  322   Wednesday, April 24, 2013, 14:09 chad fisherSouth Hot-CellRepairTM3 TM3 Refurbishment E.O.D. Optics tray has been removed from module.
Waterblock jig installation has commenced.
Of note, jig installation on TM3 has proven
  
  323   Friday, April 26, 2013, 11:20 chad fisherSouth Hot-CellRepairTM3 Water Block Jig (back half)The back half of the water block jig (services
tray side) has been sucessfully located onto
the module.
  
  324   Friday, April 26, 2013, 14:31 chad fisherSouth Hot-CellRepairTM3 TM3 refurb E.O.D.Service tray side of the waterblock jig
is installed and all locking tabs enagaed
save the heat shield circuit. Locking tab
 IMG_1039.JPG 
  325   Monday, April 29, 2013, 15:58 Bevan MossSouth Hot-CellRepairTM3 Source Tray RemovalChad removed the source tray from TM3  today,
see attached picture (video was also taken).
There was some interference between the window
 20130429_TM3_SOURCE_TRAY_REMOVAL_IMG_0620.JPG 
  326   Tuesday, April 30, 2013, 07:47 chad fisherSouth Hot-CellRepairTM3 TM3 Source Tray RemovalThe source tray has sucessfully been removed
from TM3.
I will put a report in the TM3 rev
 IMG_1043[1].JPG 
  327   Tuesday, April 30, 2013, 07:51 chad fisherSouth Hot-CellRepairTM3 Coil line flow checkDavid and I checked circuits p and q (the
water cooled coil ciruit) for flow this morning
as, with the source tray still in the module,
  
  328   Thursday, May 02, 2013, 10:09 chad fisherSouth Hot-CellRepairTM3 Service tray water block leak checkDavid and I preformed a helium leak check
on the service tray waterblocks and verify
that no damage had been done during jig installation.
  
  329   Friday, May 03, 2013, 09:53 chad fisherSouth Hot-CellRepairTM3 9 pin connector wiringWith the aid of nic new manipulator snap
fingers made by Maico the peek cable ties
restraining the 9 pin connector wiring to
 IMG_1047[1].JPGIMG_1048[1].JPGIMG_1050[1].JPG 
  330   Monday, May 06, 2013, 15:45 Bevan MossConditioning StationRepairTM3 55 pin connector removedTravis and I removed the 55 pin connector
from the service cap today. The feed through
was left in place as a new design for the
 20130506_55_pin_conector_removal_IMG_3530.JPG20130506_55_pin_conector_removal_IMG_3525.JPG20130506_55_pin_conector_removal_IMG_3532.JPG20130506_55_pin_conector_removal_IMG_3535.JPG 
  332   Wednesday, May 08, 2013, 10:12 chad fisherSouth Hot-CellRepairTM3 TM3 9 pin wiring removalThe 9 pin wiring has successfully been
removed from TM3.
 IMG_1055[1].JPG 
  333   Wednesday, May 08, 2013, 13:48 chad fisherSouth Hot-CellRepairTM3 IMG wiring checkChecks of the wiring for the IMG are complete
and have passed.
  
  335   Thursday, May 09, 2013, 14:23 chad fisherSouth Hot-CellRepairTM3 Water Block Jig RemovalThe source tray side of the water block
jig has been removed in preparation for moving
the module to the  conditioning station
 IMG_1059[1].JPG 
  336   Friday, May 10, 2013, 09:26 chad fisherSouth Hot-CellRepairTM3 Containment box reinstalledthe containment box has been reinstalled
onto TM3. After electrical checks it is ready
to move to the conditioning station...for
 IMG_1062[1].JPGIMG_1063[1].JPG 
  337   Friday, May 10, 2013, 11:02 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target and no source tray
has been moved from the south hot cell to
the conditioning station.
  
  338   Friday, May 10, 2013, 11:11 Travis CaveSouth Hot-CellStandard OperationTM3no targetElectrical checkTM#3 electrical check with no target and
no source tray, see pdf.
 TM#3_elec_chk_no_tgt_no_tray.PDF 
  339   Friday, May 10, 2013, 11:28 Bevan MossConditioning StationStandard OperationTM3No Source TrayRoughing Started Roughing on TM3 was started at 11:26am
today
  
  340   Friday, May 10, 2013, 14:05 Bevan MossConditioning StationStandard OperationTM3No Source TrayTurbo Pumps OnThe turbo pumps are on. TP1 and TP2 once
again timed out and had to be restarted before
they would stay on.
  
  341   Monday, May 13, 2013, 14:59 Bevan MossConditioning StationStandard OperationTM3N/AEL testing

    

       
            
 TM3_EL_39.9kV_23042013.txt 
  342   Monday, May 13, 2013, 15:10 Bevan MossConditioning StationStandard OperationTM3N/AHV Test All common

    

       
            
 TM3_40kV_22042013.xlsx 
  344   Wednesday, May 15, 2013, 10:17 Bevan MossConditioning StationStandard OperationTM3No Source TrayPreliminary Results from HV testing Testing on TM3 without a source tray
was completed on 13/05.2013. All items were
tied to common and the water blocks were
 module_hv_test_0KV.rgaMODULE_hv_test_42kv.rgaTM3_13052013_no_source_tray.xlsx 