622
|
Thursday, March 13, 2014, 16:23 |
Keith C Ng | ITE | Repair | | | 2a3 window - inspection | Video inspected 2a3 window joint this morning.
Screenshots from video showing debris
forming around aluminum cradle and brown/red |
 |
623
|
Monday, March 17, 2014, 15:39 |
Keith C Ng | ITE | Repair | | | 2a3 window - prep and clean | Cleaned top of the ITE vacuum flange and
top of window clamp. Attempted to clean the
bellows/beam pipe through the wall, mostly |
|
624
|
Tuesday, March 18, 2014, 16:01 |
Keith C Ng | ITE | Repair | | | 2a3 window - prep and clean | Continued with vacuuming inside wall penetration
to remove debris. Changed filter bag in nilfisk
vacuum, left old filter in place however |
 |
626
|
Wednesday, March 19, 2014, 16:48 |
Keith C Ng | ITE | Repair | | | 2a3 window - beam tube removal | Today:
1) Vaccumed top and around clamp.
Disconnected clamp from flanges and removed |
11x |
628
|
Friday, March 21, 2014, 16:49 |
Keith C Ng | ITE | Repair | | | 2a3 window - tank flange inspection | Today:
1) Cleaned flange with methanol and
cotton glove, appears to be clean. |
   |
638
|
Friday, April 04, 2014, 14:59 |
Keith C Ng | ITE | Maintenance | | | measurement of new beam tube section | R. Kuramoto and A. Laxdal measured the
distance from the 2A tunnel to the tank flange
of ITE. The new fabricated beam pipe with |
|
647
|
Friday, April 11, 2014, 18:17 |
Keith C Ng | ITE | Repair | | | 2a3 window - install | Today:
1) Installed new cradle and shortened
beam pipe section in wall penetration. |
|
652
|
Wednesday, April 16, 2014, 17:08 |
Keith C Ng | ITE | Repair | | | 2a3 window - He leak check | Helium leak checked 2a3 window after installing
using remote line:
- There was a leak found between |
|
899
|
Monday, April 27, 2015, 16:12 |
Keith C Ng | South Hot-Cell | Development | TM2 | | Ceramic Standoffs in TM2 source tray steerer assembly | On drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001". |
|
1461
|
Friday, March 24, 2017, 11:12 |
Keith C Ng | Spent Target Vault | Standard Operation | | | 2A window transfer | Transfered the 2A window from the ISAC
Storage Vault to the Cyclotron Vault Tunnel
Storage area. RPG storage form attached. |
|
1462
|
Friday, March 24, 2017, 11:19 |
Keith C Ng | Spent Target Vault | Standard Operation | | 2A3 window | Window now in vault |
|
|
1592
|
Wednesday, August 02, 2017, 15:41 |
Keith C Ng | Assembly/Bench Test | Development | | | spare source tray build | After re zeroing alignment telescope to
master jig and adjusted parts into place:
|
 |
1640
|
Wednesday, October 11, 2017, 15:50 |
Keith C Ng | Assembly/Bench Test | Standard Operation | | | spare source tray build alignment |
Spare |
|
1642
|
Friday, October 13, 2017, 11:14 |
Keith C Ng | Assembly/Bench Test | Standard Operation | | | source tray alignment/build | Source tray is complete for brazing, gas
line bracket is currently missing but can
be made in parallel with tube bending operations. |
   |
1703
|
Friday, April 20, 2018, 15:33 |
Keith C Ng | ITW | Repair | | | ITW beam tube repair job | 2A2 window has been removed from ITW and
beamlines has removed the beamtube from the
penetration. The penetration has been sealed |
   |
1704
|
Friday, April 27, 2018, 15:06 |
Keith C Ng | ITW | Repair | | | ITW beam tube repair | Vacuumed out remainder of debris from the
wall penetration, removed cradle and checked
condition. Down stream support bracket sees |
6x |
1705
|
Tuesday, May 01, 2018, 10:54 |
Keith C Ng | ITW | Repair | | | 2a2 window installation and beamtube repair | Yesterday
we installed the 2a2 window, the drive screw
was torqued until 70 ft-lbs and we stopped, |
 |
1723
|
Thursday, May 24, 2018, 15:19 |
Keith C Ng | Assembly/Bench Test | Repair | TM2 | | tm 2 source tray build | Attached alignment check notes after brazing
and fabrication.
First page lower half shows establishment |
|
2371
|
Monday, October 03, 2022, 14:28 |
Keith C Ng | Assembly/Bench Test | Maintenance | | | ITA2826 rev E assembly | A fully built steerer sub assembly ITA2826
revision E was boxed and sealed and put on
rack storage in ISAC B2 South Hot Cell area. |
|
2549
|
Wednesday, March 13, 2024, 11:12 |
Keith C Ng | Assembly/Bench Test | Repair | TM3 | | optics tray for tm3 | Alignment notes attached for the optics
tray for the refurbished tm3 with the new
service and source tray. |
|