333
|
Wednesday, May 08, 2013, 13:48 |
chad fisher | South Hot-Cell | Repair | TM3 | | IMG wiring check |
Checks of the wiring for the IMG are complete and have passed. |
334
|
Thursday, May 09, 2013, 10:13 |
chad fisher | South Hot-Cell | Development | | | Mock-up Progress |
The source tray for the mock-up has been setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the photos for the TM3 rebuild that took place in the anteroom in 09' and Maico and Dan for the support in ironing the issues with the source tray side soldering issues.
|
335
|
Thursday, May 09, 2013, 14:23 |
chad fisher | South Hot-Cell | Repair | TM3 | | Water Block Jig Removal |
The source tray side of the water block jig has been removed in preparation for moving the module to the conditioning station for electrical tests. |
336
|
Friday, May 10, 2013, 09:26 |
chad fisher | South Hot-Cell | Repair | TM3 | | Containment box reinstalled |
the containment box has been reinstalled onto TM3. After electrical checks it is ready to move to the conditioning station...for electrical tests. |
351
|
Friday, May 17, 2013, 10:04 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair |
Manipulator has been sucessfully repaired. Recieved 0.19 mSv. Took Approx. 10-20 minutes |
356
|
Wednesday, May 22, 2013, 14:11 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#40 | Ta#40 installed |
Ta#40 has been installed.
Leak checking and high voltage tomorrow before the move. |
364
|
Monday, May 27, 2013, 11:55 |
chad fisher | South Hot-Cell | Standard Operation | | | Special Tooling for RFQ target |
The special tool made for the RFQ target autopsy has been inserted into the hot cell.
4-40 button head screws have been successfully lossened. |
372
|
Wednesday, May 29, 2013, 12:07 |
chad fisher | South Hot-Cell | Development | | SiC#28 RFQ | RFQ Autopsy |
Major portions of the RFQ target have now been sucessfully dismantled. More minor dismantling with conclude this afternoon. |
378
|
Thursday, June 13, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM3 | | Source Tray/Extraction Column Removal |
TM3 Rev 2 source tray/extraction column insertion into its storage was completed yesterday and it was then removed from the hot cell and put into the anteroom until June 25th when it will be moved into the vault tunnel.
The Box did have 10000 counts of contamination "all over" it. It has recieved inital decontamination and is down to 1000 counts.
|
379
|
Thursday, June 13, 2013, 09:21 |
chad fisher | South Hot-Cell | Development | | | Warm Cell Mock-up |
the warm cell mock-up has been inserted into the warm cell and final preparation for the remote test are being made. |
380
|
Tuesday, June 18, 2013, 14:00 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up testing / water block connections |
The testing of the mock-up and tooling has commenced.
Source tray mock-up has been driven into the mock-up and the first two water block connections have been made; the first with the torque limiting
T-handle tool and the second with the torque limiting air rachet attachment. Both seem to work well, although achieving the required torque with the manipulators proved to be near the limit of the manipulator.
|
381
|
Wednesday, June 19, 2013, 08:15 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock up water block connections |
All water block connections on the mock-up have bben achieved. It is now ready for leak checking.
The front half of the water block jig proved extremely difficult to remove. |
383
|
Friday, June 21, 2013, 09:26 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up Leak Check Results |
The Mock-up has been leak tested after the remote connection of the water blocks and is leak tight!
Thanks everybody who contributed to its success. |
388
|
Thursday, June 27, 2013, 14:21 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ucx#6 | Ucx#6 installed Ta#39? rewmoved |
Ucx#6 was installed on TM1 on Wednesday.
Ta#39 was removed. |
389
|
Thursday, June 27, 2013, 14:23 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 Autopsy performed |
An autopsy of Ta#39 was performed yesterday and today. Ta#39 will be sent to the spent target storage vault on Tuesday.
|
390
|
Thursday, June 27, 2013, 14:27 |
chad fisher | South Hot-Cell | Development | | | Polishing Cleaning tool - Water blocks |
The polishing/cleaning tool prototype is now finished and appers to work great.
Thanks to Dan and Maico for the great job making my design a reality. |
391
|
Tuesday, July 02, 2013, 09:37 |
chad fisher | South Hot-Cell | Development | TM3 | | TM3 Rev.2 Source Tray Disposal |
Tm3 Rev.2 source tary has been transfered to the vault tunnel storage. |
393
|
Wednesday, July 03, 2013, 08:43 |
chad fisher | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault |
|
397
|
Friday, July 05, 2013, 09:22 |
chad fisher | South Hot-Cell | Repair | TM3 | | Service Tray Water Block Inspection |
I have inspected the service tray water block and suggest that they SHOULD be cleaned/polished before we install the new source tray.
The water blocks have slight water scalling to the inside of the ID of where the c seals locate.
I have taken two close up pictures of each water block for reference and to document their current state. They can be found at http://documents.triumf.ca/docushare/dsweb/View/Collection-10841
|
420
|
Thursday, August 15, 2013, 09:32 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 source tray installation status |
The installation of the module side water block jig has been successful.
During initial attempts yesterday afternoon, installation of the jig proved, as expected to be extremely difficult. This was primarily due a poorly position water block from a previous repair were the soldering jig had not been used to position the block; specifically coil 1. This is the same block that contributed with the difficulties in removing the old source tray.
I was able to utilize the water block polishing tools as handles to reposition this water block ( as well as another slightly difficult one) into its location in the water block jig.
Please be aware, as the jig was very difficult to install, it will be very difficult to remove later (as it was when removing the old source tray).
Chad |