  2389   Tuesday, November 22, 2022, 10:37 Adam NewsomeNorth Hot-CellStandard OperationTM4 TM4 Move - ITE to NHC

TM4 was moved from ITE to NHC with C#4.

  2390   Tuesday, November 22, 2022, 12:41 Frank SongNorth Hot-CellStandard OperationTM4C#4electrical check

 TM4 with C#4 is checked on NHC right after moving from ITE.

Attachment 1: TM4_with_C#4_electrical_check_right_after_moving_to_NHC.png
TM4_with_C#4_electrical_check_right_after_moving_to_NHC.png
  2391   Tuesday, November 22, 2022, 14:53 Carla BabcockNorth Hot-CellMaintenanceTM4 Multipin connector alignment pin on TM4 module loose

The pin on TM4 has become loose again, making it very difficult to remove the multipin connector with the last target, C#4. For the installation of the next target, UCx#41, we will drill out the hole on the target side bracket so that it doesn't contact the multipin pin. Will try to remove this pin by force in January, or if needed change out the whole multipin bracket.

  2392   Wednesday, November 23, 2022, 11:27 Frank SongNorth Hot-CellStandard OperationTM4UCx#41electric and leak check after new target installed

 an electric check and leak check done on NHC, TM4 with new target UCx#41 is ready moving to TCS.

Attachment 1: TM4_with_UCx#41_electric_and_leak_check_on_NHC.png
TM4_with_UCx#41_electric_and_leak_check_on_NHC.png
  2397   Thursday, December 01, 2022, 13:45 Carla BabcockNorth Hot-CellStandard OperationTM4C#4Post irradiation inspection C#4

Post irradiation inspection of C#4 which was running in TM4/ITE was conducted at the NHC on Nov. 22 2022.

The yields from this target had been dropping and its behaviour was erratic, with the voltages on the tube and target jumping all over the place sometimes. The ion current on the FCs followed the voltages. We took this to mean the target container was breaking down.

Upon inspection we found the container looked pretty damaged - highly crystallized and distorted. The container had gone banana-shaped, but not in the usual direction. It had curved  in the direction of the ion source (see photos). The heat shield and other surrounding components were super clean, no deposits or marks at all.

Attachment 1: 20221122_152435.jpg
20221122_152435.jpg
Attachment 2: 20221122_153033.jpg
20221122_153033.jpg
Attachment 3: 20221122_152407.jpg
20221122_152407.jpg
  2422   Monday, March 06, 2023, 11:31 Adam NewsomeNorth Hot-CellRepair  Spare Telemanipulator: Y-Motion Linear Actuator Repair

The linear actuator used for the Y-motion motor assistance on the spare telemanipulator was replaced and tested. It was observed around September 2021 that the former one which was installed was causing fuses to blow for the main 120 VAC power supply in the control box. After some troubleshooting, it was determined that the linear actuator itself did not operate smoothly - it was suspected that this caused motor overload due to additional friction. This suspicion was confirmed by operating the linear actuator independently with a power supply and measuring current draw. The part has been replaced by Thomson PPA90-58B65-08NXXX. Note: this part took over 1 year to arrive since it was first ordered. The spare telemanipulator is confirmed operational.

 

Update 2024-09-11: noting that this was for serial number 9351

  2423   Tuesday, March 07, 2023, 10:37 chad fisherNorth Hot-CellRepair  Spare Telemanipulator: Y-Motion Linear Actuator Repair

Adam Newsome wrote:

The linear actuator used for the Y-motion motor assistance on the spare telemanipulator was replaced and tested. It was observed around September 2021 that the former one which was installed was causing fuses to blow for the main 120 VAC power supply in the control box. After some troubleshooting, it was determined that the linear actuator itself did not operate smoothly - it was suspected that this caused motor overload due to additional friction. This suspicion was confirmed by operating the linear actuator independently with a power supply and measuring current draw. The part has been replaced by Thomson PPA90-58B65-08NXXX. Note: this part took over 1 year to arrive since it was first ordered. The spare telemanipulator is confirmed operational.

 During this repair it was noted that the Y-axis electrical translation is locked out when the Z-axis is in the fully retracted position (i.e. the Z-axis limit switch engaged). I have made a note of this in the operator manual (CRLD-1046-B Rev1 ) which can be found in docushare collection 26780

  2429   Monday, April 03, 2023, 07:55 chad fisherNorth Hot-CellStandard Operation  NHC, SHC field check

NHC is 1.26 mSv/h inside approximately .5m from table surface, between manipulators

 

SHC 186 uSv/h inside approximately .5m from table surface and between manipulaotrs

  2430   Tuesday, April 11, 2023, 11:35 chad fisherNorth Hot-CellStandard Operation  NHC fields post sample removal

The fields in the NHC after removal of Ferran's graphite sample is 238 uSv/h. This again seems to emanate for the items in the 5 gal pail...the copper tubing from the beam window or, as I mentioned in my previous elog, the peek samples. I did ask about removing these during the graphite sample removal but was told they were not "hot".

  2432   Tuesday, April 18, 2023, 07:28 chad fisherNorth Hot-CellMaintenance  NHC entry summary

NHC was entered on April 17, 2023 for inspection and maintenance. Summary :

Compressible and non-compressible waste was loaded into a 55 gal drum and removed from the NHC. This same drum will be inserted into the SHC at a later date to be sorted, compressible waste compressed, and drum filled more.

Manipulator remote end tong cables checked. Tong cables didn't show any wear but both east and west had tong cables had hopped off the third highest pulley (see detailed write up . This was fixed by tying the tongs in the closed position to provide slack in the cables then inserting a t-handle through the wrist and offering the cables back onto the pulleys. Cable hopping is most likely due to aggressive ratcheting and releasing of the tong during operation.

Manipulator booting flanges were removed from both manipulators as it was previously found that  the booting interferes with access to the inside of the containment box so it could not be used. Flanges were remove to provide even more clearance.

Containment box cover removal arm - linkage fasteners were removed one at a time and blue locktite added then reassembled and tightened appropriately to allow arm to swing freely (see detailed write up) . Lack of locktite during initial assembly was allowing fasteners that pass through bushings into the linkage arms to loosen over time/cycling.

Exhaust pre-filter changed.

Target insertion jig - The target insertion jig was rumored to had a missing fastener. A loose nut was found that appeared to belong to it but after much inspection a location for it could not be found...i.e. all parts appeared to be counted for. During this inspection it was noted that some over the fasteners in the main hinge were loose. Again these were removed one at a time, blue locktite added and fasteners tightened to allow proper movement (see detailed write up).

Window inspected for leak. No sign of any leakage from the "hot" side.

 

  2439   Monday, May 08, 2023, 10:59 Frank SongNorth Hot-CellStandard OperationTM4TiC#5electrical check/leak check

 TM4 with target TiC#5 installed has been leak checked and electric checked on NHC.

Attachment 1: TM4_with_TiC#5_20230508.png
TM4_with_TiC#5_20230508.png
  2456   Tuesday, June 13, 2023, 11:45 Frank SongNorth Hot-CellStandard OperationTM4TiC#5electrical check

 TM4 with spent target TiC#5 electric check after moving from ITE to NHC.

Attachment 1: TM4_with_spent_target_electric_check_right_after_moving_to_NHC.png
TM4_with_spent_target_electric_check_right_after_moving_to_NHC.png
  2457   Tuesday, June 13, 2023, 11:49 Frank SongNorth Hot-CellStandard OperationTM4SiC#45electrical check and leak check

 TM4 with new target SiC#45 installed has been leak checked and electrical checked on top of NHC.

Attachment 1: TM4_with_SiC#45_leak&electric_check_on_top_of_NHC.png
TM4_with_SiC#45_leak&electric_check_on_top_of_NHC.png
  2463   Wednesday, July 12, 2023, 22:21 Carla BabcockNorth Hot-CellStandard Operation TiC#5TiC#5 post irradiation inspection results

The TiC#5 post irradiation inspection was done on Wed. June 14 and Mon. June 19. This target didn't have any obvious issues but it didn't produce much beam. The inspection revealed that the container was quite embrittled and showed significant damage, though it was not broken. The FEBIAD grid looked fine, despite the large anode current draw (indicating that current was flowing elsewhere). The gas line looked fine though the gas injection to this target looked as if it wasn't connected. But there was a plug on the unused line, so it must have been correct. No other obvious signs that would explain the poor performance. Pictures are can be found here https://documents.triumf.ca/docushare/dsweb/View/Collection-37913

  2464   Tuesday, July 18, 2023, 10:08 Frank SongNorth Hot-CellStandard OperationTM4SiC#45module disconnection & electrical check right after transferred from ITE to NHC

 TM4 with spent target SiC#45 was disconnected ITE  and an electrical check made right after moved on NHC. 

Attachment 1: TM4_with_SiC45_disconnection_and_e_check.pdf
TM4_with_SiC45_disconnection_and_e_check.pdf TM4_with_SiC45_disconnection_and_e_check.pdf TM4_with_SiC45_disconnection_and_e_check.pdf TM4_with_SiC45_disconnection_and_e_check.pdf
  2466   Wednesday, July 19, 2023, 08:09 Frank SongNorth Hot-CellStandard OperationTM4UCx#42electrical check

 An electrical check was made after new target installed on TM4.

Attachment 1: E__check_after_UCx42_installed_on_TM4.pdf
E__check_after_UCx42_installed_on_TM4.pdf
  2467   Tuesday, July 25, 2023, 16:25 Carla BabcockNorth Hot-CellStandard Operation SiC#45SiC#45 post irradiation inspection

Looked at SiC#45 in the hot cell. Looked very clean, no deposits on the heat shield or other components. Target also looked very straight. Only issue we saw was sparking marks on the EE side that faces the ground electrode, in several spots. This target had a bout of sparking when ramping up the protons, so I guess that was the location. Will look for matching spark marks on the ground electrode next time TM4 is in the hot cell. Forgot to take picutres...

  2473   Tuesday, August 08, 2023, 13:01 David WangNorth Hot-CellStandard OperationTM2TiC#6TM2 TiC#6 post run electrical check at NHC.

TM2 TiC#6 post run electrical check has been done at TCS. See attachment

Attachment 1: TiC#6_post_run_electrical_check.pdf
TiC#6_post_run_electrical_check.pdf TiC#6_post_run_electrical_check.pdf
  2474   Wednesday, August 09, 2023, 09:41 David WangNorth Hot-CellStandard OperationTM2Nb#10TM2 Nb# 10 electrical and leak check at NHC

Nb#10 has been installed on TM2 . electrical and leak check on HS line are good. See attachment.

Attachment 1: Nb_#10_electrical_and_leak_check_at_NHC.pdf
Nb_#10_electrical_and_leak_check_at_NHC.pdf Nb_#10_electrical_and_leak_check_at_NHC.pdf Nb_#10_electrical_and_leak_check_at_NHC.pdf
  2476   Wednesday, August 09, 2023, 13:43 Carla BabcockNorth Hot-CellStandard OperationTM2TiC#6TiC#6 PIE

PIE on TiC#6 was done in the NHC. The target assembly looked brand new when we took it out, no heating spots or deposits (pictures on docushare). Online we measured a 400kOhm connection between TGHT-TBHT-COIL to HV common (TGHT and COIL shorted in TM2 service tray) and anode was unstable above ~300V. After the module move and before the target removal David found TGHT-TBHT-COIL was a dead short to HV common and the anode was at 39kOhms to HV common.

1. Wanted to see if the TGHT-TBHT-COIL short was on the COIL. Measured with ohmmeter the COIL lines to HS and got about 700Ohms. But with the target lying down the COIL lines drop and touch the heat shield so to do this measurement Chad had to lift the lines, which could cause them to touch something else. So not sure how reliable this measurement was. It jumped around a lot, saw 0L occasionally.

2. Measured both target legs and tantalum gas line to HS, got about 5kOhms repeatedly using the ohmmeter.

3. Meggered across the gas line insulator to the gas line going into the target and got open circuit at 250V, so the gas line wasn't coated.

4. Target container looked vaguely red in the areas where the target material was, otherwise still no deposits on the inside. The container was not overly crystalized as seen on the legs and end caps.

5. Some sparking marks on the EE and some slightly asymmetric deposits

Continuing Aug. 22 2023:

6. Found what looks like a hole in the insulation on the COIL, maybe the cause of our short? Found a corresponding line mark on the copper plates that hold the coil down but not sure if it is related. Pics on docushare.

7. Grid looks perfectly new. Where was that current going?

8. Copper plates that hold coil were loose and bolts that hold coil in just fell out as well.

9. What can be seen of the anode wire looks good.

ELOG V2.9.2-2455