  ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  596   Tuesday, February 11, 2014, 13:56 chad fisherSouth Hot-CellRepairTM2 waterblock cleaningNew cleaning and polishing pads have been
inserted onto the hot cell as well as rubber
bungs and a new blank off.
 TM2_20140207_2.jpgTM2_20140211_2.jpg 
  597   Thursday, February 13, 2014, 09:24 David WangSouth Hot-CellRepairTM2 Leak check TM2 tube heater (+) water line with rubber insert blocked WB in SHCChad and I  did the Leak checked TM2
tube heater (+) water line  with rubber
insert plugged water block on " D" 
 001.JPG002.JPG003.JPG004.JPG 
  598   Thursday, February 13, 2014, 13:30 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.Chad and I did the pressure test on TM2tube
heater+(D) water  line at SHC with shop
air.We tested from 30psi to 80psi on both
  
  599   Thursday, February 13, 2014, 14:15 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.

    

       
            
 007.JPG008.JPG013.JPG 
  600   Thursday, February 13, 2014, 14:23 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(elastic seal) installed on WB.Chad and I did the leak check on TM2 tube
heater (+) water line  with blank off(
+ elastic o ring seal) installed on "D" 
 005.JPG001.JPG 
  601   Monday, February 17, 2014, 09:32 David WangConditioning StationRepairTM2 helium pressure test on TM2 tube heater +(D) water line.I did the helium pressure test on Tube
heater+ line this morning. The  vacuum on
CS and TM2 are very good. The base lake rate
 6x 
  602   Tuesday, February 18, 2014, 11:26 David WangConditioning StationRepairTM2 I stopped turbo pumps and disconnected vacuum system on TM 2 and CSI stopped turbo pumps and disconnected
vacuum system on TM2 and CS. The TM2 will
be moved to SHC for C seal installation on
  
  603   Thursday, February 20, 2014, 09:45 Travis CaveConditioning StationStandard OperationTM2no targetmodule moveTM#2 has been moved from the conditioning
station to the south hot cell.
  
  604   Thursday, February 20, 2014, 11:04 chad fisherSouth Hot-CellRepairTM2 Readying TM2 for C-Seal Leak CheckContainment box has been removed and water
block jig installed.
 TM2_20140220_01.jpg 
  605   Monday, February 24, 2014, 11:05 chad fisherSouth Hot-CellRepairTM2 Circuit D blank offThe blank off with the o-ring has been
removed, manipulator fixed, circuit D water
block sealinhg surfaces cleaned and blank
  
  606   Monday, February 24, 2014, 12:09 chad fisherSouth Hot-CellRepairTM2 C-seal blank off testCircuit D has passed the vacuum leak check.
Jig has been removed and containment box
re-installed for move to conditioning station.
 TM2_20140224_1.jpg 
  607   Monday, February 24, 2014, 13:52 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 moved from the south hot cell to the
conditioning station.
  
  608   Tuesday, February 25, 2014, 06:53 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(C-seal) installed on WB.Chad and I did the leak check   on
TM2 tube heater (+) water line  with
blank off and C-seal  installed on 
  
  609   Tuesday, February 25, 2014, 10:00 David WangConditioning StationRepairTM2 helium pressure test on TM2 tube heater (+) water line with blank off(C-seal) installed on WB.I did the helium pressure  test 
on TM2 tube heater (+) water line  with
blank off(C-seal) installed on  water
 10x 
  611   Wednesday, March 05, 2014, 10:07 Travis CaveConditioning StationStandard OperationTM2no targetmodule moveTM#2 with no target or source tray has
been moved from the conditioning station
to the north east silo. TM#1 with no target
  
  713   Thursday, July 24, 2014, 09:10 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 has been moved to the hot cell from
the north east silo.
  
  714   Thursday, July 24, 2014, 18:21 Grant MinorSouth Hot-CellRepairTM2No target / no source trayLeak check on TM2 ionizer tube cooling lines C and D - module sideTarget Ionizer tube cooling lines "C"
and "D" in Target Module 2 were
both leak checked at the Hot Cell. 
 ITA6021_Rev_14_screencapture_cooling_lines_24July2014.jpgTM2_hot_cell_leak_check_tube_heater_C_D_24July2014_small2.jpgTM2_hot_cell_leak_check_no_source_tray_24july2014.JPG 
  715   Monday, July 28, 2014, 09:29 Travis CaveConditioning StationStandard OperationTM2no targetmodule moveTM#2 has been moved from the south hot
cell to the conditioning station.
  
  716   Monday, July 28, 2014, 14:37 David WangConditioning StationDevelopmentTM2 helium pressure test on TM2 tube heater +(D)and -(C)water lines.
    TM2 installed in Conditioning
Station
    Varian Leak detector
connected directly to Target Module 2   
 7x 
  717   Monday, July 28, 2014, 14:45 David WangConditioning StationDevelopmentTM2 turned off TM2 and CS turbo pumps.I turned off TM2 and CS turbo-pumps. TM2
will be moved from CS to silo tomorrow morning.
  