  RH-ISAC, Page 3 of 140  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject
  2756   Wednesday, January 29, 2025, 09:06 David WangITE/ITWStandard Operation  ITE and ITW water system paddle wheels and coils on flow sensors have been replaced

ITE and ITW water system paddle wheels and coils on all flow sensors in pits have been replaced. It's a SAS job.

  2755   Tuesday, January 28, 2025, 11:47 David WangConditioning StationStandard OperationTM3No targetTm3 has been moved from TCS to silo.

Tm3 has been moved  from TCS to silo. The move is successful.

  2754   Monday, January 27, 2025, 08:27 om David WangSouth Hot-CellMaintenance parasite targetTransfer parasite target from SHC to NHC.

A parasite target has been transferred from SHC to NHC. It is a job to reduce SHC field for coming SHC entry job. The transfer is successful.

  2753   Wednesday, January 22, 2025, 10:29 Frank SongFaraday CageMaintenance  Annual clean up for ITE/ITW Faraday cages

 David and I cleaned both cages in ISAC1 electric room, all done.

  2752   Tuesday, January 21, 2025, 10:46 David WangITE/ITWStandard Operation  ITW/ITE pit general annual cleaning up.

ITW/ITE pit general annual cleaning up were done. all concrete floor and TM equipment surface are vacuum  cleaned. HV cage inside and blue nylon insulators were wiped by paper.

  2751   Monday, January 20, 2025, 11:33 Adam NewsomeWaste Package/ShipStandard Operation   F-308 flask loading - six flasks loaded

Today (2025-01-20), six flasks were loaded in preparation for shipment with the following targets: C#4, TiC#5, Ta#64,Ta#62, Nb#10, SiC#44

Some of the pails (256, 273, 279, 277) required replacement of the wire rope cable with new style, 30 ft length, as requested by CNL. A lifting label was also applied to these pails. Some of the pails (295, 298) already had the appropriate cable and lifter label.

 

At the time of writing this log:

  • The second crimped lifting loop has not yet been applied to each pail.
  • The locks have not yet been applied to the flasks.

 

The mini-storage vault is now EMPTY. The mini-storage vault has been swiped and checked for contamination.

The target index spreadsheet has been updated (attached).

  2750   Thursday, January 16, 2025, 14:21 David WangConditioning StationStandard OperationTM3No targetTM3 electrical check at TCS under good vacuum

A complete TM3 electrical check at TCS under good vacuum has been done. Pin 14 to 60KV only has 8K ohm on ohmmeter check , and it's about 2Kohm @250V Megga. It's low in resistivity. The pin 14 is for thermocouples only so no big concern.  The rest things are good. See attachments.

  2749   Thursday, January 16, 2025, 10:03 Travis CaveSpent Target VaultStandard Operation UC#47Spent Target Move

 The spent UC#47 was moved from the south hot cell to the spent target vault placed in pail #302 in spot 1C of the vault, it was 24.5mSv/hr when removed from the south hot cell. See attached for vault details.

  2748   Tuesday, January 14, 2025, 10:00 David WangSouth Hot-CellStandard OperationTM3UCx#47after operation electrical check, Tm3 UCx 47

TM3 UCx#47 after operation electrical check  is done at SHC. The result is normal. See attachment.

  2747   Monday, January 13, 2025, 10:36 Frank SongITEStandard OperationTM3UCx#47module disconnection

 TM3 with spent target UCx#47 was disconnected in ITE and will be moved to SHC.

  2746   Monday, January 13, 2025, 10:02 Travis CaveSpent Target VaultStandard Operation UC#46Spent Target Move
UC#46 was placed in pail# 301 in spot 1B and was 26.3mSv/hr when removed from the SHC. See attached PDF for vault 
details.
  2745   Thursday, January 09, 2025, 11:46 David WangSafe Module ParkingStandard OperationTM4No targetSMP is under vacuum for TM4 storage during shut down.

 SMP:MP1 is started with SMP BV1 is opened. SMP is under vacuum for TM4 storage during shut down.

  2744   Thursday, January 09, 2025, 11:08 David WangFacilitiesMaintenance  ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings

ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings and investigation in pit. A fault 17644 has been issued. this pump will be replaced in March when general fielding in vacuum pit is reasonable for the job.

  2743   Wednesday, January 08, 2025, 07:37 chad fisherSouth Hot-CellStandard OperationTM4UCx#46UCx#46 removal

UCx#46 removed from TM4 and placed into a pail back-filled with argon. Nothing visually unusual; no issues.

  2742   Tuesday, January 07, 2025, 12:05 David WangITEStandard OperationTM3UCx #47ITE primary and secondary vacuum vessel leak check for 2025 shut down

ITE primary and secondary vacuum vessel leak check for 2025 shut down have been done. No leak.  The TM3 waterlines helium pressure test will be done at TCS when module is there.

TM3 water lines helium pressure test  are done. 70 psi helium 3 minutes to each line( except HS which has no target on it ) . leak detector base leak rate :0.0Xe-9 atm.cc/sec. No leak on all tested water lines.Helium were purged out after test. and 60 psi nitrogen were filled in lines for storage. 

  2741   Monday, January 06, 2025, 08:38 Frank SongITWStandard OperationTM4UCx#46module disconnection

 TM4 WITH UCx#46 was disconnected in 2025-01-02 in ITW. Forms attached.

  2740   Friday, January 03, 2025, 12:34 Frank Song5 Shielding BlocksMaintenance UCx#47shielding blocks moving

 Five shielding blocks are moved from ITE to storage area ( one of them is sitting on B2 as limit of room) for target stations maintenance in 2025 winter shut down .

  2739   Friday, January 03, 2025, 10:41 David WangITWStandard OperationTM4UCX46ITW primary and secondary vacuum vessel leak check for 2025 shut down

ITW primary and secondary vacuum vessel leak check for  2025 shut down has been done. Also,TM4 internal water line helium pressure test has been finished.  Both results are normal. There are two small old leak on EXit 1 and Exit2 module top plate  o-ring under 1Xe-8 atm.cc/sec which we knoew in past years test. resin spray on leak  area reduce the leak ratee below 5Xe-9 atm.cc/sec. No concern on these small leak.   See attachment  for detail results.

  2738   Friday, January 03, 2025, 09:59 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target Hall

A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Hot Cells:
    • NHC right manipulator gripper stuck (known, repair planned)
  • Target Hall:
    • 50% of overhead light bulbs burnt out (David Wang contacted Electrical Services to rectify)
    • One RH camera for target pit not working (Travis Cave notified)

Action has been taken on all deficiencies.

  2737   Wednesday, December 18, 2024, 14:17 Adam NewsomePail Handling ToolMaintenance  Pail Handling Tool - Inspection

An informal inspection of the main Pail Handling Tool was performed today as the final one for the year. Note that the main formal annual inspection was performed June 18, 2024 for this year.

The attachment to this e-log serves as a record of all inspections for this tool throughout 2024.

The spare tool was not inspected as it was not in service this year.