Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x
TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned.
See attachments for updated schedule.
I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.
Entry  Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
This schedule is following Dons schedule on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4.
Entry  Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
Updated schedule this morning after last Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed
to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time  weekly update.
Entry  Monday, June 01, 2020, 12:40, David Wang, Crane, Maintenance, , , TH crane festoon cable maintenance 
Tom Kauss corrected the TH crane  festoon cable loops. He lubricated festoon cable wheels as well.    The maintenance is done.
Entry  Monday, March 18, 2013, 12:39, Bevan Moss, Conditioning Station, Repair, TM4, CS Test Target #1, TGHT PS Failure IMG_0529.JPG
The Model of the Power Supply (PS) is TSQLG 480-20/1500 and serial number is 2755.02.01.01.09. 
We went to test the PS and supplied the required 480V and turned the local switch to on. At this point nothing happened, the
controls screen didn’t light up nothing. We tried to run the PS in remote mode as that is what it had previously been set at and again there was
    Reply  Monday, December 15, 2014, 12:53, Anders Mjos, Conditioning Station, Maintenance, TM2, , TCSTK2 topped up 


    
        
            Anders Mjos wrote:
        
        
            
            
            
Entry  Wednesday, October 19, 2022, 12:04, Carla Babcock, Conditioning Station, Repair, , , TCS:TBHT taken as replacement for ITE:TBHT 
During the last ITE run with the SiC#44 target, the ITE:TBHT controls card was fried twice. The first time we put in our spare, and the second time we
just continued to run without controls readback. For the C#4 run starting Oct. 19, we used the conditioning station supply. As soon as one of the other
supplies is fixed, we will install it in the conditioning station. The equipment list (https://triumfoffice365-my.sharepoint.com/:x:/g/personal/cbabcock_triumf_ca/EQPffP4p1P9JqEDWIHGRPfsBVDSQjMCv-M8ZNg4ngkyGHw?e=fnLVYe)
Entry  Monday, April 22, 2013, 11:35, Bevan Moss, Conditioning Station, Repair, TM3, N/A, TCS:DIF2 broken 
 The flow meter on the primary side (TCS:DIF2) of the conditioning station is broken. I investigated and there is flow, the gauge is not fouled,
and the PLC does read back when current supplied. The gauge is also reciving 24V but the output is 0V and 0mA. I will contact ESC and the supplier.
Entry  Friday, October 17, 2014, 13:36, Anders Mjos, Conditioning Station, Maintenance, , , TCS:Chil staging not operational 
NOTE: If cooling is required, the compressors will have to be run manually. Make sure to switch it off again when the water has reached an acceptable
temperature.
The staging did not work properly this morning. Dave Morris have been contacted and will look into it.
Entry  Friday, September 27, 2024, 07:29, David Wang, Conditioning Station, Repair, , , TCS water system resistivity analyzer has been repaired. 
TCS water system resistivity analyzer has been repaired. Two diodes and one capacitor on PS board were broken. They were replaced. Installed analyzer
back and tested it in system. it works fine. Operator closed e-fault, removed force on TS5, and enabled alarm on TS5 and TC1.
Entry  Thursday, November 03, 2016, 09:01, David Wang, Conditioning Station, Standard Operation, TM4, , TCS water system has been started for TM4. 
The system works fine. All water signals to TM4 at TCS are normal. HV cover is installed on to TM4 at TCS.
Entry  Thursday, October 24, 2024, 10:37, David Wang, Conditioning Station, Standard Operation, , , TCS water system functionnal test.  
TCS water system has been started for functional test. System parameters including  pressure, all temperature sensors, flow rate sensors, resistivity
are ok. I will watch on chiller CP1/2/3 in rest of the week and make sure chiller CP1/2/ 3 auto stage in/out work fine. 
Entry  Wednesday, June 05, 2024, 11:32, David Wang, Conditioning Station, Standard Operation, , , TCS water system filters have been changed.  
TCS water system  five filters were changed yesterday by plant group Dan.T. Service labels on filters are updated.  No water leak after job.
Entry  Thursday, March 20, 2025, 13:10, David Wang, Conditioning Station, Standard Operation, , , TCS water system filters annual replacement has been done. 
TCS water system filters annual replacement has been done. Plant group Dan Tower finished the job and updated the inspection tags . 
Entry  Thursday, April 28, 2016, 06:28, David Wang, Conditioning Station, Maintenance, TM2, , TCS water system are turned off. 
 TCS water system worked fine overnight. I turned off TCS water system at 6:16 AM this morning. Start of purging TM2 water lines for helium pressure
test again this morning.
2016-4-28 7:58AM. Disconnected TM2 water lines at TCS. Purged them with compression air each for 5 minutes. 
Entry  Tuesday, November 29, 2016, 06:27, David Wang, Conditioning Station, Standard Operation, TM2, , TCS water pumps are stopped 
Argon venting on TCS and TM2 is processing
Entry  Monday, June 12, 2023, 07:36, David Wang, Conditioning Station, Standard Operation, , , TCS water filters annual change.  
Plant group changed TCS water filters last Friday. 4 filters on resin can inet /outlet sides and filters(4 in one cartridge house)on pump return line
have been changed. Triumf maintenance tags on filters have been updated. No water leak after job. The TCS TK2 water level dropped  from 20" to
16" because of the job. I will refill the level to 28" today. 
Entry  Wednesday, May 08, 2024, 12:36, David Wang, Conditioning Station, Standard Operation, TM3, UCx#44, TCS was argon vented this morning between 7:00 to 8:30 am. 
TCS was argon vented this morning between 7:00 to 8:30 am before module was moved to ITE.
Entry  Tuesday, May 28, 2024, 07:45, David Wang, Conditioning Station, Standard Operation, TM4, UCx#45, TCS was argon vented this morning between 6:00 and 7:30am.  
TCS was argon vented this morning between 6:00 and 7:30am for TM4 moving to ITW.
Entry  Tuesday, January 14, 2020, 10:19, David Wang, Conditioning Station, Standard Operation, TM3, , TCS vacuum system is switched off.  
TM3 TP1 and TP2 work  fine in past 4 days. During operation, The current draw on pumps were 0.7A to 0.8 A. TM3 will be moved back to silo tomorrow.