Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 77 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  394   Wednesday, July 03, 2013, 08:44 chad fisher, Travis CaveSouth Hot-CellStandard Operation  Ta#39 Transfered to spent target storage vaultTa#39 has been transferred to spent target
storage vault. Ta#39 was placed into pail
#106 and placed into spot of 4C of the spent
 Vault_Storage_July_3_2013.pdf 
  397   Friday, July 05, 2013, 09:22 chad fisherSouth Hot-CellRepairTM3 Service Tray Water Block InspectionI have inspected the service tray water
block and suggest that they SHOULD be cleaned/polished
before we install the new source tray.
  
  400   Tuesday, July 16, 2013, 13:09 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.TM4 has been disconnected in ITE. All water
lines on TM4 have been purged. ITE is venting
now.
  
  401   Wednesday, July 17, 2013, 08:29 David WangConditioning StationDevelopmentTM3 TM3 leak check in CS without source tray.Leak checked TM3 without source tray in
CS this morning. The CS and TM3 vacuum: IG1(top
of the TM3 service cap)4.9x E-7Torr, IG2(diagnostic
  
  402   Wednesday, July 17, 2013, 10:10 David WangConditioning StationDevelopmentTM3 CS cooling and vacuum system have been turned off CS water cooling and vacuum system have
been turned off at 10:00 AM this morning.The
TM3 will be disconnected and moved to silo
  
  412   Friday, July 26, 2013, 11:06 David WangSouth Hot-CellStandard Operation  The steel shielding plug has been put on theSHC top in target hallto reduce the radioactive shining from 
SHC Ta# 40 target.
  
  415   Tuesday, July 30, 2013, 14:42 David WangITEStandard OperationTM4 TM4 has been connected in ITE.TM4 has been connected in ITE. All turbo
pumps have been started now. The pumping
down on TM4 and ITE is good so far. The water
  
  416   Wednesday, July 31, 2013, 11:13 Travis CaveSpent Target VaultStandard Operation  Spent target moveFive spent targets have been removed from
the storage vault and placed into the mini
storage. The target placed into the mini
 Vault_Storage_July_31_2013.pdfMini_Vault_Storage_July_31_2013.pdf 
  417   Wednesday, August 07, 2013, 06:47 maicodallavalleSpent Target VaultMaintenance  F-308All the F-308's have been torqued up 
and the locks installed. Ready to be moved.
  
  418   Wednesday, August 14, 2013, 11:50 Travis CaveSouth Hot-CellMaintenanceTM3 module moveTM#3 and its new source tray have been
both moved into the south hot cell.
  
  419   Thursday, August 15, 2013, 07:37 David WangITERepairTM4 I moved 5 shielding blocks from ITE to block storage area.I moved5shielding blocks from ITE to block
storage area, This is a job for preparing
ITE vacuum surge investigation and leak check.
  
  420   Thursday, August 15, 2013, 09:32 chad fisherSouth Hot-CellRepairTM3 TM3 source tray installation status 
The installation of the module
side water block jig has been successful.
 
During
  
  423   Wednesday, August 21, 2013, 20:36 Grant MinorSouth Hot-CellRepairTM3 TM3 module-side water block sealing surface inspection (post polishing)The water block sealing surfaces on the
module-side of TM3 were polished this week
by Chad Fisher, using his air-ratchet controlled
 TM3_final_water_block_polishing_16-048.JPGTM3_final_water_block_polishing_16-031.JPG 
  424   Thursday, August 22, 2013, 19:38 Grant MinorSouth Hot-CellRepairTM3 TM3 Rev 3 source tray - water blocks connected and torquedAfter a great struggle with the water block
jigs, the TM3 source tray was finally advanced
fully into the service tray and all water
 6x 
  425   Friday, August 23, 2013, 18:32 Grant MinorSouth Hot-CellRepairTM3 TM3 Rev 3 - steerer wire broken from connector on module sideWhile continuing on the TM3 Rev 3 source
tray installation, Chad noticed today that
one of the steerer wires is broken and has
 TM3_Broken_Steerer_Wire_Module_Side_23Aug2013.JPGTM3_Broken_Steerer_Wire_Module_Side_23Aug2013-001.JPGTM3_Broken_Steerer_Wire_Module_Side_23Aug2013-002.JPGITA2826D_RevD02_23Aug2013.pdfThermocouple-style_connector_23Aug2013.JPG 
  426   Monday, August 26, 2013, 18:22 Grant MinorSouth Hot-CellRepairTM3 TM3 Rev 3 - all connetions made except steerers, IMG, and entrance windowToday Chad finished making all connections
to the new source tray, except for:
- steerers - broken wire, must be
 8x 
  427   Monday, August 26, 2013, 18:26 Grant MinorConditioning StationStandard OperationTM3 TM3 moved from Hot Cell to Conditioning StationTarget Module 3 with no target, and a partially-installed
Rev-3 source tray (no steerers connected,
no IMG connected, entrance window lines blanked
  
  434   Thursday, August 29, 2013, 06:48 David WangConditioning StationDevelopmentTM3 TM3 leak check in CS with new source tray.A huge leak had been found on HS circuit
during 60 psi helium pressurize test. Other
circuits are free of obvious major leak at
 TM3_leak_check_at_CS_2013__AUG_27th.pdf 
  435   Thursday, August 29, 2013, 09:08 chad fisherSouth Hot-CellRepairTM3 Heat Shield Circuit LeakThe heat shield circuit was pressurized
with air (15-20 psi) and snoop applied to
the water block joint and brazes. Bubbles
 20130829_084751.jpg20130829_084754.jpg20130829_084949.jpg20130829_084957.jpg 
  436   Thursday, August 29, 2013, 10:09 Bevan MossSouth Hot-CellRepairTM3 Heat Shield Circuit Leak

    

       
            
  