  RH-ISAC, Page 71 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subjectdown
  1167   Wednesday, March 16, 2016, 14:23 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 removal Target Module Inspection

SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the left target heater A.

As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector.

Attachment 1: 20160316_141127.jpg
20160316_141127.jpg
Attachment 2: 20160316_141146.jpg
20160316_141146.jpg
  1105   Monday, October 19, 2015, 11:53 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 installed on TM2

SiC#32 has been installed on TM2. High current fasteners torqued to 130 in lbs.

  1172   Friday, March 18, 2016, 11:43 chad fisherSouth Hot-CellStandard Operation  SiC#32 dissection

SiC#32 has been open for inspection.

Attachment 1: 20160318_105519_1.jpg
20160318_105519_1.jpg
Attachment 2: 20160318_105311.jpg
20160318_105311.jpg
Attachment 3: 20160318_105248.jpg
20160318_105248.jpg
Attachment 4: 20160318_105428.jpg
20160318_105428.jpg
  1023   Tuesday, July 28, 2015, 14:40 chad fisherSouth Hot-CellStandard OperationTM4SiC#31 UCx#13SiC#31 removed UCx#13 installed

SiC#31 has been removed from TM4 and UCx#13 installed. UCx#13 connection to the 9 pin connector was VERY VERY tight to the tube heater insulator on both the test jig and module.

 

 

Attachment 1: 20150727_115314.jpg
20150727_115314.jpg
  924   Tuesday, June 02, 2015, 09:43 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 installed

Ta #45 has been removed from TM4 and SIC#31installed.

  1022   Tuesday, July 28, 2015, 14:36 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 Autopsy

Extraction electrode was removed from SiC#31 and target inspected.

Pictures of findings can be found at          https://documents.triumf.ca/docushare/dsweb/View/Collection-15131

 

 

 

  720   Thursday, July 31, 2014, 08:08 chad fisherSouth Hot-CellStandard OperationTM3SiC#30SiC#30 Removed and inpect

SiC#30 has been removed from TM3. A quick exam of TM3 source tray did not  yield any obvious signs of damage.

9 pin connector on the target showed the usual sparking/arcing marks.

Heat shield has been removed from the target. Inside of heat shield has some unusual marks on it and quite a lot of black deposits.

 

Attachment 1: TM320140731_01.jpg
TM320140731_01.jpg
Attachment 2: TM320140731_02.jpg
TM320140731_02.jpg
Attachment 3: TM320140731_03.jpg
TM320140731_03.jpg
Attachment 4: TM320140731_04.jpg
TM320140731_04.jpg
  105   Friday, May 18, 2012, 08:17 chad fisherSouth Hot-CellStandard OperationTM4SiC#27SiC#27 Installed

SiC#27 has been installed onto TM4. Fit was very good. All electrical connections double checked with mirror.

Pictures can be found at: http://documents.triumf.ca/docushare/dsweb/View/Collection-8530
 

  101   Tuesday, May 15, 2012, 12:14 chad fisherSouth Hot-CellStandard OperationTM4SiC#26SiC#26 removal TM4 degredation

SiC#26 was removed from target module #4 this morning. Target shows the now standard arc marks on the 9 pin connector housing...pictures to follow.

Of greater concern is the amount of "plating out" or "arc" marks on both the insulators and connductor of the TM4 source tray. I will again warn that the source trays historically have a life expectancy, and that TM4 continues to show visual signs that the current source tray is rapidly approaching the end of its useful life!

I understand that one of this years goals is to retrofit TM3; however I fear TM4(and possibly TM1) may fail before this can be released. With the current absence of backup source trays and modules I fear we leave the ISAC program in a very vulnerable position.

 

 

 

Attachment 1: RHB_2236.JPG
RHB_2236.JPG
Attachment 2: RHB_2237.JPG
RHB_2237.JPG
Attachment 3: RHB_2238.JPG
RHB_2238.JPG
Attachment 4: RHB_2239.JPG
RHB_2239.JPG
Attachment 5: RHB_2240.JPG
RHB_2240.JPG
Attachment 6: RHB_2241.JPG
RHB_2241.JPG
Attachment 7: RHB_2242.JPG
RHB_2242.JPG
Attachment 8: RHB_2243.JPG
RHB_2243.JPG
Attachment 9: RHB_2244.JPG
RHB_2244.JPG
Attachment 10: RHB_2245.JPG
RHB_2245.JPG
Attachment 11: RHB_2246.JPG
RHB_2246.JPG
Attachment 12: RHB_2247.JPG
RHB_2247.JPG
Attachment 13: RHB_2248.JPG
RHB_2248.JPG
Attachment 14: RHB_2249.JPG
RHB_2249.JPG
Attachment 15: RHB_2250.JPG
RHB_2250.JPG
Attachment 16: RHB_2251.JPG
RHB_2251.JPG
Attachment 17: RHB_2251.JPG
RHB_2251.JPG
Attachment 18: RHB_2252.JPG
RHB_2252.JPG
Attachment 19: RHB_2253.JPG
RHB_2253.JPG
  42   Friday, October 28, 2011, 09:37 chad fisherSouth Hot-CellStandard OperationTM4SiC#26 HP FebiadSiC#26 installed on TM4

HP febiad target SiC#26 was installed onto Tm4 on Monday morning.

"JP's" connector required lossing of the two mounting fasteners. Connector was pushed tight to its mating half on the source tray and both fasteners retightened, and the mating checked; it was good.

Two new 7/8 long 3/8-16 fasteners were used for the febiad coil connections.

Installation went well.

Leak check was performed:

 

Base Pressure: 0.0x10-4

Stable leak rate 0.0x10-9

Left vcr joint was checked two times with a 2 second spray of helium with a 60 second waiting time between sprays; no response.

Right vcr joint was checked two times with a 2 second spray of helium with a 60 second waiting time between sprays; no response.

Fllod of system with a 6 second spray; no response.

  233   Thursday, January 17, 2013, 10:06 chad fisherSouth Hot-CellStandard Operation  SiC Test Target for TM4/CS

I have inserted the test target for TM4 and the CS into the hot cell.

I had some concerns about the condition of the target which I have discussed with Pierre and he has cleared. Pictures are attached.

Attachment 1: IMG_0909[1].JPG
IMG_0909[1].JPG
Attachment 2: IMG_0910[1].JPG
IMG_0910[1].JPG
Attachment 3: IMG_0911[1].JPG
IMG_0911[1].JPG
Attachment 4: IMG_0912[1].JPG
IMG_0912[1].JPG
Attachment 5: IMG_0913[1].JPG
IMG_0913[1].JPG
Attachment 6: IMG_0914[1].JPG
IMG_0914[1].JPG
Attachment 7: IMG_0915[1].JPG
IMG_0915[1].JPG
Attachment 8: IMG_0916[1].JPG
IMG_0916[1].JPG
Attachment 9: IMG_0917[1].JPG
IMG_0917[1].JPG
Attachment 10: IMG_0918[1].JPG
IMG_0918[1].JPG
Attachment 11: IMG_0919[1].JPG
IMG_0919[1].JPG
Attachment 12: IMG_0920[1].JPG
IMG_0920[1].JPG
Attachment 13: IMG_0921[1].JPG
IMG_0921[1].JPG
Attachment 14: IMG_0922[1].JPG
IMG_0922[1].JPG
Attachment 15: IMG_0923[1].JPG
IMG_0923[1].JPG
Attachment 16: IMG_0924[1].JPG
IMG_0924[1].JPG
  918   Tuesday, May 26, 2015, 14:34 chad fisherSouth Hot-CellRepairTM2 Shutter replacement

The shutter in TM2 was successfully replaced today.

New lock washer and nut were installed onto shutter and nut torqued to 120 ft lbs.

Shutter guide alignment tool was used to insure tapped shutter guide holes were concentric with thru holes in shutter side mounting panel, button head screws replaced and torqued to 110 ft-lbs.

The shutter was manually cycled open and closed by David and everything is to operate well.

Attachment 1: Shutter.jpg
Shutter.jpg
  915   Wednesday, May 13, 2015, 13:55 chad fisherSouth Hot-CellRepairTM2 Shutter removal

TM2 has been successfully de-shuttered.

All went pretty much according to plan except I had to remove one fastener out of the upper wiring harness (the one that has just been installed) to allow for enough clearance to rotated the shutter guide out of the way...I shutter to think what would have happened otherwise...anyways...

Close inspection of the shutter does show that the "thin" area isn't in very good shape; whether this is a result of removal or just the way it was is hard.Due to the ease of removal I would quess that it may have been a preexisting condition. That being said...I think we may want to consider replacing it.

 

Attachment 1: TM2_20150513_131339.jpg
TM2_20150513_131339.jpg
Attachment 2: TM2_20150513_134232.jpg
TM2_20150513_134232.jpg
  1670   Friday, December 22, 2017, 11:09 Anders MjosITWStandard OperationTM2 Shut down High Active Cooling water

Stopped MP1 today in preparation for the power outage over the holidays. both P-25 and P-26 breakers have been switched off to prevent inadvertent start of system

  1145   Tuesday, December 01, 2015, 11:47 Anders MjosConditioning StationMaintenanceTM4UC#14Short on Extraction Electrode

 After conditioning over the weekend the EE developed a short. This was confirmed by measuring the resistance between EE and Heat Shield on the module yesterday.

  328   Thursday, May 02, 2013, 10:09 chad fisherSouth Hot-CellRepairTM3 Service tray water block leak check

David and I preformed a helium leak check on the service tray waterblocks and verify that no damage had been done during jig installation. All 14 circuits were checked and verified to be ok except circuit E and circuit I which were unstable when helium was applied. The resonse time on E and I would suggest that it is an issue with the bungs that were used and not the braze joint however.

  397   Friday, July 05, 2013, 09:22 chad fisherSouth Hot-CellRepairTM3 Service Tray Water Block Inspection

I have inspected the service tray water block and suggest that they SHOULD be cleaned/polished before we install the new source tray.

The water blocks have slight water scalling to the inside of the ID of where the c seals locate.

I have taken two close up  pictures of each water block for reference and to document their current state. They can be found at http://documents.triumf.ca/docushare/dsweb/View/Collection-10841
 

  1873   Thursday, February 21, 2019, 15:10 Isaac EarleSafe Module ParkingDevelopment  Seismic requirements for SMP

Dragan Mitrovic, TRIUMF structural engineer, was consulted earlier this week regarding seismic requirements for the SMP assembly.  Installation location, overall dimensions, total weight, and the center of mass for assembly IRH1670 were provided to him by e-mail.  On Feb 20th he communicated verbally that he had analyzed the assembly for seismic loads, and concluded that this equipment does not require anchoring or any other form of seismic restraint.

Update (May 30, 2019): Confirmed with Dragan that the approach he used for analysis was that specified in the BC Building Code (both 2012 edition and updated 2018 edition).

  2704   Thursday, October 10, 2024, 12:20 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target Hall

A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Hot Cells:
    • Phone not working at North hot cell operator station
  • Target Hall:
    • Uncertain if NHC and SHC ventilation pressure gauges have recently been inspected

Action has been taken on all deficiencies.

  2738   Friday, January 03, 2025, 09:59 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target Hall

A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Hot Cells:
    • NHC right manipulator gripper stuck (known, repair planned)
  • Target Hall:
    • 50% of overhead light bulbs burnt out (David Wang contacted Electrical Services to rectify)
    • One RH camera for target pit not working (Travis Cave notified)

Action has been taken on all deficiencies.