Tuesday, June 07, 2022, 14:15, Frank Song, ITE/ITW, Standard Operation, TM2, SiC#42, Module Connection
|
TM2 with Febiad target SiC#42 was connected in ITW. |
Thursday, June 09, 2022, 09:47, Matthew Gareau, South Hot-Cell, Repair, TM2, SiC#42, containment box repair, Einzle lens, multi pin
|
On June 2 2022, while attempting to install target SiC#42 a gasket fell off the water line. I attempted to remove the target to have the gasket reattached, however the multi pin connector guide pin was loose and was preventing the target from being removed. During the attempt to remove the target it was noticed that an electrical cable in the back of the module had become loose and was dangling. The target was then secured to the module, and then the module was moved to the SHC to complete the job/repairs.
June 3 2022, containment box was removed, Einzle Lens cable reattached and tested, and the multi pin guide pin was retightened.
On June 6 2022, the containment box was damaged while lifting the containment box back onto the module.
The left rear corner of the box caught on the module and the corner weld snapped and folded the corner down about 90 degrees.
With help from Chad, we were able to restraighten the corner with a C-clamp, enabling the box to be reattached to the module.
However the 2 bolts that were on the corner that attach to the module were not able to be aligned and were not used.
The target was reattached to the module, and to save time was brought directly to ITW, skipping the conditioning station. |
Monday, June 20, 2022, 11:00, Frank Song, North Hot-Cell, Repair, TM2, SiC#42, Failed Sic#42 electrical measurement at NHC
|
An electrical check was done at NHC, see attachment pls. |
Wednesday, July 06, 2022, 10:30, Travis Cave, Spent Target Vault, Standard Operation, , SiC#42, Spent Target Move
|
The spent SiC#42 was moved from the north hot cell to the spent target vault, it was placed in pail #271 and put in spot 2B. see attached PDF for more details. |
Wednesday, September 15, 2021, 08:39, Travis Cave, ITE, Standard Operation, TM4, SiC#41, Module move
|
TM#4 with SiC#41 has been moved from the NHC to ITE. |
Monday, October 04, 2021, 10:52, Travis Cave, North Hot-Cell, Standard Operation, TM4, SiC#41, Module move
|
TM#2 moved from ITE to NHC SiC#41 removed and then moved back to ITE. |
Wednesday, October 13, 2021, 11:54, Travis Cave, North Hot-Cell, Standard Operation, , SiC#41, Spent Target Move
|
The spent SiC#41 target has been placed in pail #260 and placed in spot 5B of that spent target vault. See attached PDF for details. |
Tuesday, September 14, 2021, 09:18, Travis Cave, South Hot-Cell, Repair, TM4, SiC#40, Module move
|
TM#4 with SiC#40 has been moved from the east target station to the south hot cell. |
Friday, November 29, 2019, 11:03, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#39, Module move
|
TM#2 with the SiC#39 target has been moved from the south hot cell to the east target station. |
Thursday, February 27, 2020, 09:50, Travis Cave, Safe Module Parking, Standard Operation, TM2, SiC#39, Module move
|
TM#2 with SiC#39 has been moved from the east station to the smp. |
Thursday, November 18, 2021, 09:47, Travis Cave, Spent Target Vault, Standard Operation, , SiC#38 and UC#29, Spent Target Move 
|
The spent targets SiC#38 and UC#29 have been removed from the spent target vault and placed into the mini storage. See attached PDF for details. |
Friday, November 29, 2019, 11:02, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#38 SiC#39, Electrical Check 
|
Results from the electrical check with the old SiC#38 target and the new SiC#39. |
Thursday, November 07, 2019, 08:56, David Wang, Conditioning Station, Standard Operation, TM2, SiC#38, TM2 in TCS.
|
Helium pressure leak check on TM2 HS line at TCS is done. No leak. Also, Helium are sprayed to gas line adapter and fittings. No leak. TM2 is connected at TCS. Anode plug on TCS is connected to module 52pin connector. Water system is started. Vacuum pumping down is good. HV cover will be installed today. |
Thursday, November 07, 2019, 10:39, Anders Mjos, Conditioning Station, Standard Operation, TM2, SiC#38, Conditioing SiC#38
|
Thursday, November 07, 2019, 10:35: Tested source to 30 A on TGHT, TBHT and COIL. ANODE at 100 V.
Tuesday, November 12, 2019
The FEBIAD source worked well over the weekend. The anode current limit was adjusted twice to stop voltage limiting. About 5E-8 A on the FC with TGHT=580A, TBHT=300A, ANODE=200V,150 mA, COIL=50A. Bias was conditioned to 30 kV |
Tuesday, November 12, 2019, 10:02, Adam Newsome, ITE, Standard Operation, TM2, SiC#38, TM2 Move
|
TM2 was moved from the Conditioning Station to ITE, with SiC#38 target. |
Tuesday, November 26, 2019, 10:24, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#38, Module move
|
TM#2 with SiC#38 has been moved from ITE to the south hot cell. |
Tuesday, December 03, 2019, 12:45, Adam Newsome, Spent Target Vault, Standard Operation, , SiC#38, SiC#38 in Pail 205 moved to Storage Vault: 4B
|
SiC#38 in Pail 205 was moved to section 4B of the storage vault. Dose rate when retrieving from Hot Cell was 22.2 mSv/h. |
Wednesday, October 18, 2017, 10:45, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#37, Electrical Check
|
The results of the electrical check of TM#4 with SiC#37, see attached PDF. |
Wednesday, October 18, 2017, 10:46, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#37, Module move
|
TM#4 with SiC#37 has been moved from the south hot cell to the conditioning station. |
Thursday, October 19, 2017, 14:20, Anders Mjos, Conditioning Station, Standard Operation, TM4, SiC#37, SiC#37 Conditioning 
|
Thursday, October 19, 2017, 14:20: EE configured for conditioning. HV cage locked up
Thursday, October 19, 2017, 16:46: BIAS / EL / EE at 45 / 22.5 / 0 kV
Thursday, October 19, 2017, 17:16: 30 min without sparking. Lowering to 0. Continue conditioning tomorrow.
Friday, October 20, 2017, 08:22: Resuming HV conditioning
Friday, October 20, 2017, 08:44: BIAS / EL / EE at 45 / 22.5 / 0 kV
Friday, October 20, 2017, 09:48: No sparking. Continue conditionoing
Friday, October 20, 2017, 10:40: BIAS / EL / EE at 50 / 22.5 / 0 kV
Friday, October 20, 2017, 11:30: HV spark (at 52.5 kV) tripped TP2 and TP1s resulting in IG1S and power supplies tripping.
Friday, October 20, 2017, 13:50: Gelo is troubleshooting flickering on/off of ANODE, TGHT and TBHT power supplies.
Friday, October 20, 2017, 13:51: BIAS / EL / EE at 50 / 25 / 0 kV
Friday, October 20, 2017, 14:26: BIAS / EL / EE at 55 / 28 / 0 kV
Friday, October 20, 2017, 14:37: TP2 tripped on spark
Friday, October 20, 2017, 14:51: Gelo has determined there is a communication problem with the PLC on the HV platform. Troubleshooting continues.
Friday, October 20, 2017, 19:02: Troubleshooting did not succeed. Not able to control power supplies. Troubleshooting continue on Monday.
Monday, October 23, 2017, 09:00: After starting the TCS again today communication has been reestablished. Started heater conditioning.
Monday, October 23, 2017, 14:03: Heater ramping previously aborted and ramp down started due to ongoing PLC communication issues. TGHT and TBHT power supplies tripped on timeout around 13:45. Gelo will continue the troubleshooting.
Monday, October 23, 2017, 19:55: Switching off source after operating for 5 hours without any communication glitches detected (fiber optic communication cables swapped between HV platform and BIAS/EZL PLCs) |
|