831
|
Thursday, January 08, 2015, 10:34 |
chad fisher | South Hot-Cell | Standard Operation | | | TM2 Tray Build Status and Problems | Final assembly of the source tray for TM2
was started this morning.
Sliding tray was received from keensert |
   |
833
|
Monday, January 12, 2015, 14:29 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Build Status | Countersink problem with supports has been
remedied. Scratches, dings, and pitting has
been buffed out and supports re-cleaned and |
|
837
|
Thursday, January 29, 2015, 11:31 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Build | On Tuesday morning I attempted to complete
assembly of the source tray for TM2 however
discovered that 3 1/4-20 x 0.25 titanium |
|
838
|
Monday, February 02, 2015, 09:59 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Build | Missing heli coils installed this morning.
Threads had to be chased with tap
for 1/4-20 heli coil and missing countersinks |
|
834
|
Tuesday, January 20, 2015, 13:45 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Alignment | TM2 Tray Alignment is complete except for
verification with alignment tray.
First attempt results were: |
 |
835
|
Monday, January 26, 2015, 09:36 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Alignment | TM2 tray alignment was confirmed with the
alignment tray this morning:
Front target 0.000 vertically, 0.000 |
|
2473
|
Tuesday, August 08, 2023, 13:01 |
David Wang | North Hot-Cell | Standard Operation | TM2 | TiC#6 | TM2 TiC#6 post run electrical check at NHC. | TM2 TiC#6 post run electrical check has
been done at TCS. See attachment |
|
2770
|
Friday, February 14, 2025, 11:35 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 TP1/TP2 and TCS TP1S have been started at TCS. | TM2 TP1/TP2 and TCS:TP1S have been started
at TCS. The starting time and operation of
turbo pumps are ok. TM2 had been stored in |
|
964
|
Friday, June 26, 2015, 09:45 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | Containment box window waterlines have
been connected and leak checked and new containment
box cover installed. |
|
986
|
Wednesday, July 08, 2015, 14:48 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | Water block jig has been removed. Stuck
source tray side water block jig component
has been removed. An attempt was made to |
|
1000
|
Thursday, July 16, 2015, 14:36 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | IMG gauge, clip for ground to window lines
and gas line extensions were installed today.
David and I also tried to locate |
 |
1001
|
Friday, July 17, 2015, 13:51 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | Gas lines extensions installed yesterday
were too long and gas lines touched top inside
of containment box. They have been removed |
|
1002
|
Monday, July 20, 2015, 14:12 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | Ultem high voltage spacer installed and
9 pin banana plug plugged in. Target has
been inserted into the hot cell and will |
  |
1035
|
Thursday, August 13, 2015, 13:46 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | As previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to |
|
1874
|
Friday, February 22, 2019, 10:31 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source tray removal | The source tray has been removed from TM2. |
6x |
1879
|
Friday, March 01, 2019, 09:57 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source tray removal | TM4 optics tray was installed onto the
old TM2 source tray yesterday and tray filled
with non-active metal scrap. Tray inserted |
   |
1733
|
Friday, June 08, 2018, 11:36 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Removal Progress | The containment box has been removed from
TM2, the Enzel lens and steerers disconnected
and optics tray removal has commenced. |
|
955
|
Friday, June 19, 2015, 11:57 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Progress | Window waterline has been successfully
connected using 1 1/2 inch long non-blunt
start 1/4-28 bolts. |
|
949
|
Tuesday, June 16, 2015, 14:28 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Installation/Water Block Sealing Surface Clean | Today cleaning and polishing pads were
inserted into the hot cell.
Module side waterblock jig installation |
  |
952
|
Friday, June 19, 2015, 09:37 |
Isaac Earle | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Installation - June 18, 2015 | The following work was done on
June 18 2015:
- Finished cleaning and polishing |
|