949
|
Tuesday, June 16, 2015, 14:28 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Installation/Water Block Sealing Surface Clean | Today cleaning and polishing pads were
inserted into the hot cell.
Module side waterblock jig installation |
|
952
|
Friday, June 19, 2015, 09:37 |
Isaac Earle | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Installation - June 18, 2015 | The following work was done on
June 18 2015:
- Finished cleaning and polishing |
|
956
|
Friday, June 19, 2015, 13:00 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Install Status | Left manipulator now broken. Master side
however, so repair can take place Monday
or Tuesday. |
|
937
|
Tuesday, June 09, 2015, 14:36 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | TM2 Source Tray Final Inspection | Final inspection took place with Pierre,
Grant, Friedhelm and Anders present.
Two action items were raised: |
|
935
|
Monday, June 08, 2015, 14:40 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | TM2 Source Tray Final Alignment Check | Final Alignment checks of the TM2 source
tray took place today.
Mater Jig: Front - 0,0 Back - 0 left, |
|
936
|
Tuesday, June 09, 2015, 09:49 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | TM2 Source Tray Final Alignment Check | Final alignment continued this morning.
Steerers have been aligned to 0.001
low, 0.000 left/right wrt master jig. |
|
934
|
Thursday, June 04, 2015, 08:27 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | TM2 Source Tray C-seal removal and inspection | Source tray for TM2 has been moved to the
alignment area by Dan and co.
This morning Dan removed the c-seals |
|
2472
|
Tuesday, August 08, 2023, 12:59 |
David Wang | ITW | Standard Operation | TM2 | SiC #6 | TM2 SiC#6 dhas been disconnected in ITW | TM2 SiC#6 has been disconnected in ITW.
See check list |
|
2035
|
Friday, November 29, 2019, 13:10 |
David Wang | ITE | Standard Operation | TM2 | SiC 39# febiad | TM2 SiC#39 connection check list. | TM2 has been connected in ITE.
All turbo-pumps are started. |
|
2030
|
Tuesday, November 19, 2019, 13:41 |
David Wang | ITE | Standard Operation | TM2 | SiC 38# febiad | TM2 SiC#38 connection check list. | TM2 was connected in ITE 12th Nov. attach
checklist |
|
1551
|
Wednesday, June 07, 2017, 13:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 SiC#36 leakc check and electrical check. | The results are good. See attachment. |
|
2077
|
Thursday, March 05, 2020, 07:16 |
David Wang | South Hot-Cell | Standard Operation | TM2 | SiC #39 | TM2 SiC #39 post run electrical checklist | Electrical check result is fine.
See attachment. |
|
2032
|
Wednesday, November 27, 2019, 13:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | SiC 38# febiad | TM2 SiC #38 disconnection checklist. | TM2 was disconnected in ITE yesterday. |
|
1009
|
Wednesday, July 22, 2015, 12:13 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Short Findings | Pin X was unplugged, short remained, however
any slight pressure on the block towards
the source tray makes the short go away. |
|
2283
|
Wednesday, January 05, 2022, 12:45 |
Frank Song | ITW | Maintenance | TM2 | UC#36 | TM2 SIS with Target and No external Connections | electrical checked in ITW |
|
963
|
Friday, June 26, 2015, 09:44 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Retrofit Status | On June 25th the following work was completed:
Optics tray was installed into TM2.
The lower fastener on the vertical cable |
|
807
|
Tuesday, December 02, 2014, 10:15 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Reburb. Loop Install | Final polish, clean with methanol and clean
compressed air.
Loop installed and torqued to 90 |
|
805
|
Monday, December 01, 2014, 14:06 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 REFURB. WATER LOOP TEST | Some issues with the turntable and having
to wait for a decision on whether to remove
TM2 from the hot cell so that TM4 with dead |
|
951
|
Thursday, June 18, 2015, 08:03 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Optics Tray Transfer | The TM2 optics tray has been transferred
from the source tray to the transfer fixture
in preparation for installation of the source |
|
879
|
Tuesday, March 31, 2015, 11:36 |
chad fisher | South Hot-Cell | Development | TM2 | | TM2 Optics Tray Complete | TM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right |
|