890
|
Monday, April 20, 2015, 07:27 |
David Wang | ITE | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4. |
|
892
|
Monday, April 20, 2015, 10:22 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM1 with UCx12 has been connected to CS and ready for conditioing. | The TH will be locked during the TM1 conditioning
time due to an interference issue between
CS HV cover and a gas analysis valve on top |
|
895
|
Wednesday, April 22, 2015, 11:05 |
David Wang | Conditioning Station | Standard Operation | TM1 | | electrical check on TM1 at CS under vacuum | I did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m |
|
896
|
Thursday, April 23, 2015, 09:08 |
David Wang | Conditioning Station | Maintenance | TM1 | UCx12 | Huge Leak on TM1 contaiment box window. | There is a huge leak on TM1 containment
box window. I did a 70 psi helium pressure
test on all TM1 water circuits this morning. |
|
898
|
Monday, April 27, 2015, 10:28 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM4 has been partially disconnected at CS. | TM1 has been partially disconnected at
CS for tomorrow move. The CS TP1S is still
running and will be stopped and disconnected |
|
901
|
Tuesday, April 28, 2015, 10:21 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | CS and TM1 was vented with Argon gas | Dan and I vented CS and TM1 with Argon
gas before it is moved this morning. |
|
902
|
Tuesday, April 28, 2015, 10:26 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | ITW target pit o-ring seal replacement. | Dan and I replaced ITW target pit o-ring
seal(.275DIA X42"ID). It is an annual
job before first beam to ITW. The old o-ring |
|
905
|
Tuesday, April 28, 2015, 17:17 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | TM1 has been connected in ITW. | TM1 has been connected in ITW. Five turbo
pumps have been started. The TM1 containment
box window line is capped on the service |
|
908
|
Friday, May 01, 2015, 13:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 update | Target Hall Scheduled Activities
April 07 - June 26 2015 update.
2015-05-01. All TH scheduled |
|
914
|
Monday, May 11, 2015, 11:20 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 | The schedule has some changes due to
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in |
6x |
916
|
Friday, May 22, 2015, 15:44 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | 5 Shielding blocks have been transferred from ITE to ITW. | 5 shielding blocks have been transferred
from ITE to ITW. I checked all ITW
water signals, and they are good. ITW |
|
923
|
Tuesday, June 02, 2015, 06:51 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Target Hall schedule weekly update. All
jobs are finished on time so far. |
|
927
|
Tuesday, June 02, 2015, 14:32 |
David Wang | South Hot-Cell | Standard Operation | TM4 | SiC #31 | Leak check on TM4 HS water line with new SiC #31 target. at SHC | Chad and I leak checked TM4 HS water line
with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec.
No leak. The line will be helium pressurized |
|
928
|
Tuesday, June 02, 2015, 14:38 |
David Wang | Conditioning Station | Repair | TM4 | | replace broken TM4 IG1 | TM4 IG1 filament was broken during
last run at ITE. The broken filament
is replaced with a new one today when TM4 |
|
929
|
Tuesday, June 02, 2015, 14:39 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #31 | TM4 and CS turbo- pumps are started . | TM4 and CS turbo-pumps are started this
afternoon. Everything is good so far. |
|
930
|
Wednesday, June 03, 2015, 11:22 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 | I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW. |
|
932
|
Wednesday, June 03, 2015, 13:51 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #31 | TM4 is connected at CS | TM4 has been connected at CS. CS HV cover
is installed.I made a pair of new cooling
lines for TM window cooling at CS. The TM4 |
|
939
|
Wednesday, June 10, 2015, 11:49 |
David Wang | ITE | Standard Operation | TM4 | SiC #31 | TM4 has been connected in ITE | Dan and I connected TM4 in ITE. At this
stage, water is supplied to TM4 only. We
checked the TM4 water signals from electrical |
|
940
|
Wednesday, June 10, 2015, 13:17 |
David Wang | ITE | Standard Operation | TM1 | | Target Hall Scheduled Activities April 07 - July 26 2015 | Weekly update the schedule after some jobs
have been finished in this week. |
|
945
|
Friday, June 12, 2015, 13:27 |
David Wang | South Hot-Cell | Standard Operation | | | TM2 new source tray has been remotely transferred from TH into SHC successfully. | TM2 new source tray has been remotely transferred
into SHC successfully. The transfer table
has been moved back to TH within 1 hour. |
|