ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  2246   Friday, September 17, 2021, 12:34 Frank SongITEStandard OperationTM4Sic#41Module Connection TM4 with a new target was moved back
from NHC to ITE and reconnected at pit. The
5 shielding blocks were installed as well.
 IMG_3602.jpgIMG_3601.jpgIMG_3600.jpgIMG_3599.jpg 
  2254   Monday, October 04, 2021, 09:37 Frank SongITEStandard OperationTM4Sic#41module disconnection TM4 was disconnected and moved to
NHC. 
 IMG_3715.jpgIMG_3716.jpgIMG_3717.jpg 
  2322   Thursday, May 19, 2022, 11:42 Travis CaveSpent Target VaultStandard Operation Sic#39, Ta#59, C#2, UC# 32 & 30Targets moved to the mini vault. Sic#39, Ta#59, C#2, UC# 32 &
30 have been moved from the spent target
vault to the mini vault. See the attached
 Target_Index_2022-05-19.pdfMini_Vault_Target_Index_2022-05-19.pdf 
  280   Wednesday, March 27, 2013, 11:49 David WangITEStandard OperationTM4Sic LIS-RFQ Connected TM4 in ITETM4 has been reconnected to ITE after the
module moving. The roughing is started .
The water will be supplied to ITE after 
  
  281   Wednesday, March 27, 2013, 12:08 David WangSouth Hot-CellStandard OperationTM4Sic LIS-RFQTM4 heat shield circuit leak check with SiC LIS-RFQ targetChad and I did the TM4 heat shield leak
check yesterday at SHC. The leak detector
was pumped to 4.6 xE-9atm.cc/sec, and 0.0xE-4
  
  409   Wednesday, July 24, 2013, 17:46 David WangConditioning StationStandard OperationTM4Sic 29#Started 3 turbo pumps on CS for TM43 turbo pumps on TM4 and CS have been started.
The pumping down is good so far, The TM4
PNG1 reading is more than 10 times higher
  
  284   Wednesday, April 03, 2013, 12:26 David WangITEMaintenanceTM4Sic LIS/RFQLeak check on ITE TM4.TM 4 had been leak check in ITE due to
  relatively high PNG1 and IG1 readings.All
TM4 primary and secondary  vessel air
  
  2625   Tuesday, June 25, 2024, 12:49 Frank SongITEStandard OperationTM3SiC#46Module Connection TM3 with new target SiC#46 was connected
in ITE.
 TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf 
  2630   Thursday, July 04, 2024, 01:20 Carla BabcockITEDevelopmentTM3SiC#46TM3 conditioning with protonsInitial Summary:
TM3 sparking behaviour in ITE has
been very disruptive both with and without
  
  2646   Tuesday, August 06, 2024, 09:16 Frank SongITEStandard OperationTM3SiC#46module disconnection TM3 with spent target SiC#46 was
disconnected in ITE and ready to move to
TCS soon.
 TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf 
  2659   Wednesday, August 14, 2024, 11:29 Aaron TamWaste Package/ShipStandard Operation SiC#46Target Disposal and visual check  SiC#46 loaded into pail 293 successfully
along with other hotcell waste 
Upon visual inspection of the target,
 SiC46.jfif 
  2660   Friday, August 16, 2024, 08:47 Travis CaveSpent Target VaultStandard Operation SiC#46Spent Target Move SiC#46 (pail 293) was placed in the
vault (spot 3B) on Wednesday the 14th
of August. It was 111 mSv/hr when removed
 Target_Index_2024-08-16.pdf 
  2457   Tuesday, June 13, 2023, 11:49 Frank SongNorth Hot-CellStandard OperationTM4SiC#45electrical check and leak check TM4 with new target SiC#45 installed
has been leak checked and electrical checked
on top of NHC.
 TM4_with_SiC#45_leak&electric_check_on_top_of_NHC.png 
  2458   Wednesday, June 14, 2023, 07:10 Frank SongITEStandard OperationTM4SiC#45TM4 with SiC#45 connection in ITE TM4 with new target SiC#45 was connected
in ITE, all TPs are running at their full
speed.
 TM4_with_SiC#45_connected_in_ITE_20230613.pdf 
  2464   Tuesday, July 18, 2023, 10:08 Frank SongNorth Hot-CellStandard OperationTM4SiC#45module disconnection & electrical check right after transferred from ITE to NHC TM4 with spent target SiC#45 was
disconnected ITE  and an electrical
check made right after moved on NHC. 
 TM4_with_SiC45_disconnection_and_e_check.pdf 
  2467   Tuesday, July 25, 2023, 16:25 Carla BabcockNorth Hot-CellStandard Operation SiC#45SiC#45 post irradiation inspectionLooked at SiC#45 in the hot cell. Looked
very clean, no deposits on the heat shield
or other components. Target also looked very
  
  2358   Thursday, August 18, 2022, 10:41 Frank SongITE/ITWStandard OperationTM4SiC#44TM4 with SiC#44 connection in ITE TM4 with target SiC#44 was connected
in ITE on Tuesday.
 TM4_with_SiC#44_connection_in_ITE.jpg 
  2359   Tuesday, August 23, 2022, 10:51 Carla BabcockITERepairTM4SiC#44TBHT to HV common short on SiC#44-TM4TM4 with SiC#44 installed developed a short
TBHT to HV common during its first heating
in ITE. Was fine before installation. Now
  
  2377   Thursday, October 13, 2022, 09:32 Travis CaveSpent Target VaultStandard Operation SiC#44Spent Target Move Spent target move done. The SiC#44
was moved from the north hot cell to the
spent target vault. It was placed in pail#275
 Target_Index_2022-10-13.pdf 
  2379   Wednesday, October 19, 2022, 12:00 Carla BabcockNorth Hot-CellStandard OperationTM4SiC#44PIE on SiC#44Conducted PIE on SiC#44, which failed online.
It had a cathode short, a target short and
an anode short by the time we called the
 SiC44_PIE_20221012_150145.jpgSiC44_PIE_20221012.jpgSiC44_PIE_20221012_161755.jpg 