1448
|
Friday, March 10, 2017, 09:19 |
chad fisher | South Hot-Cell | Standard Operation | | | South Hot Cell Field Measurements | The fields in the hot cell have been measured
by means of a pole monitor through the tool
port. Field was measured to be 25 uSv/h. |
|
1820
|
Thursday, November 08, 2018, 09:27 |
chad fisher | South Hot-Cell | Maintenance | | | South East Manipulator cable replacement | The handle cable on the east manipulator
of the south hot cell has been replaced.
Old cable showed signs of wear but had no |
|
1617
|
Tuesday, September 19, 2017, 10:40 |
chad fisher | South Hot-Cell | Maintenance | | | South East Manipulator Maintenence | Entered hot cell to preform replacement
of slave tong cable. Existing cable shows
no signs of wear so it has been re-installed. |
|
1321
|
Tuesday, August 16, 2016, 11:27 |
chad fisher | South Hot-Cell | Maintenance | | | South Cell Field Readings | Field readings have been taken at the south
hot cell in preparation for entry into the
cell to fix manipulator. |
|
1880
|
Friday, March 01, 2019, 10:23 |
Travis Cave | Spent Target Vault | Standard Operation | | | Source tray moved | The old TM#2 source tray and TM#4
optics tray have been removed from the vault
and placed into the spent target storage |
|
1648
|
Thursday, October 19, 2017, 14:20 |
Anders Mjos | Assembly/Bench Test | Standard Operation | | | Source tray inspection | Two minor chips in the main 60 kV
insulators on the source tray was inspected
today by Anders, Tom and Aurelia. The chips |
|
1646
|
Wednesday, October 18, 2017, 14:54 |
Anders Mjos | Assembly/Bench Test | Standard Operation | | | Source tray assembly electrical check | Source tray meggered today by Anders and
Keith
GND - MSP OL @ 1000V |
|
378
|
Thursday, June 13, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM3 | | Source Tray/Extraction Column Removal | TM3 Rev 2 source tray/extraction column
insertion into its storage was completed
yesterday and it was then removed from the |
|
1666
|
Wednesday, December 13, 2017, 15:32 |
Anders Mjos | Assembly/Bench Test | Maintenance | TM2 | | Source Tray inspection | The Source tray was inspected in the RH
shop today by Anders, Friedhelm and Jens.
The routing of the lines are satisfactory, |
|
325
|
Monday, April 29, 2013, 15:58 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Source Tray Removal | Chad removed the source tray from TM3 today,
see attached picture (video was also taken).
There was some interference between the window |
|
1292
|
Tuesday, July 26, 2016, 11:22 |
chad fisher | South Hot-Cell | Maintenance | | | Soth Hot Cell Waste Storage Vault Tunnel | The two 45 gal (m) drums of waste removed
from the south hot cell in December 2015
and January 2016 were transferred from the |
|
1739
|
Friday, June 22, 2018, 13:59 |
chad fisher | South Hot-Cell | Repair | | | Soth Hot Cell Fields | Field measurements have been taken to determine
the level before entry for repair of manipulators.
Field on contact at manipulator is |
|
1578
|
Thursday, July 06, 2017, 14:23 |
Isaac Earle | North Hot-Cell | Repair | | | Slave side Z motion tape snapped on NHC right side manipulator | The NHC right side manipulator was evaluated
today to check if operation was normal through
all ranges of motion. The manipulator |
|
2094
|
Wednesday, May 20, 2020, 13:30 |
David Wang | Safe Module Parking | Maintenance | | | Silo area radio active waste clean up. | Sorted and packed one 55 gallon drum with
low contamination and active stuffs which
are placed around silo area in the past. |
|
705
|
Wednesday, July 16, 2014, 13:59 |
chad fisher | South Hot-Cell | Standard Operation | TM3 | SiC#30 | Sic#30 install | Just some notes on the install of SiC#30
on TM3 last month...It was installed with
all new fasteners and torque values provided |
|
2467
|
Tuesday, July 25, 2023, 16:25 |
Carla Babcock | North Hot-Cell | Standard Operation | | SiC#45 | SiC#45 post irradiation inspection | Looked at SiC#45 in the hot cell. Looked
very clean, no deposits on the heat shield
or other components. Target also looked very |
|
2036
|
Tuesday, December 03, 2019, 12:45 |
Adam Newsome | Spent Target Vault | Standard Operation | | SiC#38 | SiC#38 in Pail 205 moved to Storage Vault: 4B | SiC#38 in Pail 205 was moved to section 4B
of the storage vault. Dose rate when retrieving
from Hot Cell was 22.2 mSv/h. |
|
1649
|
Thursday, October 19, 2017, 14:20 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | SiC#37 | SiC#37 Conditioning | Thursday, October 19, 2017, 14:20: EE configured
for conditioning. HV cage locked up
Thursday, October 19, 2017, 16:46: |
|
1380
|
Monday, October 24, 2016, 14:44 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#35 | SiC#35 installed | Sic#35 has been installed onto TM2. High
current fasteners torqued to 130 in lbs.
Mating of the 9 pin connector was |
|
1328
|
Tuesday, August 23, 2016, 13:31 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#33 | SiC#33 Removed | SiC#33 has been removed from TM2. |
|