Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x
Entry  Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
Entry  Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
Entry  Monday, June 01, 2020, 12:40, David Wang, Crane, Maintenance, , , TH crane festoon cable maintenance 
Entry  Monday, March 18, 2013, 12:39, Bevan Moss, Conditioning Station, Repair, TM4, CS Test Target #1, TGHT PS Failure IMG_0529.JPG
    Reply  Monday, December 15, 2014, 12:53, Anders Mjos, Conditioning Station, Maintenance, TM2, , TCSTK2 topped up 
Entry  Wednesday, October 19, 2022, 12:04, Carla Babcock, Conditioning Station, Repair, , , TCS:TBHT taken as replacement for ITE:TBHT 
Entry  Monday, April 22, 2013, 11:35, Bevan Moss, Conditioning Station, Repair, TM3, N/A, TCS:DIF2 broken 
Entry  Friday, October 17, 2014, 13:36, Anders Mjos, Conditioning Station, Maintenance, , , TCS:Chil staging not operational 
Entry  Friday, September 27, 2024, 07:29, David Wang, Conditioning Station, Repair, , , TCS water system resistivity analyzer has been repaired. 
Entry  Thursday, November 03, 2016, 09:01, David Wang, Conditioning Station, Standard Operation, TM4, , TCS water system has been started for TM4. 
Entry  Thursday, October 24, 2024, 10:37, David Wang, Conditioning Station, Standard Operation, , , TCS water system functionnal test.  
Entry  Wednesday, June 05, 2024, 11:32, David Wang, Conditioning Station, Standard Operation, , , TCS water system filters have been changed.  
Entry  Thursday, March 20, 2025, 13:10, David Wang, Conditioning Station, Standard Operation, , , TCS water system filters annual replacement has been done. 
Entry  Thursday, April 28, 2016, 06:28, David Wang, Conditioning Station, Maintenance, TM2, , TCS water system are turned off. 
Entry  Tuesday, November 29, 2016, 06:27, David Wang, Conditioning Station, Standard Operation, TM2, , TCS water pumps are stopped 
Entry  Monday, June 12, 2023, 07:36, David Wang, Conditioning Station, Standard Operation, , , TCS water filters annual change.  
Entry  Wednesday, May 08, 2024, 12:36, David Wang, Conditioning Station, Standard Operation, TM3, UCx#44, TCS was argon vented this morning between 7:00 to 8:30 am. 
Entry  Tuesday, May 28, 2024, 07:45, David Wang, Conditioning Station, Standard Operation, TM4, UCx#45, TCS was argon vented this morning between 6:00 and 7:30am.  
Entry  Tuesday, January 14, 2020, 10:19, David Wang, Conditioning Station, Standard Operation, TM3, , TCS vacuum system is switched off.  