  652   Wednesday, April 16, 2014, 17:08 Keith C NgITERepair  2a3 window - He leak checkHelium leak checked 2a3 window after installing
using remote line: 
- There was a leak found between
  
  899   Monday, April 27, 2015, 16:12 Keith C NgSouth Hot-CellDevelopmentTM2 Ceramic Standoffs in TM2 source tray steerer assemblyOn drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001".
 IMG_3106.JPG 
  1461   Friday, March 24, 2017, 11:12 Keith C NgSpent Target VaultStandard Operation  2A window transferTransfered the 2A window from the ISAC
Storage Vault to the Cyclotron Vault Tunnel
Storage area. RPG storage form attached.
 2017mar24_vault_tunnel_storage_form(1).pdf 
  1462   Friday, March 24, 2017, 11:19 Keith C NgSpent Target VaultStandard Operation 2A3 windowWindow now in vault


   
        
            
 2017mar24_vault_tunnel_storage_form(1).pdf 
  1592   Wednesday, August 02, 2017, 15:41 Keith C NgAssembly/Bench TestDevelopment  spare source tray buildAfter re zeroing alignment telescope to
master jig and adjusted parts into place:
 
 20170802_sourcetray_RHB_8264.JPG20170802_sourcetray_RHB_8266.JPG 
  1640   Wednesday, October 11, 2017, 15:50 Keith C NgAssembly/Bench TestStandard Operation  spare source tray build alignment 
 
Spare
  
  1642   Friday, October 13, 2017, 11:14 Keith C NgAssembly/Bench TestStandard Operation  source tray alignment/buildSource tray is complete for brazing, gas
line bracket is currently missing but can
be made in parallel with tube bending operations.
 20171013_sourcetray_P1030815.JPG20171013_sourcetray_P1030816.JPG20171013_sourcetray_P1030817.JPG20171013_sourcetray_P1030818.JPG 
  1703   Friday, April 20, 2018, 15:33 Keith C NgITWRepair  ITW beam tube repair job2A2 window has been removed from ITW and
beamlines has removed the beamtube from the
penetration. The penetration has been sealed
 20180420_2a2beamtuberepair_P1040034.JPG20180420_2a2beamtuberepair_P1040030.JPG20180420_2a2beamtuberepair_P1040029.JPG20180420_2a2beamtuberepair_P1040036.JPG 
  1704   Friday, April 27, 2018, 15:06 Keith C NgITWRepair  ITW beam tube repairVacuumed out remainder of debris from the
wall penetration, removed cradle and checked
condition. Down stream support bracket sees
 6x 
  1705   Tuesday, May 01, 2018, 10:54 Keith C NgITWRepair  2a2 window installation and beamtube repairYesterday
we installed the 2a2 window, the drive screw
was torqued until 70 ft-lbs and we stopped,
 20180420_2a2beamtuberepair_P1040025.JPG2018_2a2window00017.jpg 
  1723   Thursday, May 24, 2018, 15:19 Keith C NgAssembly/Bench TestRepairTM2 tm 2 source tray buildAttached alignment check notes after brazing
and fabrication.
First page lower half shows establishment
 20180524_alignmentcheckresults.pdf 
  2371   Monday, October 03, 2022, 14:28 Keith C NgAssembly/Bench TestMaintenance  ITA2826 rev E assemblyA fully built steerer sub assembly ITA2826
revision E was boxed and sealed and put on
rack storage in ISAC B2 South Hot Cell area.
  
  2549   Wednesday, March 13, 2024, 11:12 Keith C NgAssembly/Bench TestRepairTM3 optics tray for tm3Alignment notes attached for the optics
tray for the refurbished tm3 with the new
service and source tray.
 20240313_optics_tray_alignment_notes.pdf 
  2471   Thursday, August 03, 2023, 12:24 Jason ZhangCraneDevelopment  Cleanup of camera installation on target hall crane, installation of replacement laser The cleanup of
the ISAC Target Hall crane and installation
 LaserProgramCalibrationLocation.pngSICK_Laser_Upgrade_Calibration.xlsxInstallation_IMG.png 
  446   Tuesday, September 10, 2013, 12:11 Isaac EarleSouth Hot-CellRepairTM3 Module side heat shield water block polishing and blank-off installation The sealing surfaces of the module
side heat shield water block were polished
on September 9th in the morning using Chad's
  
  894   Tuesday, April 21, 2015, 17:14 Isaac EarleSouth Hot-CellStandard OperationTM1UC#12UC#12 Installed in TM1On Friday April 17th, UC#12 target was
installed in TM1.  One of the copper
water lines was bent slightly as the target
 IMG_4836.JPGIMG_4833.JPG 
  952   Friday, June 19, 2015, 09:37 Isaac EarleSouth Hot-CellRepairTM2 TM2 Source Tray Installation - June 18, 2015 The following work was done on
June 18 2015:
- Finished cleaning and polishing
  
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box RemovedThe containment box was taken off TM2 in
preparation for installation of a new coil
line isolator.
  
  1221   Wednesday, May 04, 2016, 11:14 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Scope DecisionA meeting was held on May 4, 2016 to determine
the scope of the North Hot Cell project.
 The following was agreed upon by those
  
  1294   Friday, July 29, 2016, 14:27 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Measurements & Cleanup The North
Hot Cell was accessed today via the Ante
  