attachment 2: 2015-06-19_ITW_dump_water_external_leak_002.JPG
2015-06-19_ITW_dump_water_external_leak_002.JPG
Attachment 3: 2015-06-19_ITW_dump_water_external_leak_003.JPG
2015-06-19_ITW_dump_water_external_leak_003.JPG
Attachment 4: 2015-06-19_ITW_dump_water_external_leak_004.JPG
2015-06-19_ITW_dump_water_external_leak_004.JPG
Attachment 5: 2015-06-19_ITW_dump_water_external_leak_006.JPG
2015-06-19_ITW_dump_water_external_leak_006.JPG
Attachment 6: 2015-06-19_ITW_dump_water_external_leak_005.JPG
2015-06-19_ITW_dump_water_external_leak_005.JPG
  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.

5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  961   Wednesday, June 24, 2015, 13:49 David WangSouth Hot-CellRepairTM2 TM2 new source tray vacuum leak check.

All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment

Attachment 1: TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
  962   Friday, June 26, 2015, 08:27 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2

2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
  965   Friday, June 26, 2015, 14:33 David WangConditioning StationStandard OperationTM2 TM2 have been moved from SHC to CS

Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing.

  967   Monday, June 29, 2015, 10:51 David WangConditioning StationRepairTM2 leak on TM2 side panel

There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will be vented soon. The seal on this panel has to been changed.

2016-06-30.  The o-ring seal on this panel(PNG1 and steerers)  is replaced and leak checked. No leak now.

  971   Tuesday, June 30, 2015, 15:41 David WangITWStandard OperationTM1 TM1 was disconnected in ITW this morning.

TM1 was disconnected in ITW  this morning. The ITW was vented with argon last night.