2671
|
Tuesday, August 27, 2024, 13:30 |
Frank Song | ITW | Maintenance | TM3 | TiC#8 | module disconnection |
TM3 is disconnected and all water lines are purged/refilled with 50psi Nitrogen. Pls see pics attached with. |
2672
|
Tuesday, September 03, 2024, 11:40 |
David Wang | ITW | Standard Operation | TM3 | TiC#8 | TM3 has been moved from ITW to S-W silo. |
TM3 has been moved from ITW to S-W silo. The move is smooth. |
2685
|
Wednesday, September 18, 2024, 13:40 |
Aaron Tam | South Hot-Cell | Standard Operation | TM3 | TiC#8 | Target removal |
TiC#8 HP FEBIAD removed from TM3
Target sitting in SHC
1 Coil Conductor bolt fell under source tray
Photo Dump uploaded |
2686
|
Wednesday, September 18, 2024, 13:47 |
David Wang | South Hot-Cell | Standard Operation | TM3 | TiC#8 | Tm3 has been moved from silo to SHC. |
Tm3 has been moved from silo to SHC. The move is smooth. |
2687
|
Monday, September 23, 2024, 11:26 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | TM3 window line has been leak checked. |
TM3 window line has been leak checked after containment box removal and installation for insulator installation on water cup C. No leak. |
2688
|
Monday, September 23, 2024, 11:31 |
David Wang | South Hot-Cell | Development | TM3 | | 10 pins lectrical check result after insulator is installed on water cap C. |
10 pins lectrical check result after insulator is installed on water cap C.
pin 14 to 60kv bias has 20 Kohm @250V Megga check. The rest check on ohmmeter and megga @250 are either OLor over 25Mohm which are good. |
2690
|
Monday, September 23, 2024, 16:06 |
Aaron Tam | South Hot-Cell | Repair | TM3 | | Insulator Addition to Water block |
September 23, 2024 - C. Fisher
- Containment box removed
- Insulator installed
- New window line VCR seals installed
- Dropped bolt from TiC#8 removed
- Containment box reinstalled
September 23, 2024 - A. Tam
- Containment box cover reinstalled
Photos attached |
2693
|
Wednesday, September 25, 2024, 09:12 |
David Wang | South Hot-Cell | Maintenance | TM3 | | Tm3 has been moved from SHC to silo. |
Tm3 has been moved from SHC to silo. the move is smooth. |
2720
|
Monday, November 25, 2024, 09:56 |
Adam Newsome | South Hot-Cell | Standard Operation | TM3 | | TM3 move - silo to SHC |
TM3 was moved from silo to SHC with no target. Move successful. |
2721
|
Tuesday, November 26, 2024, 13:03 |
Frank Song | South Hot-Cell | Standard Operation | TM3 | UCx#47 | electrical check/leak check |
An electrical check and leak check had been done after new target UCx47 was installed on TM3 in SHC. see attachment pls. |
2722
|
Tuesday, November 26, 2024, 13:54 |
Adam Newsome | Conditioning Station | Standard Operation | TM3 | | TM3 move - SHC to TCS |
TM3 was moved from SHC to TCS with UCx#47. The move was smooth. |
2723
|
Tuesday, November 26, 2024, 14:52 |
Aaron Tam | South Hot-Cell | Standard Operation | TM3 | UCx#47 | UC#47 LP-SIS w/ gas Install |
November 26, 2024 - Aaron Tam
Handover from TPO and inspection
- Completed
- Some modification to the center Inner-Outer conductor had to be made (hole enlarged as tab was slightly short)
Target Insertion:
Target Mounting:
- Upon fully seating UC#47 on service tray locating pins, the gas line VCR gasket came off
- Operator doesn't have line-of-sight to this area, so there has to be healthy clearance (Foreshadowing)
- Gas line VCR gasket reinstalled using manipulators
- 2nd seating of UC#47 on service tray locating pins, the gas line VCR gasket came off again
- Some alignment interference with the gas line coupling is the cause of the gasket falling off during placement (photo attached)
- Gas line on service tray was loosened, raised to highest position and fastened (Photo attached)
- Failed to re-install VCR gasket (Plastic separated from gasket material)
- Target removed from Hot cell to reinstall gaskets and make modifications to the gas-line coupling
- Gas line coil plastically deformed to give less of a spring action so the coupling can stay down under friction until it is time to couple
- Target carefully inserted into hot cell without disturbing spring/friction of gas-line coupling.
- This had to be repeated several times. Once for the waterline gaskets coming off, and a few other times to insert the target/tray without disturbing sprung coupling
- Target mounted without issue after the above steps successfully
Gas and Water Services:
- VCR connections coupled
- Leak test passed
- leak test faster today because module had been left in silo for a long time to dry out.
- Gas line no-longer needed, so was not checked
Electrical Services:
- Conductor bolts installed
- All bolts (including mounting bolts) checked for fit with mirror
- Coil conductor bolts torqued to at least 130inch-lbs
- Electrical test completed
Containment box panel reinstalled
Cleared area around module for craning out.
|
2729
|
Wednesday, December 04, 2024, 08:05 |
Frank Song | ITE | Standard Operation | TM3 | UCx#47 | Module Connection |
TM3 with new target UCx#47 was connected in ITE right after be moved from TCS. |
2735
|
Monday, December 09, 2024, 13:10 |
Frank Song | 5 Shielding Blocks | Standard Operation | TM3 | UCx#47 | shielding blocks transfer |
5 Shielding Blocks have been transferred from ITW to ITE. MAA is secured after moving. |
2742
|
Tuesday, January 07, 2025, 12:05 |
David Wang | ITE | Standard Operation | TM3 | UCx #47 | ITE primary and secondary vacuum vessel leak check for 2025 shut down |
ITE primary and secondary vacuum vessel leak check for 2025 shut down have been done. No leak. The TM3 waterlines helium pressure test will be done at TCS when module is there.
TM3 water lines helium pressure test are done. 70 psi helium 3 minutes to each line( except HS which has no target on it ) . leak detector base leak rate :0.0Xe-9 atm.cc/sec. No leak on all tested water lines.Helium were purged out after test. and 60 psi nitrogen were filled in lines for storage. |
2747
|
Monday, January 13, 2025, 10:36 |
Frank Song | ITE | Standard Operation | TM3 | UCx#47 | module disconnection |
TM3 with spent target UCx#47 was disconnected in ITE and will be moved to SHC. |
2748
|
Tuesday, January 14, 2025, 10:00 |
David Wang | South Hot-Cell | Standard Operation | TM3 | UCx#47 | after operation electrical check, Tm3 UCx 47 |
TM3 UCx#47 after operation electrical check is done at SHC. The result is normal. See attachment. |
2750
|
Thursday, January 16, 2025, 14:21 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | TM3 electrical check at TCS under good vacuum |
A complete TM3 electrical check at TCS under good vacuum has been done. Pin 14 to 60KV only has 8K ohm on ohmmeter check , and it's about 2Kohm @250V Megga. It's low in resistivity. The pin 14 is for thermocouples only so no big concern. The rest things are good. See attachments. |
533
|
Friday, November 01, 2013, 09:08 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | module move |
TM#2 has been moved from the north west silo to the south hot cell. The module has a field of about 3.1mSv/hr when it was lowered into the hot cell. |
534
|
Monday, November 04, 2013, 10:46 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Exploration |
TM2 is now in the hot cell with the containment box off for inspection and eventual blank off off the water blocks.
Upon initail inspection the status (fron a hot cell point of view) is:
-Water block jig is equipped/on
-There is a thermocouple line that will need to be removed
-TM2 requires a new front containment box cover - already manufactured and waiting for installation
|